Preview

Project Management

Powerful Essays
Open Document
Open Document
2716 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management
Contents Executive Summary 3 Schedule 1 5 Performance Analysis 5 Estimate at Completion 7 Control Plan 7 Revised Estimate at Completion 8 Schedule 2 9 Summary and Conclusions Section 10 References 11

Executive Summary

This document comprises of several sections that are financial analysis of a new Indoor theme park project. The financial analysis of any project is very vital for any project since it gives an opportunity to better understand where on the project the project team is and what is needed to be done to improve the project. For example if based on the analysis it turns out to be that the project is behind the schedule and over the budget as a project manager one needs to inform the stakeholders about it and ask for taking corrective actions. If the project is behind the schedule then some resources may be added to the project so that the project team is capable of catching up with the progress. Or if there is a situation where the project is over budget the stakeholders need to be aware of the reasons and try to mitigate the issue or at least be ready for getting additional funds from different donors and sponsors.
Each section of the executive summery is important and gives a detailed information about how a certain part of the project is doing or how the project looks in terms of Gantt Chart which incorporates the provided project data, established baseline, and proper review date representing the anticipated 50% completion date for the project. When we look at the project Gantt Chart we can see that the baseline finish date is 12/19/2008 and we do not have actual finish date. The baseline start date shows 4/14/2008. The duration of the project is 180 days as well as is the baseline.
Performance Analysis section discusses Earned Value data to analyze the project cost and schedule performance. By Looking at the project plan MPP file the Earned Value (BCWP) is $1,086,640.61 the actual cost is $1,230,683.00



References: F.J. Jüngen, W. K. (July 1995). An intelligent interactive project management support system. European Journal of Operational Research, Volume 84, Issue 1, 7, 60-81. Ildar Batyrshin, T. S. (April 2008). Perception based data mining and decision support system. International Journal of Approximate Reasoning , 1-3. JE Diekmann, H. A.-T. (February 1992). Knowledge-based approach to construction project control. International Journal of Project Management, Volume 10, Issue 1, Pages 23–30. Prasanta Kumar Dey, M. T. (August 1996). Petroleum pipeline construction planning: a conceptual framework. International Journal of Project Management, Volume 14, Issue 4, 231-240. R. Bünde, M. G. (November 2001). Project control of WENDELSTEIN 7-X. Fusion Engineering and Design, 803-808. Wideman, R. M. (1989 May). Successful project control and execution. International Journal of Project Management, Volume 7, Issue 2, 109-113.

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    Burke, R. (2006). Project Management - Planning and Control Techniques (5th ed.). www.burkepublsihing.com: Burke Publishing.…

    • 13536 Words
    • 144 Pages
    Powerful Essays
  • Powerful Essays

    Pm592 Course Project 2

    • 3890 Words
    • 16 Pages

    After entering the data and setting the project to 40% completion, we noticed that the project is behind schedule. This was apparent by the Schedule Variance and the SPI (Schedule Performance Index). The Schedule Variance for the project is ($570,977.84) with a Schedule Variance Percentage of -35%. We also noticed that…

    • 3890 Words
    • 16 Pages
    Powerful Essays
  • Better Essays

    Project Management Institute. (2000). _A Guide to the Project Management Body of Knowledge (4th ed.)._…

    • 1150 Words
    • 6 Pages
    Better Essays
  • Better Essays

    Bus 375 Assignment 1

    • 1282 Words
    • 6 Pages

    References: Kerzner, H. (2010). Project management, a systems approach to planning, scheduling, and controlling. (10 ed.). hoboken, NJ: Wiley.…

    • 1282 Words
    • 6 Pages
    Better Essays
  • Good Essays

    how much ahead or behind schedule the project is. With this information the PM will be able to…

    • 413 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Can Go week 3

    • 321 Words
    • 2 Pages

    2) According to your Project Summary, is this project on schedule? Will you be over or under budget and by how much? From what I have gathered this project is on schedule which show that the start &finish date due match the baseline start and finish time frame. Furthermore, the budget will be over by the mark of $1,720.00.…

    • 321 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Team PMP

    • 3308 Words
    • 9 Pages

    Kerzner, H. (1995). Project Management: A systems approach to planning, Scheduling and controlling. New York: Thomson Ltd.…

    • 3308 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Organizational Structures

    • 820 Words
    • 4 Pages

    Kerzner, H. (2003). Project Management: A Systems Approach to Plan, Scheduling, and Controlling 8th Edition. John Wiley & Sons Inc.…

    • 820 Words
    • 4 Pages
    Good Essays
  • Best Essays

    Corwin Corporation

    • 4432 Words
    • 18 Pages

    Kerzner, H. 2009. Project Management A System Approach to Planning, Scheduling, and Controlling. Tenth Edition. New Jersey: John Wiley & Sons, Inc.…

    • 4432 Words
    • 18 Pages
    Best Essays
  • Powerful Essays

    Chunnel Project

    • 9442 Words
    • 38 Pages

    Kerzner, H. (2003). Project management: A systems approach to planning, scheduling and controlling (8th ed.). New York: John Wiley & Sons.…

    • 9442 Words
    • 38 Pages
    Powerful Essays
  • Better Essays

    Cited: Kerzner, H. (2005). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. New York: Wiley…

    • 1884 Words
    • 8 Pages
    Better Essays
  • Satisfactory Essays

    Project management

    • 603 Words
    • 3 Pages

    B- The team needs to use screening criteria to get rid of projects that need too many…

    • 603 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Project Management

    • 1443 Words
    • 6 Pages

    Time value of money Present value NPV & Discounted cash flow Simple Examples Formulae IRR…

    • 1443 Words
    • 6 Pages
    Good Essays
  • Powerful Essays

    Research over many years in the field of project management has identified several hindrances in the smooth execution of operation a construction project. But here it is more important to find out some common obstacles from the early literature and measure their impact on performance scientifically. Traditionally construction industry is segmented, and this segmentation is depends upon the nature of construction that is to be carried out, and this segmentation widely consider as residential housing construction, institutional and commercial building construction, specialized industrial construction, infrastructure and heavy construction, to see this, Hendrickson’s (2000, ch.1). Hindrances could also depend upon the nature of construction that is to be carried out but mostly it considered that all type of construction project faces common type of problems.…

    • 2315 Words
    • 10 Pages
    Powerful Essays

Related Topics