Preview

Project Management

Good Essays
Open Document
Open Document
836 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management
Djenane Jeanty
Project Management Context
Professor C. Lennon
Module V
11.17.12

Abstract

Project managers carefully manage slack on sensitive resource-limited projects (Larson and Gray, p.295). If possible, they will add slack at the end of the project by committing to a completion date that goes beyond the scheduled date. Eliyahu Goldratt (1997) advocates an alternative approach to managing slack. He championed the “theory of constraints” and has coined the term “critical-chain” recognizing that the project network may be constrained by both resource and technical dependencies (Larson and Gray, p.295).

Projects often can exceed their planned schedule by a certain percentage, sometimes even 50 to 100 percent. Often this is attributed to uncertainty or the unforeseen. Managers and project personnel have learned to compensate to this dilemma by adding additional time to their schedule estimates (Larson and Gray, p.302). Yet even when they do, projects still overrun their schedules. Goldratt (1997) argues that there is a natural tendency for people to add safety time, just in case, to their estimations. One of the key problems identified in this case was the project time estimate. Even when management added 10 percent time to all activities or added 10 percent project estimates to ensure project durations would be met, the issues still remained (Larson and Gray, p.302). Then, Pinyarat explained that the activity durations had gotten squeezed down to less than the 50 percent guideline and that the estimates were impossible. Pinyarat also mentioned that she was allowed to put in a big enough project buffer and other members of the firm had no idea why management would use CCPM scheduling in these projects (Larson and Gray, p.303).
It is believed that project managers who estimate activity times provide an estimate that has about an 80 to 90 percent chance of being completed on or before the estimated time (Larson and Gray, p.295). Using the Critical



References: Erik w. Larson, Clifford F. Gray (2011) Project Management – The Managerial Process 5th ed. Eliyahu Goldratt (1997) Critical Chain (Great Barrington, MA: North River Press). DRM Associates – Critical Chain Project Management from http://www.npdsolutions .com/ critical.html Retrieved 11.17.12

You May Also Find These Documents Helpful

  • Satisfactory Essays

    V. VI. OPMA 317 3. Project Management & Scheduling 3.3 Project Management in Practice   …

    • 5350 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    The project management team should have used several people to estimate the time, costs and resources required for the project. Discussion of the individual differences in their estimate tends to eliminate extreme estimate errors. Reports indicate that several managers advised the BAE Senior Management team that the project was at minimum a four year project, not a two year project. If these voices could be risen up and better discussed, the project would have been treated differently.…

    • 505 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Management

    • 1515 Words
    • 7 Pages

    Construct a Cost-Benefit Analysis matrix for an organization that is considering replacing its internal payroll system with a payroll outsourcing service. Include direct and indirect revenue enhancements and direct and indirect cost reductions.…

    • 1515 Words
    • 7 Pages
    Powerful Essays
  • Powerful Essays

    HKH DFC USM Paper JCEM 2013

    • 9802 Words
    • 51 Pages

    focus on the distributions of the possible errors in the time and cost estimates and on the reliability of the estimates used as planned values…

    • 9802 Words
    • 51 Pages
    Powerful Essays
  • Satisfactory Essays

    Laudon Mis 6ce Ch14

    • 11622 Words
    • 55 Pages

    1) Between 30 and 40 percent of all software projects are "runaway" projects that far exceed original schedule and budget projections.…

    • 11622 Words
    • 55 Pages
    Satisfactory Essays
  • Best Essays

    5DPP Written Report

    • 2399 Words
    • 7 Pages

    ‘Keeping projects on track -- especially in the face of constant change requests and additions -- is a project manager 's greatest challenge. And when project managers don 't properly set expectations from the start -- with senior management, the client or their team -- and don 't have a strategy in place for dealing with scope creep or last-minute requests or changes, deadlines can suffer.’ *1…

    • 2399 Words
    • 7 Pages
    Best Essays
  • Satisfactory Essays

    Project Management

    • 252 Words
    • 2 Pages

    2. Assume that the project is time constrained and try to resolve any over allocation problems by leveling within slack. What happens?…

    • 252 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    5. Lientz, Bennet P. and Kathryn P. Rea (1998). 2nd edition. Project Management for the 21st Century. San Diego, California: Academic Press. (ISBN-10: 012449966X).…

    • 1051 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    References: Larson, E. W., & Gray, C. F. (2011). Project Management (5th ed.). New York, New York: McGraw-Hill Irwin.…

    • 681 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Team PMP

    • 3308 Words
    • 9 Pages

    Kerzner, H. (1995). Project Management: A systems approach to planning, Scheduling and controlling. New York: Thomson Ltd.…

    • 3308 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    1. What is the estimated project completion date? (Assume there are no holidays and ignore the sunk cost of the planning team’s effort)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Best Essays

    Failure of IT projects has plagued the IT industry since the introduction of automated systems into organisations. While failures in software are perhaps one of the more quickly excused reasons, the problem often lies at the project management level.…

    • 3083 Words
    • 13 Pages
    Best Essays
  • Good Essays

    * Time spent on project activities is approximately 370 minutes including going over project reports and preparing for weekly status meeting (25m), Progress review meeting (45m), Reviewing project assignment with Victoria (30m), listening to teammates (20m), Discussing problem with John (30m), negotiating with purchasing agent (30m), Conference call (60m), negotiating with Mary (40m), reviewing the impact the client’s requests (30m), Reviewing e-mails and project documents (30m), and Working with “what-if” scenarios (30m).…

    • 861 Words
    • 4 Pages
    Good Essays
  • Better Essays

    The Mythical Man-Month (Brooks, 1995) is a collection of lessons the author learned during his experience working on a large software project. One of the very first errors he suggests is considering a program as a programming software product, without realizing that a programming software product is nine times more expensive than a simple program. Brooks (1995) then addresses the common failure to deliver software projects on time. The reasons he gives to explain this problem are manifold. Mainly, it is due to excessive optimism in the estimation and poorly allocated time for planning and testing—with too much time scheduled to code, and not enough to plan and test the software. There are two other errors that are arguably even more captivating. One being that an estimation in man-months cannot be simply multiplied or divided by the men or the months, but rather a more complex analysis must be carried out to understand whether the work can be partitioned among the software engineers and how much communication is needed between the engineers. Specifically, when a task cannot be partitioned, then…

    • 1719 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    Critical Path

    • 8065 Words
    • 33 Pages

    1. Introduction Construction projects generally have highly complicated situations during execution, involve many project stakeholders and interfaces, and are influenced by many external factors. Therefore, schedule delays in construction projects are common and affect total project duration in unpredictable ways. Delay information and evidence are usually recorded and represented in different records,…

    • 8065 Words
    • 33 Pages
    Powerful Essays

Related Topics