Preview

Project Crashing Using Cpm

Powerful Essays
Open Document
Open Document
1143 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Crashing Using Cpm
Scamoail Ahmed - Project Mgmt assignment no 2
Q No 1 : What is meant by Project Crashing? How you incorporate Project Crashing through PERT-CPM?

Definition
1. Project Crashing is a technique / process by which a project can be expedited by compressing the project schedule.
Explanation
2. When we say that a project completion time is XX days, we generally mean that the project will normally takes these number of days within a specified resource / budget constraint. We could make it take less time , but to do so we will have to increase our budget or resources or a combination of both.
3. We can however reallocate resources from one facet of the project and use it to speed up an activity that is lagging behind OR we can all together allocate new resources to our ACTIVITIES IN CRITICAL PATH. However care must be taken that, if the resources should always be withdrawn from activities that have more SLACK . In Short for project crashing we have to concentrate our efforts on THE CRIRICAL PATH i.e whatever efforts we have to do in term of time , resources or budget will be done on the critical path and these things have to be taken out either from the non-critical activities having enough SLACK or new allocation should be made.
4. While carrying out project crashing utmost care must be taken that appropriate activities are being crashed and that diverted resources are not causing needless risk and PROJECT SCOPE INTEGRITY

Example (Using PERT / CPM)
Example narrative
5. An aircraft gets damage as a result of ground accident, the damage was analyzed by the maintenance crew and timelines for the repair were analyzed using CPM which came out to be 6 days (8 hrs/ day), however the stake holder needed the repair to be completed in 3 days as the aircraft was needed for a VIP mission. Efforts were made to meet the timelines by working overtime, however still the timelines could not be met. Project crashing was carried out keeping in view the fact that PROJECT

You May Also Find These Documents Helpful

  • Good Essays

    Ops 571 Final

    • 433 Words
    • 2 Pages

    What is the net result of reducing the duration of a task (crashing) not on the critical path?…

    • 433 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Ops/571 Final

    • 549 Words
    • 3 Pages

    11- WHAT IS THE NET RESULT OF REDUCING THE DURATION OF A TASK (CRASHING) NOT ON THE CRITICAL PATH?…

    • 549 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    There are times when it will be necessary to expedite a project’s schedule. The term we use is to “crash” the project schedule.…

    • 2212 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Create a WBS and include dates. Schedule regular meetings to ensure timelines are being met.…

    • 740 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    7) Refer to the figure. Suppose that additional resources are provided to crash the project completion time below its expected normal completion time. Which activities would be potential…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Powerful Essays

    Nhs It Project Report

    • 3047 Words
    • 13 Pages

    In this report, we will look through the stages of the project and figure out how a potentially successful IT project can turn out to be a disastrous failure.…

    • 3047 Words
    • 13 Pages
    Powerful Essays
  • Satisfactory Essays

    Chapter 9 Quiz

    • 609 Words
    • 9 Pages

    Intense global competition and rapid technological advances create pressure on developing projects rapidly. This is an example of reducing project duration caused by:…

    • 609 Words
    • 9 Pages
    Satisfactory Essays
  • Powerful Essays

    CP1 Essay

    • 1082 Words
    • 5 Pages

    Now that your project schedule has been created and your resources have been loaded, it is very important to perform risk management…

    • 1082 Words
    • 5 Pages
    Powerful Essays
  • Powerful Essays

    The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    2. Once the resource leveling is completed, the over allocated resources decrease from 4 to 2. The over allocated problems are design engineer and industrial engineer, with the greatest total slack for detailed marketing plan decreasing. In the end the project task changes in the duration period after resources leveling.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    There was significant misunderstanding of the complexity of this project. Not having a sufficient timeline and accurate planning of all tasks allowed room for the project to go over the timeline because there was no planning for testing and failures. In addition, staff working more than one project at a time and not being solely dedicated showed initiative…

    • 476 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    IT Project Failure Paper

    • 717 Words
    • 3 Pages

    The approach to this paper will be an analysis based on literature review. Data analysis will be completed post-mortem through a mixed research approach. Both inductive and deductive analysis will be completed to develop correlations between IT project failures and causes. Information gathered will come from a variety of sources, researched through university libraries and search engines, such as:…

    • 717 Words
    • 3 Pages
    Good Essays
  • Best Essays

    Failure of IT projects has plagued the IT industry since the introduction of automated systems into organisations. While failures in software are perhaps one of the more quickly excused reasons, the problem often lies at the project management level.…

    • 3083 Words
    • 13 Pages
    Best Essays