PROJ598
PROJ598 – Contract and Procurement Management

Request for Proposal

New Ballfield

The Louisville Sluggers, Inc address phone

name email session
TABLE OF CONTENTS

1. INSTRUCTIONS TO BIDDERS
This will be single source negotiated contract. The instructions to the Contractor are provided below.
1.1. General Description of Work
This work shall deliver is facilities to include the construction of one baseball field that will accommodate a semi-pro baseball team, the construction of one clubhouse, and the construction of one parking area sized to hold 50 cars. A 20-acre parcel of land will be provided for the construction of these facilities, which has already been acquired. The contractor shall be responsible for the demolishing, clearing, removal, and disposal of existing buildings and trees. The site shall be evenly graded to drain away from the playing field. The Contractor shall erect a perimeter fence and security lighting. The Contractor shall be responsible to make utilities operational, to include power, water, and sewer. The Contractor shall be responsible for coordination with the utility companies. Refer to the detailed Description of Work, and Specifications and Drawings, in Sections 2.0 and 4.0, respectively, for details.
1.2. What Must Be Included with Bid
The proposal must include: - Three (3) copies of the Proposal – One (1) original and two (2) copies - All Information requested in Section 3 – Proposal: Breakdown of Bid Price Revisions and Extra Work Escalation Formulas Scheduled Completion Dates List of Subcontractors Key Supplier or Contractor Personnel Length of Time Bid is Valid List of Bid Document Addenda Reviewed by Bidder Notice of Conflicts or Errors in Bid Documents Clarifications of Bids Bidder Signature
1.3. Schedule of Bid Period Activities
The Bid is due by midnight on August 10, 2013,

You May Also Find These Documents Helpful

  • Good Essays

    Siempro Baseball Field is in need of a practice field. The land chosen is approximately 20 acres and has a few structures and trees. The existing water and sewer lines will need to be inspected/connected and the project deadline will be 2 years from project start date. We will be selecting one General Contractor to complete this project. The end result should include an updated field, clubhouse, and parking area to hold about 50 cars. We will need existing plans, specs, and drawings to map out this new renovation. The intent of this document is to provide interested vendors and enable them to submit sufficient information for the project. There will be 2 vital phases to begin this project:…

    • 592 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Is589

    • 325 Words
    • 2 Pages

    #1: Now we need to find out how long does it take to transmit one label over the cell network, assuming that the cell phone network operates at 14 kbps:…

    • 325 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    8 CONSULTANT’S PROPOSED DESIGN & CONSTRUCTION SCHEDULE ........................... 8 CONSULTANT DESIGN SCHEDULE ........................................................................................ 9 BID DOCUMENT CONSTRUCTION SCHEDULE…

    • 13739 Words
    • 88 Pages
    Powerful Essays
  • Satisfactory Essays

    Hr593

    • 709 Words
    • 3 Pages

    * Commissioned sales employees of retail or service establishments are exempt from overtime if more than half of the employee 's earnings come from commissions and the employee averages at least one and one-half times the minimum wage for each hour worked. You may also wish to review the applicable regulation.…

    • 709 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project?…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    − General Projects and other items such as Masterplan, Section 106 constructions, Project insurances and Security associated with the construction phase…

    • 952 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Landscape Procurement Plan

    • 2681 Words
    • 11 Pages

    Following a major renovation and addition to the house, a redesign of the front yard is required. This redesign will encompass the front yard that is approximately 65 ft wide by 70 ft deep. The area is bounded on the south side by the house and a wooden fence, on the west side by a continuation of the wooden fence for approximately 40 feet. The north side is to the property line, and the east side is bound by the driveway. There is a sidewalk that comes away from the house to about 25 feet and turns to the driveway. The area enclosed by the driveway and sidewalk is approximately 350 ft2.…

    • 2681 Words
    • 11 Pages
    Powerful Essays
  • Powerful Essays

    3. Compensation. For Services performed under this Agreement during the Term, Contractor will be compensated at a…

    • 4000 Words
    • 16 Pages
    Powerful Essays
  • Satisfactory Essays

    Your written proposal must not exceed 25 pages in length and include the items below.…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    The contractor, Hill Construction (Bob Hill) was given a 270 days deadline for the project. There will be a contract penalty of $10,000 per day for running late. Hill again reviewed the data and noted that the optimistic time estimates can be used as crash times. He gathered his foremen and told them, “Folks, if we’re not 75% sure we’ll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days— also for 240 days. I want to be early, not just on time!”…

    • 966 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    ARB exam part 1

    • 263 Words
    • 2 Pages

    • Final Plans, Elevation & Sections (A27.4); Accommodating contemporary living, and forming a credible relationship with the surroundings…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    This essay will examine how to best prepare a contract administration plan. The contract administration plan will examine different methods used in preparing a plan. This essay will explain how important it is to have technical and other support of personnel, the importance of surveillance, and to determine what functions need to be delegated, identify qualified personnel as well as authorized, it is necessary for the Contracting officer to be represented in administering contract requirements. Also there will be a discussion on what is determined from the contract administration functions and how they will be delegated.…

    • 1049 Words
    • 5 Pages
    Better Essays
  • Better Essays

    N.B Please ensure that your proposal is word processed, and completed under the appropriate headings…

    • 1110 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    The formal paper will cover sports facility planning and management. Design your own sports facility in terms of what type of activities you want to include. Describe the procedures and policies of the facility and the responsibilities of the manager operating the building. The sports facility planning or management paper can include some of the following subtopics: activities, planning and producing events, membership, financing facilities, ADA requirements, risk management, medical emergency and evacuation plans, concession management, and box office management. Submit an outline for the formal paper. Make sure to discuss and get your topic approved.…

    • 307 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Disinvestment in India

    • 1843 Words
    • 8 Pages

    · Bidders are invited through advertisement in newspapers / website to submit their Expression of Interest. On receiving EOI from bidders, the advisors, after due diligence of the PSU, prepare the information memorandum in consultation with the concerned PSU. This is given to the short listed prospective bidders who have entered into a confidentiality agreement. The list of bidders is prepared after scrutiny of EOIs and those are shortlisted, who meet the prescribed qualification criteria.…

    • 1843 Words
    • 8 Pages
    Powerful Essays