Preview

Proj Mngment

Satisfactory Essays
Open Document
Open Document
345 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Proj Mngment
Discussion 7.1
Class Discussion: Critical Path
Define "critical path."
Critical Path Method (CPM) is the most widely used and popular method used for scheduling a project. The CPM shows the path forward or backward for a project; meaning in shortest or longest time, start and finish time (earliest and latest) and slack time for a project. The CPM also shows the project duration. This is displayed through a project network diagram that shows the relationship between activities. CPM determines and separates critical and non-critical requirements, displays schedule and predicts time (as previously mentioned).
“The critical path is the path (from start to finish) that joins all activities with zero slack” (QSO 640 Module 7)
Discuss why it is so important to the project schedule. How is the critical path determined?
Critical Path is determined through specification of each activity, sequence determination, network diagram, and estimate in completion time for each segment, critical patch identification and CPM updates through project cycle.
How do you manage critical path activities differently from non-critical path activities? What could happen if you focus only on critical path activities and not caring about non-critical activities?
Critical Path activities are managed with ‘no slack’. Meaning, they are scheduled and managed on no extra time for the project activity and setting the earliest possible close date so the next activity can begin. Non-critical path activities do not follow this same model, as we see from the readings. If a critical path activity is not completed within the scheduled time and cause slack, the end activity may also be delayed. This could happen is a non-critical activity is a focus for the project team. This is a trickledown effect for the remainder of the project.
Resources:
QSO 640Module 7: Project Scheduling. SNHU. Retrieved on May 15, 2013 from

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    First Cars Ltd

    • 1031 Words
    • 5 Pages

    Critical path analysis is a method that is used to plan out the many activities involved in a project to be able to find the most efficient way of complete it and how to complete it on time.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Introduction to Project Scheduling IX. The Critical Path Method (CPM) X. Program Evaluation and Review Technique (PERT) XI. Project “Crashing”…

    • 5350 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    The Critical Path is the Shortest Time in which the Project Can Be Completed. Any delay in Critical Path activities delays the project. Critical Path Activities have no slack time Variability in Activity Times: CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a Probability Distribution for Activity Times to allow for Variability.…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    AIB Problem

    • 565 Words
    • 3 Pages

    Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) Answer: 32 days b) What is the Critical Path of the Project? (5 points)…

    • 565 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    5. For visual understanding, the critical path is marked green in the CPM flow for the project schedule below.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    What is a critical path, and why is it important to project managers? How do you…

    • 702 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    2- What is the critical path and how long is the project expected to take?…

    • 294 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Critical Path

    • 1047 Words
    • 5 Pages

    As audit of liquid assets (activity 4) is not on the critical path, it is not a critical activity. This slack job has a slack time of 178 hours for which slack time= late start time – early start time (231-53) = late finish time – early finish time (266-88).…

    • 1047 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is the critical path in the project? How would you assess the level of risk in the project?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Pm Que and Ans

    • 382 Words
    • 2 Pages

    PERT is a Program Evaluation and Review Technique and it is designed to analyze the tasks and time to complete them in the project. Critical path analysis(method) is an algorithm which schedules all the tasks in the project according their time, priority and relationships to each other. By determining activities with total float it…

    • 382 Words
    • 2 Pages
    Satisfactory Essays