Preview

pinto pm2 tif ch12

Satisfactory Essays
Open Document
Open Document
5994 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
pinto pm2 tif ch12
Project Management, 2e (Pinto)
Chapter 12 Resource Management

12.1 True/False

1) There is, for almost all projects, usually a dominant constraint that serves as the final arbiter of project decisions.
Answer: TRUE
Diff: 1
Section: 12.1 The Basics of Resource Constraints
Skill: Definition
AACSB Tag: Reflective

2) In a resource constrained project, the work must be finished by a certain time, or date, as efficiently as possible.
Answer: FALSE
Diff: 1
Section: 12.1 The Basics of Resource Constraints
Skill: Definition
AACSB Tag: Reflective

3) All that is needed to create a resource loading calendar is the work breakdown structure and the activity network.
Answer: FALSE
Diff: 2
Section: 12.2 Resource Loading
Skill: Factual
AACSB Tag: Reflective

4) Because resource management is typically a multivariate, combinatorial problem (i.e., on that is characterized by multiple solutions involving literally dozens, hundreds, or even thousands of activity variables) truly correct answers are not possible.
Answer: FALSE
Diff: 2
Section: 12.3 Resource Leveling
Skill: Definition
AACSB Tag: Reflective

5) A resource loading table is created through identifying the project activities and their resources required to completion and applying this information to the project schedule baseline.
Answer: TRUE
Diff: 2
Section: 12.3 Resource Leveling
Skill: Factual
AACSB Tag: Reflective
6) If resources have been over-allocated, the loading table must be reconfigured to eliminate resource contention points. The project manager can focus solely on the original point of contention since the activities in a project are separate entities.
Answer: FALSE
Diff: 2
Section: 12.3 Resource Leveling
Skill: Conceptual
AACSB Tag: Reflective

7) Resource loading charts are used to display the amount of resources required as a function of time on a graph.
Answer: TRUE
Diff: 2
Section: 12.4 Resource Loading Charts
Skill: Definition
AACSB Tag: Reflective

8) If an activity can

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 6 Paper

    • 579 Words
    • 3 Pages

    Create a project schedule using Microsoft Project. Project schedule will built from and contain the following information:…

    • 579 Words
    • 3 Pages
    Powerful Essays
  • Satisfactory Essays

    Unit 421 Unit 7

    • 686 Words
    • 3 Pages

    of such resource loading and develop a more leveled schedule. This forms your Exercise 2 for this week.…

    • 686 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    A) The triple constraint of project management describes the interdependency between the three cornerstones of a project: 1. Scope - all the work we have to do in order to create the clearly specified product. 2. Schedule - the time we need in order to create that product. 3. Budget - the total amount of money we need in order to create that product. If the scope is increased because of additional features added to the product then the time and amount of money has to increase as well. In order to shorten the time we could reduce the scope and consequently reduce the budget of that project. The time could be shortened as well by involving more resources…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    CIS 348 ASSIGNMENT 1

    • 960 Words
    • 4 Pages

    Describe the different levels and types of resources required for producing each deliverable described in the assignment summary.…

    • 960 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    [Replace this text with a high-level estimate of project team size requirements.] * [Consider the number and type of tasks to be performed, and the total effort required to complete them.]…

    • 885 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    bubbaganoosh

    • 515 Words
    • 3 Pages

    If one of these constraints was to change, then the other two would be immediately influenced. To ensure that these essential constraints do not become detrimental to the project our team must follow similar standards that completed subdivision projects have put in place. Cost and Time will be managed by monitoring project performance closely through an Earned Value Analysis.…

    • 515 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Proj586 Project

    • 2037 Words
    • 9 Pages

    While meeting with your project team, you have worked with them to determine the appropriate sequencing of the activities, and the duration for each activity. The data that you compiled is shown below. Using MS Project, follow the Project Schedule Instructions provided below to build a project schedule for the Huntsville Project by entering the information from the below task list with duration and predecessors.…

    • 2037 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Project Management Theory: What activities in our project schedule are candidates for expediting? Why? Based on what you learned about the triple constraints, what are the effects on scope and budget when we crash a project?…

    • 2212 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    2) Technical constraint -> deal with the actual construction processes that are tasked to complete an activity or assembly.…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Powerful Essays

    Pm592 Course Project 2

    • 3890 Words
    • 16 Pages

    Given the scope of the project by the customer, we took the information and formatted it into a WBS (Work Breakdown Structure) and presented it back for customer buy-in. We developed the WBS using Microsoft Project, breaking it down into more manageable packages and into separate activities to better manage.…

    • 3890 Words
    • 16 Pages
    Powerful Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    1. The activities involved for the project schedule can be represented using Central Path Method (shown below) showing various interdependence and parallelism among activities.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    DA Garden

    • 552 Words
    • 3 Pages

    Project Resource Requirements can be defined as anything that an organisation needs to ensure its effective operation and achieve its goals. Resources allocation systems are made up of various components which collectively achieve the desired goals of the organisation…

    • 552 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Grt Task 1

    • 19334 Words
    • 78 Pages

    Correct Answer: D QUESTION 5 During which of the following process groups is the availability of required resources for the project determined? A. Executing…

    • 19334 Words
    • 78 Pages
    Powerful Essays

Related Topics