Preview

Network Diagram Excercises

Good Essays
Open Document
Open Document
1634 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Network Diagram Excercises
Exercise 1
[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.

Activity
Start C B P A U T R N End

Predecessor
Start Start Start C, B, P P A A U T, R, N

Estimate in weeks 0
6 4 3 7 4 2 3 6 0

. How many paths are in the network, and what are they?

2. What is the critical path and its duration?

3. What is the float on activity U?

4. What is the impact to the project if activity B takes three weeks longer than planned?

Do a forward and backward pass using the original estimates.



Answer to Exercise 1
[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.

Activity
Start C B P A U T R N End

Predecessor
Start Start Start C, B, P P A A U T, R, N

Estimate in weeks 0
6 4 3 7 4 2 3 6 0

C

A

T

Start

B

R

End

P

U

N

. How many paths are in the network, and what are they? There are seven paths. See the details on the next page.

2. What is the critical path and its duration? Start, C, A, R, End 16 WEEKS

3. What is the float on activity U? 3 weeks 4. What is the impact to the project if activity B takes three weeks longer than planned? Critical path shifts to Start, B, A, R, End. It will delay the project end by one week.

Do a forward and backward pass using the original estimates.

2

Answer to Exercise 1
Note: Answers are based on using the zero method. See www.rmcproject.com/free/tips.htm for an explanation of the two methods.

6 C 0 0 0 4 Start 0 2 B 2 3 P 0 3 3 3 6 3 6 4 6 4 U 3 6 6 6 6

7 A 0 13 13 13 14 3 R 13 13 0

2 T 1 15 16

End 16 16

N 7 10 7 10 3 13 16

Legend D ID ES EF S LS LF

Start, C, A, T, End Start, C, A, R, End Start, B, A, T, End Start, B, A, R, End Start, P, A, T, End Start, P, A, R, End Start, P, U, N, End

5 6 3 4 2 3

You May Also Find These Documents Helpful

  • Satisfactory Essays

    The project is pouring a concrete patio in my backyard. The results will be a new patio to entertain guests. I am allowing two additional weeks in case there is inadequate funding or scheduling conflicts for the project ending in May of 2008. The two extra weeks are there in case there is an unexpected expense elsewhere, or I can’t get my brother to my house to help out because of scheduling conflicts. Each activity is defined within a week’s time.…

    • 784 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Nt1330 Unit 3 Assignment 1

    • 5050 Words
    • 21 Pages

    This is a rudimentary diagram representing the basic network that is employed in the Boston College Rochford Campus.…

    • 5050 Words
    • 21 Pages
    Powerful Essays
  • Powerful Essays

    Assignment 4-Bus 517

    • 2043 Words
    • 9 Pages

    1. One of the project team members wants to take a week’s vacation during a major holiday season and at a time when critical project deadlines are imminent.…

    • 2043 Words
    • 9 Pages
    Powerful Essays
  • Satisfactory Essays

    opma 317

    • 395 Words
    • 5 Pages

    Since two weeks were added to task #3 - Obtaining Final Drawings and Building Permits, in order to complete the project in the original normal time with minimal costs, he would crash activities #2, and #1 since these activities would reduce the project by two weeks’ time at a minimal cost of $7000 as shown by our project crashing…

    • 395 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    100 NT2580 Lab01 Final

    • 287 Words
    • 2 Pages

    interfaces. Finally, you used Zenmap to perform a scan of the network and created a network…

    • 287 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Com 135 Week 5 Analysis

    • 678 Words
    • 3 Pages

    Perform an analysis of the current XYZ network, using the current network diagram and nmap report Diagram; NMAP and files are below.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Pre Algebra Final Exam 1

    • 1202 Words
    • 7 Pages

    3. Use the diagram below to answer the following questions. Type your answers below each question.…

    • 1202 Words
    • 7 Pages
    Satisfactory Essays
  • Satisfactory Essays

    PROJ 586 W4 Homework

    • 588 Words
    • 3 Pages

    Use the network diagram below and the additional information provided to answer the corresponding questions. [15 points]…

    • 588 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Week 3 Aib Problems

    • 895 Words
    • 4 Pages

    Once the homework assignment has been graded, the solution key will be made available. The network diagrams will be provided, along with the answers to the questions.…

    • 895 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    network 204

    • 558 Words
    • 3 Pages

    For the simple 3 router network (Figure 1), fill in the information that would be in each router’s routing table once the network has converged (see example in Chapter 4, pages 192-193).…

    • 558 Words
    • 3 Pages
    Powerful Essays
  • Satisfactory Essays

    AIB Simulation

    • 771 Words
    • 4 Pages

    Once the homework assignment has been graded, the solution key will be made available. The network diagrams will be provided, along with the answers to the questions.…

    • 771 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    operation management

    • 252 Words
    • 1 Page

    To conclude, we cut activity T by 2 weeks. The project can be completed in 14 weeks.…

    • 252 Words
    • 1 Page
    Satisfactory Essays
  • Powerful Essays

    psych journal review

    • 2278 Words
    • 10 Pages

    You may work on this assignment ahead of its deadline but may not submit it prior to Week 3.…

    • 2278 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    constrained because a. each of the activities are independent from the c. the activities use different resources to be other activities. completed. b. one activity cannot be started until the d. some activities use the same resources that may predecessors are finished. not be available. ANS: B Feedback A Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. B Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. C Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. D Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. PTS:1 DIF: M OBJ:1. Create a network…

    • 17168 Words
    • 69 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Lan Topologies Assignment

    • 354 Words
    • 2 Pages

    11. Your network consists of four servers. Each server has three NICs. Server A is connected to servers B, C, and D. Server B is attached to C and D. Server C is attached to server D. No hub is used. All cabling is CAT 3 UTP crossover cables. What…

    • 354 Words
    • 2 Pages
    Satisfactory Essays

Related Topics