Natural Blends Inc
Natural Blends Inc

Natural Blends Inc.
(Part A)

Questions – Part A
Assume that the production system was running only one size of oranges. Consider just steps two through four :

Extraction

Filtration

Concentration

Extraction Process : -Time Setup = 20min -Capacity = 20,000lbs/hr

Filtration Process : - Operation time = 90min -Filter Change = 30min -Capacity = 20,000lbs/hr

Concentration Process : -Capacity = 18,000lbs/hr

Question 1a :
How much orange juice concentrate can be produced in one 8-hour workday?
Since we have bottleneck on process 3 (Filtration – with lowest production capacity in total 8hrs) then all process should be following process number 3 with downtime 30min for filter change. So we only can get maximum output from Concentration process is 108,000 lbs = (4 x (18,000+9,000)) = 108,000 lbs

Question 1b :
Assume extraction had previously been setup for the size oranges being processed. How much idle time will there be in the extraction operation during one 8-hour workday?
Process 2 (extraction) should wait and follow the operation time of Process 3 since it should be shutting down for 30min for filter change after operate 90min. Then during 8hr, process 2 have 4 idle times (=8hrs/2hrs) Idle time = 4 x 30min = 120min / 2hrs

Question 2a :
If you could add storage capacity somewhere between steps two and four in this production line in order to increase daily output, where would you place it? How much storage would you add?
We will put 1 storage between process 3 (filtration) and process 4 (concentration) with capacity 3000lbs to accommodate the output from process 3 since the production time and speed is not the same between process 3 and 4.

Question 2b :
Why?

Process 3 after operate for 90min, it can produce 30,000 lbs of orange juice (20,000 lbs/hr) but the process 4 only have production capacity 18,000 lbs/hr and for 90min operation it only can proceed 27,000 lbs meanwhile the total output from

You May Also Find These Documents Helpful

  • Powerful Essays

    Bus 210 Quiz

    • 1385 Words
    • 6 Pages

    Time Elapsed 1 hours, 2 minutes, and 57 seconds out of 1 hours and 30 minutes allowed. Instructions Question 1 A process involves transforming inputs into outputs. Selected Answer: Question 2 Labor productivity is an index of the output per person or hours worked. Selected Answer: Question 3 True True 1 out of 1 points 1 out of 1 points…

    • 1385 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Bus 630 Case Study

    • 392 Words
    • 2 Pages

    To meet the volume of 5,800 hrs: 5,800 hrs needed2,000 hrs per equipment=2.90 or 3 pcs of equipment…

    • 392 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Hilcrest Auto Case

    • 973 Words
    • 3 Pages

    machine takes 0.06 seconds per tube (60 seconds per 1000 tubes). Each of these processes runs…

    • 973 Words
    • 3 Pages
    Better Essays
  • Satisfactory Essays

    Question: B. Determine annual unit sales volume at which Martinez Company would be indifferent between the two manufacturing methods.…

    • 335 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Mat 540 Stateline shipping

    • 1018 Words
    • 5 Pages

    = Number of Barrels transported per week from plant ‘i’ to the j-th waste disposal site,…

    • 1018 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Sst4e Tif 07

    • 7361 Words
    • 28 Pages

    6) A machine is set to pump cleanser into a process at the rate of 5 gallons per minute. Upon inspection, it is…

    • 7361 Words
    • 28 Pages
    Good Essays
  • Good Essays

    National Cranberry

    • 620 Words
    • 3 Pages

    3. Recall the definition of a capacity bottleneck from Module 1. Identify the potential capacity bottleneck(s) in the…

    • 620 Words
    • 3 Pages
    Good Essays
  • Good Essays

    The closing of the plants in Guarulhos caused the Jaboatão plant to increase the production of one-eighth of its production to absorb this shortcoming. Luiz Pinto can basically choose from several solutions to reach a required capacity of 540 units/min:…

    • 1193 Words
    • 5 Pages
    Good Essays
  • Better Essays

    1) Suppose that a peak harvest-season day involves 18,000 barrels of berries, 70% of them wet harvested, arriving uniformly over a twelve-hour period from 7 a.m. to 7 p.m., and process initiates as soon as the first truck arrives.…

    • 1389 Words
    • 6 Pages
    Better Essays
  • Good Essays

    Natural Blends Case Study

    • 898 Words
    • 4 Pages

    Since we also need to replace the filter every 90 minutes which adds another 30 minutes to overall downtime, it makes sense then to try to minimize as much idle time as possible by coordinating when the bin has to be changed at EXTRACTION with the filter change at FILTRATION. In order to meet the processing requirements; each orange size must be processed at least once per day, and all three sizes must be processed equally during the week. If we change the bin (4) times each day with one size twice per day for the 6 days, we can satisfy both requirements. What’s more since we are limiting the total downtime by coordinating each bin change every 90 minutes with every filter change, we maintain the (2) hour downtime with no difference in processing time each week.…

    • 898 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Spmproject File

    • 667 Words
    • 3 Pages

    The maximum achievable throughput rate would be affected by changes in the percentage of dry or wet berries. The throughput would also be affected by the bottleneck for drying berries to be loaded into bulk trucks or bagged. The processing rate of the three separator lines also affected the throughput rate as processing declined as the percentage of bad fruit increased.…

    • 667 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Tomato paste

    • 292 Words
    • 2 Pages

    a) What is the optimal solution, and what are the optimal production quantities? W=1.0 M=1.250 PROFIT=800000…

    • 292 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Sulphuric Acid

    • 1528 Words
    • 7 Pages

    MATERIAL BALANCE GIVEN: TO DESIGN A 1000TPD CAPACITY H2SO4 ACID PLANT BASIS: 1 HOUR OF OPERATION. PURITY: PRODUCT WHICH IS TO BE MANUFACTURED IS ASSUMED TO HAVE STRENGTH OF 98% ACID. 1000TPD implies that we have Acid 1000 x 10 / 24 = 41666.67 Kg/Hr of…

    • 1528 Words
    • 7 Pages
    Good Essays
  • Good Essays

    First objective is to increase the capacity of plant by 50%, as current capacity of plant is around 4500 m3/day. So 50% increment is about 9000 m3/day, which is same as 2035 demand as calculated earlier. Demand of 9000 m3/day can be fulfill buy one Siltbuster HB300R lamella clarifier, which save the significant area of land when compared to conventional horizontal tanks. Volume occupied by the conventional sedimentation would be 10*40*5 = 2000 m3. (Existing) which provide 4500 m3/day. But two such tanks required to cater future demand of 9000 m3/day. But Siltbuster HB300R takes only 6*7.1*3.5 = 150 m3. It’s about 1/10 of area…

    • 884 Words
    • 4 Pages
    Good Essays