Preview

MGT203 CH4

Satisfactory Essays
Open Document
Open Document
723 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
MGT203 CH4
Chapter 4:

Objective Questions

5, 7, 8, 13

5.The following activities are part of a project to be scheduled using CPM:

a. Draw the network.

b. What is the critical path?
A-C-D-E-G, also shown in the network above as the bold path.
c. How many weeks will it take to complete the project?
6+7+2+4+7 = 26 weeks
d. How much slack does activity B have?
Activity B has 6 weeks of slack – the difference between its early and late start times.
7. The R&D department is planning to bid on a large project for the development of a new communications system for commercial planes. The accompanying table shows the activities, times, and sequences required:

a. Draw the network diagram.

Note that G has both D and F as immediate predecessors. However, D is redundant because F also has D as an immediate predecessor.
b. What is the critical path?
A-C-F-G-I, and A-D-F-G-I at 18 weeks.
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?
B is not on a critical path and has slack of 4; therefore, do not shorten as it will not change the project completion time. Shorten C, D, and G one week each. C and D are on parallel critical paths, reducing them both will only reduce project completion time by 1 week.
d. What is the new critical path and earliest completion time?
A-C-F-G-I; and A-D-F-G-I remain the critical paths. Project completion time is reduced from 18 to 16 weeks.
8. The following represents a project that should be scheduled using CPM:

a. Draw the network.

TIMES (DAYS)

ACTIVITY
IMMEDIATE
PREDECESSORS a m b ET

A

1
3
5
3
0.4444
B

1
2
3
2
0.1111
C
A
1
2
3
2
0.1111
D
A
2
3
4
3
0.1111
E
B
3
4
11
5
1.7778
F
C, D
3
4
5
4
0.1111
G
D, E
1
4
6
3.833
0.6944
H
F, G
2
4
5
3.833
0.2500

b. What is the critical path?
B-E-G-H
c. What is the expected project completion time?
2.00+5.00+3.833+3.833 = 14.67
d. What is the probability of

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) b) What is the Critical Path of the Project? (5 points) c) What is the ES for Activity D? (1 points) d) What is the LS for Activity G?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Better Essays

    Mgt 448 Wk 5

    • 1112 Words
    • 5 Pages

    Business continuously expands into global organizations finding it necessary to pay close attention to the foreign exchange market. These companies must follow the foreign exchange market closely and should develop appropriate hedging strategies to protect them. Exchange rate risk is the unexpected exchange rate that may cause an organization to lose or gain income. Currency hedging is a method of minimizing the exchange financial rate risk within an international organization. Global Companies involved in operations should have good understanding of the financial risks that the company could go through prior to starting its venture.…

    • 1112 Words
    • 5 Pages
    Better Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    Our text book mentioned some of the critical success factors when scheduling. Some of these factors are when attempting to reduce the duration of a path activities that has a negative slack, focus on activities that are near term and activities that have long estimated duration, the person who will be responsible for performing the activity should approximate duration for that activity, the key to effective schedule control is address any paths with negative or deteriorating slack values aggressively as soon as they are identified, and activity estimated duration should be yet realistic (Gido & Clements, 5th Ed, pg 180). Based on the factors above, the schedule should be revised to find activities with negative slack and timing interval. For example, recruiting & training, create building design estimated duration time could be adjusted to shorter period. This will cause the earliest start and earliest finish time of other activities around these tasks to be adjusted and hence it might create some positive slack time. The Gantt chat also reveals that during the…

    • 611 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Blood and Edition Answer Key

    • 9679 Words
    • 39 Pages

    D 2. A 3. B 4. D 5. C 6.…

    • 9679 Words
    • 39 Pages
    Satisfactory Essays
  • Satisfactory Essays

    mgt 3830 ch 1-2-3-4-7-8

    • 8346 Words
    • 34 Pages

    1. Strategy today is essentially a detailed plan which every member of the organization must follow to ensure success.…

    • 8346 Words
    • 34 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    Of the five tasks identified, four of these tasks are along our critical path and attribute to 60 weeks or a little more than a year. If we were able to reduce tasks along the critical path by 30% it would provide us an extra 18 weeks or four-and-a-half months to complete the schedule. According to our current schedule we are exceeding our schedule by two-and-a-half months. I am proposing that we reduce all of the aforementioned items by a total of 10% will save us two-and-a-half months on our schedule and should provide adequate time to complete the project in the specified time.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Mgt 445

    • 1045 Words
    • 3 Pages

    In 2010 a week after my birthday the car I ordered finally came in a 2010 Camaro SS. I had the vehicle ship to Hennessey performance in Texas where I had modifications done to the vehicle. On completion the vehicle was putting down 485hp to the rear wheel which is a 150hp over stock power. Eight months with by the vehicle was running hard and great. In January of 2011 the engine starts making a ding sound at high RPMS. This sound was different from the normal knocking sound that lean or poorly tuned engine would make. Being in New Orleans Hennessey performance was not easy to get to so I took the vehicle to the dealership. The service manager drove the vehicle and connected it to the computer and the diagnosis was that everything was fine. A week later after leaving the dealership the engine started shaking and the vehicle was not drive able. The dealership diagnosis the vehicle again and determined that the noise was coming from cracked pistons 2, 4, and 7 scratching the motor walls. My family purchased many vehicles from Banner Chevrolet so I knew I had to negotiate my out of this one. Because of the modifications the vehicle power train warranty would be voided and a new LS3 was 14 thousand dollars to replace.…

    • 1045 Words
    • 3 Pages
    Better Essays
  • Satisfactory Essays

    Chapter 9 Quiz

    • 609 Words
    • 9 Pages

    Intense global competition and rapid technological advances create pressure on developing projects rapidly. This is an example of reducing project duration caused by:…

    • 609 Words
    • 9 Pages
    Satisfactory Essays
  • Powerful Essays

    If the project is shorted to 38 weeks, R.C. Coleman will be able to achieve the goal of 80% completion at 40 weeks. R.C Coleman should crash activities to reduce the expected project completion time to 38 weeks.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Satisfactory Essays

    mgt 426 wk2

    • 616 Words
    • 2 Pages

    Prepare a 700-1,050-word paper assessing the various roles of managers and individuals in the change process.…

    • 616 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    5. The total duration to complete the project changed and actually increased after resource leveling and made the completion later than the original…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Rccoleman

    • 850 Words
    • 4 Pages

    R.C.Coleman sell many types of food products to grocery store and supermarket outlets. The order request for the outlets includes many different types of products from 20 to 50. Warehouse, the R.C.Coleman current operation, they use labors to dispatch the order-picking and have the goods moved to the ware house shipping area. Now, the management decide to automate the operation because of the high cost and ow productivity for labors. After consulting with members of the engineering staff and warehouse management personnel, the director complied a list of activities associated with the project. The optimistic, most probable, and pessimistic times have also been provided for each activity.…

    • 850 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    A. The overwheming joy of completing this achievement is mixed with the uncertiany of what assignment is coming next.…

    • 369 Words
    • 2 Pages
    Satisfactory Essays