Preview

Managing Projects - Vobien Ltd

Best Essays
Open Document
Open Document
3505 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Managing Projects - Vobien Ltd
Table of contents
Task 1
1. The network diagram 3
2. The timing of activities and the total float 3
3. The project duration and the critical path 4
4. Calculation of the finish date 4
5. Delays and early completion and the effects on the duration 4 a) Activity ‘E’ is delayed 1 day 4 b) Activity ‘P’ is delayed 1 day 4 c) Activity ‘Q’ is completed 1 day earlier 5
6. Limitations of the network diagram 5

Task 2
1. Introduction 6
2. IBEK Ltd. 6
3. The Project Manager 7 Introduction 7 Organization form 8 Planning and monitoring 9 The Project life cycle 9 Work Breakdown Structure (WBS) 10 Organization Breakdown Structure (OBS) 10 Critical path analysis (CPA) 11 Cost estimation 11 Managing Risks 12 Closing the project 12 Conclusion 13
Internet sources 14 book sources 14

Task 1

1. The network diagram

My name is John Doe and I am the project manager for the Vobien Ltd. For a better overview I have produced a network diagram, which you can find in the appendix. The whole project has a duration of 50 days.

2. The timing of activities and the total float

The timing of the activities is shown in the diagram in the appendix of this work. Except ‘A’, all activities are proceeding by one or by more activities. ‘A’ is the first activity and therefore the beginning of the project.

Example:
A is followed by B – B is followed by C / D/ E – C / D / E are followed by F.

The activity-on-node diagram gives a lot of information. It shows the EST (earliest start time), the duration of each step, the EFT (earliest finish time), LST (latest start time), the total float, and the LFT (latest finish time).

To determine the total float, it is important to understand the connections between the various nodes. The duration depends on the gap between EFT and LFT.

Example:
To start with node F, we need to complete C / D and E. Node C has a duration of 7 days and a EFT of 14 days – Node D has a duration of 2 days and a EFT of

You May Also Find These Documents Helpful

  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    3) Refer to the figure. What is the slack time, in days, associated with activity E?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    Week 3 Aib Problems

    • 895 Words
    • 4 Pages

    The most critical path is B – D – F – G – I: 32 Days…

    • 895 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Management

    • 6379 Words
    • 26 Pages

    In order to stay competitive with other home improvement chain stores, Acme Home Improvement decided that it would be a wise investment to open their first international store in Mexico. Opening new retail facilities is not a new process for Acme. Since the company began in 1982, Acme Home Improvement has built 125 stores throughout the United States. The new location in Mexico is to follow Acme’s typical 100,000 square foot size, with a 10,000 square foot outdoor garden sales area, as well as a two story parking garage are what is outlined to be constructed. Work on this project is scheduled to begin January 3, 2011, with a budget of $18 million.…

    • 6379 Words
    • 26 Pages
    Powerful Essays
  • Powerful Essays

    Project Management

    • 1515 Words
    • 7 Pages

    Construct a Cost-Benefit Analysis matrix for an organization that is considering replacing its internal payroll system with a payroll outsourcing service. Include direct and indirect revenue enhancements and direct and indirect cost reductions.…

    • 1515 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Operation Management Case

    • 435 Words
    • 2 Pages

    1. The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:…

    • 435 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Management

    • 2565 Words
    • 9 Pages

    - Project stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion. They may also exert influence over the project's objectives and outcomes.…

    • 2565 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Project Management

    • 2439 Words
    • 10 Pages

    b) What phase is the Project Scope produced? What are some of the items contained in this document?…

    • 2439 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Project Management

    • 1620 Words
    • 7 Pages

    A _______________ is a temporary endeavor undertaken to create a unique product, service, or result.…

    • 1620 Words
    • 7 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Project Management

    • 305 Words
    • 2 Pages

    1. If I were in Lauren’s shoes, I would make sure it’s clear to the strategic management group that my estimate – a more detail/micro estimate – came in well over their initial macro estimate. That being said, I would also provide upper management with the ideas (outsourcing, change scope, cancel project..) developed with stakeholders in the brainstorming meeting. Simply moving forward with the project after finding such a large gap in estimates would be a terrible idea that would most likely to back fire. It’s important that the executives understand major differences or flaws in the project plan.…

    • 305 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Among the set of activities interconnected on the diagram; there is always one longest duration path from start to end of the project travelling through the network, Carmichael D. (2006, p.51). This longest path is also known as a critical path driving the project duration and all tasks falling on this path are called critical activities. Any delay which occurs on these critical activities will delay the project completion time as well. The critical path analysis is carried out in three steps. The first step consists of forward pass which calculates the early schedule (earliest start time and earliest finish time of a task).…

    • 1125 Words
    • 5 Pages
    Better Essays
  • Good Essays

    List the Activities that are on the Critical Path and fill in all columns in the table below (add rows as needed): (4 pts)…

    • 846 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    This number was then divided by the total number of minutes that is took to get to the final measurement (25 minutes).…

    • 477 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Construct the CPM network described by the following set of activities, compute the length of each path in the network, and indicate the critical path.…

    • 590 Words
    • 7 Pages
    Satisfactory Essays

Related Topics