Preview

Little Field Simulation Case

Satisfactory Essays
Open Document
Open Document
441 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Little Field Simulation Case
Operations 202
Little Field Simulation Report Little Field Simulation Game is mainly about the inventory management and optimization problems which are occurring in a factory. Since the last report, we tried to generate more profit and took some actions to beat our competitors in market. Firstly, we examined our demand and completed job counts to check our productive capacity and inventory. It demonstrated that we were producing faster than our capacity and market had increasing level. Therefore; we decided to change our reorder quantity and reorder point in order to produce more at the same time and meet the demand. Secondly, we analyzed our stations’ efficiency and utilization to optimize our productivity process. So that, we demanded more machine for station two to lower our production time and meet the terms of contract in limited days. Furthermore, we seek time delay between the stations and we convinced that station two’s main focus should be on the productions that coming from station one, besides we were in the better production contract level. Our recent contract was limiting our delivery time for three days for 750$. We were excess our demand for shorter durations; therefore; we decided to improve our contract which was limiting our delivery time for one day worth $1000. Towards the last days, we realized that focus change operation on station two turned down a mistake and we began to lose production productivity which caused by excessive supply from station three. Therefore, station two’s utilization became insufficient and we started to delay our deliveries which caused loss by contract. Reacting lately on the situation, we lost big amount of money and changed our station two’s main focus to a balanced level between board stuffing and tuning. Lately, we couldn’t generate more profit than our competitors and we reacted lately towards situations. Also, we find out that changes in delivery time cost us more than what we generated from

You May Also Find These Documents Helpful

  • Satisfactory Essays

    When the balance was achieved on the process, then we started to intervene contracts since contract 3 provides the best profitability when the Lab is able to accomplish a promised lead time of 0.5 days being careful of change to contract 2 or 1 if the promised lead time would not be accomplished due to the circumstantial conditions of the process. To optimize the profitability of the jobs received on the first day of every week, we began to modify the contracts according to the following criteria:…

    • 855 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Aren’t We Done Yet?

    • 675 Words
    • 3 Pages

    LabCo has entered into a contract with a customer, Halibut, to build a six-axis laser cutting machine that will be used by Halibut to cut airplane wings for a new fighter jet that will be sold by Halibut to a large government buyer. The contract entered into was for a fixed price and requires detailed and involved performance specifications. Upon entering into the contract, LabCo realized that this was a unique arrangement that required a great deal of customer specification in order to meet required performance standards. However, LabCo also…

    • 675 Words
    • 3 Pages
    Good Essays
  • Good Essays

    ECO 550 FINAL EXAM

    • 1177 Words
    • 4 Pages

    7. A plant manager is attempting to determine the production schedule of various products to maximize profit. Assume that a machine hour constraint is binding. If the original amount of machine hours available is 200 minutes., and the range of feasibility is from 130 minutes to 340 minutes, providing two additional machine hours will result in the:…

    • 1177 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Case Study

    • 254 Words
    • 2 Pages

    In this case, LabCo make contract entered into was for a fixed price and requires detailed and involved performance specifications. Upon entering into the contract, LabCo realized that this was a unique arrangement that required a great deal of customer specification in order to meet required performance standards. In practical, LobCo had experienced significant difficulties in the design and manufacture of the six-axis laser cutting machine. And their overall project would incur total costs that would be in excess of the total fixed-fee contract price negotiated with Halibut. Thus, they should make a change on setting contract revenue and total contract cost. Contract cost can be increased due to specifically charged to the…

    • 254 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Computer-Image’s proposal comes with a contract of 3 years which can be cancelled but with a 45 day warning before cancelling however by not outsourcing they will not need any kind of legal contract because everything done in the firm is internal. The cost with them will be $265 cheaper than the cost per chasses with insourcing, it would only cost $225 compared to $490. The number of chasses that can be produced per year is also more favorable with their outsourcing option. They can get from a minimum of 1000 chasses to 2500 maximum which is perfect considering that they expect a demand for 1250 and they can still keep expanding their market share to double in the time that this contract is valid however they cannot drop below 1250 chasses. Internally they do not have a minimum limit and maximum of 2000 which they can’t exceed which limits growth more than their outsourcing option, and adding that minimum could motivate the employees to reach higher targets and result in growth. The cost for Computer Image to do the designing is higher than TFC’s by $100,000 because it will be $300,000 but this is an extra cost that’s worth paying since this company is a professional company and there will be less room for error and with them doing it TFC’s employees can focus on meeting the higher demand and providing better customer service. This company will also be using advanced technology…

    • 543 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Littlefield Case Study

    • 875 Words
    • 4 Pages

    At this point, our team should have reevaluated our decisions, and purchased a new machine for Station 1, in order to get production moving faster to Station 2. As our utilization was remaining at a constant 100%, our lead times were also increasing. With full utilization, we were unable to produce enough product to meet our order demands, further increasing the queues at each station and increasing our lead times (as shown).…

    • 875 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Little field

    • 1749 Words
    • 7 Pages

    Management’s main concern is managing the capacity of the factory in response to the complex demand pattern. Delays resulting from insufficient capacity undermine LT’s promised lead times and ultimately force LT to turn away orders. In particular, if an order’s lead time exceeds the quoted lead time, then the revenue for that order decreases linearly, from $1000 for the quoted lead time (24 hours) to $0 for the maximum lead time (72 hours).…

    • 1749 Words
    • 7 Pages
    Better Essays
  • Better Essays

    With the MPS on hand it is clear that Realco will indeed meet their customer’s requirements based on the production available to include the promised shipments in 3 weeks. On the 8th week however, they will have a surplus of inventory. Mr. Chang the owner stated that the ending inventory of 51,650 units was too high and should be used as a Reorder Point (ROP) to indicate that there is a problem with overproducing. Fortunately Realco has not overpromised since they are able to meet their customer’s demands with the excess inventory. This does indicate that production numbers need to be readjusted to accommodate consumer demand.…

    • 2134 Words
    • 9 Pages
    Better Essays
  • Satisfactory Essays

    The Goal

    • 371 Words
    • 2 Pages

    Rogo improved the factory’s throughput rate and decreased excess inventory by rearranging the order in which the products were assembled (i.e. moved Q.C. inspection points first) and by improving the efficiency of the bottlenecks and non-bottlenecks. Moreover, he cut the batch size dramatically,…

    • 371 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Capsim Strategy

    • 869 Words
    • 4 Pages

    In order for our strategy to be effective, our optimal timing for planned investments will be when demand is predicted to be high. Hence, we will increase our capacity levels where demand is forecasted to peak. According to the…

    • 869 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Custom Molds, Inc

    • 428 Words
    • 2 Pages

    Although the number of parts orders remained virtually constant, the volume per order for parts has increased significantly during last 3 years. These, has created bottlenecks and has led to late deliveries of parts.…

    • 428 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    NoBugs

    • 589 Words
    • 2 Pages

    Sterling, Inc. had gained a high reputation in the market by establishing a strategic business relationship with NoBugs Corporation. Its state-of-the-art computer manufacturing business has been highly supported by the high quality microchips of the NoBugs. As NoBugs was the only supplier who was able to meet with the Sterling’s high specifications, thus both of the companies remain in contract for more than ten years. Mutually agreed business terms proved to be rewarding for both of them, where each has earned revenue with attractive rate of return. Sterling Inc. and NoBugs Corporation, both has agreed to enter into contract, on mutually beneficial business terms, where NoBugs was responsible for providing high quality microchips, with no defects and Sterling, Inc. would help NoBugs in achieving high business growth.…

    • 589 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Hi-Ho, YO-Yo, Inc.

    • 1985 Words
    • 11 Pages

    Sequencing is worried with determining the order in which jobs are administered. The orders also needs to be determined for handling jobs at work center and for work handled at each person’s work stations. The condition can become difficult when workers centers are heavily overloaded and long-lasting jobs are involved. However, in this case study, the main problem is to report how to meet the limitation such as delays, due dates, and to pleasing the customers so the orders will increase. The corporation experienced a delay because of the make-up day for flooding in the month of June so the production date of the order will move to July. So in the month of July, it is indicated in the given case that there are three Saturdays (July 9th, 16th, and 23rd) and the labors will continue to work. Also they will have one holiday on July 4th apart from the weekends. From the time allowed how will the operation manger choose the best scheduling from the given methods (First Come, First Serve (FCFS), Shortest Processing Time (SPT), Earliest Due Date (EDD), and Critical Ratio (CR) methods.…

    • 1985 Words
    • 11 Pages
    Good Essays
  • Good Essays

    The new car manufactured may not provide the organization with competitive advantage as other companies are also using innovation into their business model for improving the functions of the car. The project manager will have to identify the over allocation of the budget so that extra cost can be reduced. The time span of the project is high all the deadlines have to be followed for timely delivery of the project. The manufacturing and assembly is a critical phase and no time schedule and resource allocation changes can be made to that…

    • 795 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    TOPSIM Report

    • 1289 Words
    • 4 Pages

    During the first period the price established for P1M1 was 2500 and the number of sold units was 15000. However, the production costs were greater than the price per unit, respectively 3428 EUR/unit. The board decided to dismiss 100 employees and to invest 1,5 mil EUR in maintenance and 1,5 mil EUR in environment. Moreover, the team decided to make a loan of 25 mil EUR in order to invest it later in production.…

    • 1289 Words
    • 4 Pages
    Powerful Essays