Preview

Leatty Shanghai: A Construction Project

Satisfactory Essays
Open Document
Open Document
533 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Leatty Shanghai: A Construction Project
Case Study Report Assessment – Background Case Study

Leatty Shanghai: A Construction Project

Background
There is a building boom in residential, commercial and institutional buildings all over China. The country is currently using 54 per cent of the world’s production of concrete and 36 per cent of its supply of steel. Predictions suggest that this building boom will continue for at least the next 20 years.

Leatty, a major property developer, has already been involved in several projects in China. The company’s latest project, in Shanghai, aims to create a new generation of buildings based on low energy consumption, comfort and environmental protection using the most advanced technologies in the world. The project includes a three-phase housing development, as well as a shopping and leisure centre. The team is multinational, with the developer based in Canada, the architects in Germany and the multinational team of structural engineers and contractors in Shanghai.

The completion of the first phase was due 12 months after the start date. The team are now nine months into the work, and conservative estimates suggest that the project is 16 per cent over budget and two months behind schedule. A new project manager has been called in to rescue the troubled project.

Construction Phase One Milestones
Dates
Demolition and site- preparation start date
Nov 1
Building excavation start date
Dec 15
Foundations completion
Feb 9
Underground parking complete
Mar6
Phase 1 external steel structure complete
June26

The World Clock Meeting Planner:
Toronto
Berlin
Shanghai
Mon 12:00
Mon 18:00
Tuesday 00:00
Mon 15:00
Mon 21:00
Tue 3:00

Report
DELAYS TO THE CONSTRUCTION PHASE
The following information has been collected by the company to try and detect the major causes of the delay that the Leatty Shanghai building project is currently facing:

Summary of Findings

Redesign
Initial work was delayed by design reviews on the part of

You May Also Find These Documents Helpful

  • Powerful Essays

    Balfour Beatty Construction is a commercial construction company that was formulated in 1933. The headquarter of the company is in Dallas, Texas and service office in U.S. the parent company of the Balfour Beatty Construction is Balfour Beatty which is a London based group. The group is a world class construction, services and engineering organization. The competitive and strategic position of the company can be assessed by the management tools including SWOT and PESTLE analysis. The expertise of the Balfour Beatty varies from equipping, designing, manning, management and construction of the buildings. The basic aim of the company is to expand its business at global level. There are more than 20 operating companies working under the group name Balfour Beatty.…

    • 2114 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Project Management

    • 6379 Words
    • 26 Pages

    In order to stay competitive with other home improvement chain stores, Acme Home Improvement decided that it would be a wise investment to open their first international store in Mexico. Opening new retail facilities is not a new process for Acme. Since the company began in 1982, Acme Home Improvement has built 125 stores throughout the United States. The new location in Mexico is to follow Acme’s typical 100,000 square foot size, with a 10,000 square foot outdoor garden sales area, as well as a two story parking garage are what is outlined to be constructed. Work on this project is scheduled to begin January 3, 2011, with a budget of $18 million.…

    • 6379 Words
    • 26 Pages
    Powerful Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    1. The project is estimated to be completed in 260 working days. The project starts on January 2nd, 2015 and ends on January 8th, 2016.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    The phases deination/scope and consultant supplier section were completed by the second week of the project. 5% complete…

    • 606 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    My partners and I have made a list of areas that might cause the project delays or failure with their respective outcomes. We have listed the risk below that can prevent the project to finish on time.…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Better Essays

    Senior Management

    • 1685 Words
    • 7 Pages

    6) Lack of project ownership from the senior management team – It was only Frank Carau and Ben Walker, who are juniors that are handling the project. It does not have enough clout to direct and influence the project on the senior management levels. However, with the leadership and sponsorship of Phil Faraci, the project came into a turn-around from being a slow-paced to fast-paced project, from being a…

    • 1685 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    Unicon

    • 1982 Words
    • 8 Pages

    Mr. Li has an opportunity with Unicon to direct it in a new focused direction. With its competitive advantage it has established with the Hong Kong Housing Authority (HKHA). I recommend pursuing the blanket approval process with HKHA. These efficiencies could prove beneficial for both parties as this will greatly reduce lead time and costs. Façade and slabs is the growing trend in the industry and will allow Unicon to take advantage of the cost savings that come with it.…

    • 1982 Words
    • 8 Pages
    Powerful Essays
  • Powerful Essays

    Proj 592 - CP3

    • 1453 Words
    • 11 Pages

    Looking at the table above, we can conclude that the project is on budget and may not need much corrective actions. The MS Project predicts that the Budget at completion at $4,453,480, which is a little more than the planned $4,449,920. There might be some cost overruns in the future due to the schedule delay. This could affect the project’s Budget at completion. The current calculation of under budget is misleading the next table (Schedule Performance) shows the project…

    • 1453 Words
    • 11 Pages
    Powerful Essays
  • Satisfactory Essays

    The aim of this proposal is to wake awareness about a major problem which has been happening in front of our eyes for some time now. As the years go by there are more and more old-fashioned and classical buildings which are demolished for different intentions and corporate companies.…

    • 267 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    In modern day, overcrowding is once again the issue with many redevelopments happening in London, especially at Royal Docks. The developers are turning once again towards the high-rise buildings with some construction works already started. Furthermore, a recent report revealed that around 70 high-rise buildings are under construction and nearly 200 more planned in London. The construction boom would have a significant impact on capital’s skyline. Once again the opinion is split. Some argue this is the only solution to deal with housing crisis by increasing the density in central London, however, critics argue that the tower blocks are being built for foreign investors and not for ordinary Londoners who face rise in rent and house prices. In…

    • 727 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Landscape Procurement Plan

    • 2681 Words
    • 11 Pages

    | Limited experience on a Bobcat. More cost effective to hire the work out. Landscape companies routinely perform this type of work…

    • 2681 Words
    • 11 Pages
    Powerful Essays
  • Satisfactory Essays

    Jabwood

    • 856 Words
    • 3 Pages

    Expanding operations to China has its perks. China has a very large population and is one of the biggest construction markets in the world. It is also one of the few countries to survive the global financial crisis. Although, many Chinese are hesitant to build with wood because…

    • 856 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Blue Zuma Part 2

    • 310 Words
    • 2 Pages

    Once the changes are in place, the duration of the project has been reduced from 290 days to 274 days. This improvement has reduced the overall length of the project, thus allowing the deadline set by the Mr. Lane (President). We are confident we can now complete the project by January 27.…

    • 310 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    The Chunnel Tunnel project was initiated to connect via a tunnel France and England. It was among the biggest privately funded infrastructure projects ever. Fifty kilometres long, the tunnel extended under the English Channel from France to England. It required the collaboration of two very different government entities, with very different policies. The tunnel was designed and built by Trans Manche Link a private group and financed by Eurotunnel a combination of French and British investors. The project required the teamwork of variety of stakeholders from two different government entities, many contractors and investors, international lending banks, and various regulatory commissions. Furthermore the project itself required engineers to approach the task that up to that point was unprecedented in its feat…

    • 3155 Words
    • 9 Pages
    Powerful Essays
  • Satisfactory Essays

    Industrial and Infrastructure activity is at the core of any nation’s economic activity. On it depends the density & economic prosperity of its citizens.In a changing advanced pace of developments happening across the world, a country can ill afford to ignore industrial, commercial & residential construction is a barometer of economic growth and the pace at which Gross Domestic Product (GDP) is expanding.…

    • 498 Words
    • 2 Pages
    Satisfactory Essays