Preview

Johor Coastal Development Sdn. Bhd V Costrajaya Case Study

Powerful Essays
Open Document
Open Document
1176 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Johor Coastal Development Sdn. Bhd V Costrajaya Case Study
Delays of the project may lead the employer to suffer in hardship, expense, or loss of revenue. Thus, the employer may claim against the contractor a delay to the works or a defect in the works. In this case, when delays occur, the employer may have the right to claim the LAD to recover his losses such as the loss of income, the cost of alternate facilities, increased financing cost, extended overhead costs, and loss profits. Normally these claims would make under the LAD clause to reimbursement of actual damages because these costs are difficult to measure.

2.4.1.1 Liquidated and Ascertained Damages
LAD is predetermined prior to the execution of the contract. The exact amount of the LAD is specified in the contract. It is a sum of money
…show more content…
Bhd. v Costrajaya Sdn. Bhd. (2009) 4 CLJ 569, the court derived the principle that the LAD clause, which contains ambiguities and uncertain variables could not be challenged in the court. As the summary, it can be seen that the court will apply its fairness for matters which damages can be …show more content…
There are two ways the contractor may challenge the assessment of the LAD clause by the employer. First, the contractor may attack the propriety of the assessment by disclaiming responsibility for the delay. The contractor must show that the delays to the project were excusable delays or it is concurrent delays. Therefore, the contractor only can be granted relief from the assessment of the LAD. Second, the contractor may claim that the specified amount of the LAD is excessive and, consequently acts as more of a penalty than a damages compensation. According to the construction Contract Law in the United States, the penalties in a construction Contract are not enforceable. If it is found that the amount specified was too high, it may be judges as a penalty and not a LAD. Thus, the LAD clause would not be enforceable. In this case, when the contractor challenges the amount of LAD, the employer must substantiate the validity of the damages. And also shows that the amount of the LAD during the time it was prepared was

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Twbn/123 Week 4

    • 321 Words
    • 2 Pages

    However, LU has written the following on their communications “For the avoidance of doubt approval does not mean it is agreed that the sub-contractor or sub-consultant are not part of the Working Area Overhead percentage or the Fee percentage”. In specific respect to the agreement of Defined Cost and with reference to Clause 52.1, the last limb of the above Project Manager's statement all but renders the approval from the Project Manager without effect. The above issue was raised on CONC8062 issued 26/10/2017 which LU responded to on the 24/11/2017 (With a 1 day delay) with the following comment “The inclusion of the statement referred to was to give continuity to the wording in the CONC 5543 response as such; no other intent should be interpreted.”, which we consider to be unsatisfactory and to not address the issue…

    • 321 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Wright, we have a situation where implied terms can be involved. What makes this case implied is because we are dealing with a modern contract that allows certain situations of the contract to be somewhat flexible. In this case, Cerdes is suing Wright for breach of contract. Cerdes did not finish the job in enough time that was suitable for Wright. Therefore Wright proceeded to hire other service to complete the job. Due to the fact that time was the purpose of the change in contractors, implied terms can be enforced. The length of time that should be assumed in this case if not stated in the contract should be based on the job and how long it should typically take for a construction of a house. You would be able to determine this by an average number of homes that size being built. If the Cerdes is discovered to have taken too much time, then he should not be awarded the full amount of the…

    • 605 Words
    • 3 Pages
    Good Essays
  • Good Essays

    ABC Inc. Case Study

    • 620 Words
    • 3 Pages

    Employee will be in breach of contract if documentation is not obtained within 5 days of due date. Leaving ABC Inc. not liable for any future payments.…

    • 620 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Law 531 Memorandum

    • 981 Words
    • 4 Pages

    This memo is in response to the dispute over the contract between Span Systems and Citizen-Schwarz AG (C-S). Management is taking the necessary steps in resolving the issues C-S is reporting of low quality deliverables and schedule delays. C-S is threatening rescission of their contract and demand immediate transfer of all unfinished codes (University of Phoenix, 2002, Legal Environment of Business: Contract Creation and Management, Law 531). C-S must prove a material breach is occurring and give adequate notice to Span Systems to issue a rescission (Cheeseman, 2010). Span Systems and C-S signed a one-year contract worth $6 million dollars that has five clauses for breach of contract and a project structure clause. This memo will identify what management is doing to avoid legal risks, minimize liabilities, and benefit from opportunities presented to make this contract successful.…

    • 981 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Essay

    • 1594 Words
    • 7 Pages

    The construction must start on January 14, 2004 and must be completed within fifteen months. Liquidated damages (penalty clause) of $250,000 per calendar day of delay beyond March 31, 2005 is written into the contract. On the other hand, Ace will receive an Early Completion Bonus of $100,000 per day for each workday the project is completed before March 31, 2005.…

    • 1594 Words
    • 7 Pages
    Powerful Essays
  • Better Essays

    Food Mart

    • 1515 Words
    • 7 Pages

    Both the business environment and the private sector use contracts as a means for agreement regarding transactions. For any contract to be legally binding four requirements must be met: 1) agreement, 2) consideration, 3) contractual capacity, and 4) lawful object (Cheeseman, 2010, p. 162). After the four requirements are met, it is the responsibility of each party involved to complete their respective obligations. Unfortunately, not all contracts will see completion. Events that arise in the course of the completion of the contract can cause breaches. Other times, one party in the contract fails in his or her obligation because of negligence. When contractual obligations cannot be fulfilled the injured party has certain rights to recover damages or force performance. In this paper the subject to address are situations that have arisen in various contractual scenarios. Based upon the contents of the contracts and causes of the contractual breaches, each scenario will address possible defenses and determine which party will win the suit along with potential remedies.…

    • 1515 Words
    • 7 Pages
    Better Essays
  • Good Essays

    ISSUE: Whether delay of the crane delivery entitled Cut Above to withhold any money from payment. Whether delay of the crane delivery entitled Cut Above to damages.…

    • 474 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Natural Blends

    • 556 Words
    • 3 Pages

    Project Management Case Assignment - Use Microsoft Project to analyze this case. This is an example of a construction project. The construction for a large corporate building must be started by February 15th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. The details of the project activities are as follows – The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared. The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins. Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 15th, 2010 which is a Monday and that you work five days a week for 8 hours every day. Analyze the following questions based on the estimates of the above activities 1) When do you complete the project?…

    • 556 Words
    • 3 Pages
    Good Essays
  • Good Essays

    At any time during the of the project, but not later than 15 calendar days following the date of the second notification, the contractor will submit to the engineer claims for additional compensation or additional combination of compensation and contract time to the specified contract. For claims to be considered the contractor must submit an executive summary; copies of contract specification that support the contractor’s claim, theory of entitlement, itemized list of claim amounts, additional contract time request, and actual expense…

    • 556 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Termination for Cause

    • 324 Words
    • 2 Pages

    1) If the project has slipped into delays from which the contractor can make no reasonable recovery, and those delays significantly impact the project.…

    • 324 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    After completion of the Contract Creation and Management simulation the following legal issues were noted. There were problems with this contract from the beginning because the specifics of the contract were ambiguous from the start. The companies involved developed a contractual relationship by evidence of an offer, acceptance of the offer and valid and legal consideration, which in this case is money for services rendered. However, the deliveries were behind schedule, and the quality of the work was not acceptable by C-S, who was now considering rescission of the contract.” Rescission is an act to undo a contract.” (Cheeseman, 2010 pg. 254). C-S is considering rescission due to material breach of the contract by Span. On Span’s side of the contract, the original requirements that had been given to them had been changed; this in turn had increased the cost and the time needed to do the job. This makes it possible for Span to make a claim for Breach of Contract under substantial performance of contract against C-S.…

    • 1211 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Project Mgmt HW 4

    • 556 Words
    • 2 Pages

    Yes my previous answer would change. The current state of the program was that it projected cash flow problems. Knowing this and giving additional money to the contractor due to an assumption is really risky. If the program had the money available did there would be no need to take on such a risk.…

    • 556 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Workers' Compensation

    • 2198 Words
    • 9 Pages

    Hancher, D.E., de la Garza, J.M., & Eckert, G.K. Improving workers ' compensation management in construction. J. of Constr. Engrg. and Management. 123(3), 285-290. 1997…

    • 2198 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Self defence

    • 12925 Words
    • 52 Pages

    Lowery, Jack, “A Statutory study of self-defence and defence of others as an excuse for homicide”, University of Florida Law Review, Vol. V (1952), p. 58.…

    • 12925 Words
    • 52 Pages
    Powerful Essays
  • Powerful Essays

    In implementation of data's indicate that majority of the construction works suffered with an extended delay that lead to the major disputes lots of time and money, and the end user can not use the intended projects on the appropriate time. And in several instances the dalliance is not the intention for both the client and contractor as it does not help both, either in the performance or in the cash flow.…

    • 17613 Words
    • 71 Pages
    Powerful Essays