Preview

International Ratail

Satisfactory Essays
Open Document
Open Document
678 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
International Ratail
[pic]

Faculty of Business and Law

The assignment of project management

Task 1

(591 words)

Name: Wenhua CAI
Tutor: Mr. Micheal Cassop-Thompson
Student number: 129057794
Submit Date: 7th January 2013
Contents

Pages
1 The network diagram 2
2 The timing of activities and the total flat. 2
3 The project duration and the critical path. 2
4 The Duration of Project 2
5 Activity B, P and O delay reasons 3
6 The limitations of Network diagrams. 3
7 Reference 4
8 Appendix 1.0 5

1. The network diagram

‘A network diagram is originally a flow chart that includes all of the project events and relation of each activity.’ (Rick A. Morris)

The network diagram (Appendix 1.0) has been drawn out accordingly to the table for Mangeist Ltd for present activities and timetable it takes to customer forklift trucks for its customers.

2. The timing of activities and the total flat.

Activity A to activity Q go through the network diagram (Appendix 1) are using forward and backward. From earliest start time (ES) and earliest finish time (EF) that called a forward pass. The backward pass is start from right to left which uses the activity latest start time (LS), latest finish time (LF) and total float (TF). At the same time, duration is provided in the activity data.

3. The project duration and the critical path.

This project of duration uses 88 days for completion, which is using LST to add up together with the duration of the activity. Critical paths generally have two kinds, which are zero and negative total float. So the project critical paths are activity A→D→G→H→I→K→L→M→N→P→Q. The zero float showed in the activities are indicate as the critical path or critical activities.

4. The Duration of Project

If the project begins on 7th January 2013(Monday), even as the project duration is 88 days and assuming there are no holidays and using a 5 day working

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 3 Assignment 1

    • 5050 Words
    • 21 Pages

    This is a rudimentary diagram representing the basic network that is employed in the Boston College Rochford Campus.…

    • 5050 Words
    • 21 Pages
    Powerful Essays
  • Good Essays

    Along with the skills and experience listed when describing Network Analyst, the Network Designer chosen to be a part of the network analysis team must also possess expert level knowledge and experience using network design and documentation tools in order to produce the documents and graphics necessary to satisfy the service request requirements. In the event upgrading and improving the existing network is not feasible, the Network Designer will be expected to document and provide a cost study of the network topology and infrastructure necessary for Kudler Fine Foods to address current, future, and even unanticipated technology and business requirements. The Network Designer will function as a peer of the technical resources associated with the analysis project and will report directly to the project…

    • 899 Words
    • 4 Pages
    Good Essays
  • Best Essays

    One of the most convenient and practical ways to represent a project in form of a diagram is using Project Network Diagram (PND). Heldman (2011) defines PND as a graphical view of a certain project, showing its activities (dependent and independent) along with their timing and the sequence they will be performed.…

    • 3462 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    LF – EF or LST – EST Activities on the critical path have zero slack/float. b. What is the Scheduled Completion of the Project? 22 Days c. What is the Critical Path of the Project?…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Critical path analysis identifies the most efficient and cost effective way of completing a complex project. The various activities which together will make up the project are identified, and the order of these activities are identified. Then, the duration of each activity is estimated and these factors are then arranged as a network or graph, showing the whole project from start to finish, and showing which tasks can happen at the same time. The sequence of tasks which have to be done one after another with no gaps in between is called the Critical Path.…

    • 711 Words
    • 3 Pages
    Good Essays
  • Good Essays

    The network diagram display logical relationships among the various activities that take place within a project. It also allows the project manager to see how the various activities flow towards to…

    • 576 Words
    • 3 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    27. The following project is at the end of its sixth week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.…

    • 371 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    In special interest in network analysis is the average or expected time for each activity and the variance of each activity time. The expected time of analysis is a weighted average of the three estimates:…

    • 1126 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Word ARAPU 1 2

    • 323 Words
    • 2 Pages

    So the throughput time is about 10 days of working which is 2 weeks of the working process.…

    • 323 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    PSP Exam Questions

    • 5269 Words
    • 31 Pages

    C difference in float value of the critical path activities and the float value of the specific activity…

    • 5269 Words
    • 31 Pages
    Good Essays
  • Satisfactory Essays

    Case Study

    • 3127 Words
    • 13 Pages

    1. • Use the resources provided, diagram and narrative, to set up the physical network…

    • 3127 Words
    • 13 Pages
    Satisfactory Essays
  • Good Essays

    critical path

    • 543 Words
    • 3 Pages

    The minimum time in which a project can be completed is the total time taken across the critical path.…

    • 543 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    3. Network Diagramming: A network diagram is drawn using the activity sequence data showing the sequence of serial and parallel activities.…

    • 530 Words
    • 6 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The critical path can be visually observed from the Gantt chart by looking at the red activities…

    • 297 Words
    • 2 Pages
    Satisfactory Essays