Preview

IEEE-30 Bus Case Study

Good Essays
Open Document
Open Document
912 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
IEEE-30 Bus Case Study
The IEEE-30 bus system is used throughout this work to describe the proposed approach. It consists of six generating units, 41 transmission lines, 4 tap changing transformers and two VAR sources. The generator, bus, line, cost and emission data of the IEEE-30 bus system is taken from [27]. The one line diagram of this system is shown in Figure 5.1. The detailed system parameters are presented in the Appendix Tables A.1.Throughout all cases, the IEEE-30 bus system base MVA has assumed to be 100 MVA.
Load flow analysis of system consists of determination of magnitude and phase angle of voltage at each bus and active and reactive power flow in each line. Four quantities are associated with each bus. These are voltage magnitude V, phase angle,
…show more content…
The results obtained for congestion management are given in Figure 5.13.For no congestion condition under Hour-ahead schedule, the total tax imputed to the generators is Rs 0.6224/hr.
Table 5.13 Incremental and Decremental cost Bids
Generator
no. Incremental Cost
(Rs/MWh) Decremental cost
(Rs/MWh)
1 1620.44 1530.41
2 1710.46 1575.43
3 1845.5 1800.49
4 1800.49 1710.46
5 1800.49 1710.46
6 1800.49 1710.46

Figure 5.13 Congestion management cost under Hour-ahead
…show more content…
6. CONCLUSION
The operational aspects of power systems pose some of the most challenging problems encountered in the restructuring of the electric power industry. In this report we looked at one such problem. This work focuses on congestion management in day-ahead and hour-ahead markets in a deregulated electricity market scenario. The Preventive and Corrective approach is used in day-ahead and hour-ahead markets respectively to create a mechanism that enables the market players to compete, trade and simultaneously ensures that the system operation stays within security constraints.
This paper work has significantly accomplished many attainments in the area under discussion which is rescheduling the generations of Schedule Coordinators which are adjusted from the preferred schedules to relieve congestion.
The various achievements can be summarized as follows:
➢ To relieve congestion, Preventive and Corrective approach provides the preferred schedules of generations of the corresponding scheduling coordinators, so that no system constraints violates.
➢ Calculates the optimum generation pattern as well as all control variables in order

You May Also Find These Documents Helpful

  • Better Essays

    D1 Unit 4 Essay

    • 1719 Words
    • 7 Pages

    Qu6. Analyse the need for selecting the different voltages used for different parts of the generation, transmission and distribution systems drawn for Qu.5.…

    • 1719 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    There are times when it will be necessary to expedite a project’s schedule. The term we use is to “crash” the project schedule.…

    • 2212 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    BUS 323 Final Project

    • 2516 Words
    • 7 Pages

    The UFV School of Business has recently learned that high school student advisors are telling…

    • 2516 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Special occasions and emergencies like freak storms also pose problems in improvising and fixing broken schedules to maintain smooth traffic flow.…

    • 470 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Memorial Hospital

    • 328 Words
    • 1 Page

    Other way is to sequence the workforce on the priority basis. First come first serve basis. This method of scheduling the job gives the customer satisfaction can utilize the resource fully.…

    • 328 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    Southwest Airlines

    • 775 Words
    • 4 Pages

    Chapter 13 is titled “Scheduling Operations” and it is mainly about scheduling decisions for batch operations and how they deal with the allocation of scarce resources to jobs, activities, tasks, or customers. “Scheduling results in a time-phased plan, or schedule, of activities. The schedule indicates what is to be done, when, by whom, and with what equipment. Scheduling should be clearly differentiated from aggregate planning” (Schroeder, pg. 293).…

    • 775 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    | Objective of clearly meeting the time and costs deadline once decided by all and exception should be allowed with clear new deadline in presence of all.…

    • 543 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Eco/539 Week 4

    • 764 Words
    • 4 Pages

    Chapter 15 – Discussion Question #12, page 610: What are the advantages to finite capacity scheduling? By providing the scheduler with interactive computing and graphic output.…

    • 764 Words
    • 4 Pages
    Good Essays
  • Good Essays

    If the shift start times stay as it is, and the processing divisions start four hours after the receiving division, the truckers toward the end of the day will have to wait, since the cumulative backlog caused by processing will exhaust the bin storage capacity. The wait times for the truckers can be reduced by converting some of the dry bins to wet bins. However, this measure will not completely eliminate the trucker wait times.…

    • 1665 Words
    • 7 Pages
    Good Essays
  • Better Essays

    Hi-Ho Yo-Yo, Inc

    • 1077 Words
    • 5 Pages

    This process of scheduling is used for completion of work within the due date. This method emphasizes on processing with the job which takes the least time. The division of the work is done on the basis of input, processing time and the the due date for the completion of assignment. The flow time is calculated for the each part of the job, using the processing time, which helps us in determination of the overall time for the completion of work. This method is useful in single machine environment (Hochbaum, 1999).…

    • 1077 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    Power Line Efficiency

    • 6803 Words
    • 28 Pages

    I would like to thank Jason Burch and Myron Rummel for their help and support throughout the duration of the study. Jason’s help proved to be critical in overcoming some of the complex technical challenges associated with the data calculations and solutions. I would also like to thank Dr. James Barnes for his help in developing the project and organizing the report.…

    • 6803 Words
    • 28 Pages
    Powerful Essays
  • Satisfactory Essays

    -Resource scheduling will reduce the flexibility because the scheduling system will reduce slack in increasing the number of critical and near-critical activities.…

    • 332 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Workers can arrange their own starting and stopping hours before and after the core period.…

    • 1964 Words
    • 8 Pages
    Good Essays
  • Powerful Essays

    it varies. To meet the requirement of variable load , economically and also for assuring continuity of supply the number of generating units connected to a system busbar are varied suitably . The connection of an incoming alternator to system bus, ie; synchronization requires fulfillment of the condition like the same phase sequence equality of voltages and frequency between the incoming machine and frequency between the in coming machine and busbar. In order to order to overcome the 9 technical drawbacks of the conventional synchronization methods we can introduce a microprocessor based system. 2.…

    • 2650 Words
    • 11 Pages
    Powerful Essays
  • Good Essays

    To deracinate this problem, the government has set aside an approximate amount of $2 billion to replace old and deteriorating parts in all major rail lines as well as rail operators. On top of that, the government has decided to introduce new rail lines which includes the Downtown line and Thomson line so as to make rail transport faster and more adequate to host larger amounts of commuters in the future. Other strategies such as promoting flexible working hour and the use of telecommunication has surfaced. The Minster of transport, Mr Liu Tuck Yew, came up with a campaign which promotes commuters to shift their travel timings away from that of the peak-hour. With the presence of the Flexi-time policy , it allows staff of the workforce to determine when they will work, this would allow employees to adopt their work hours to public transport schedules. Thus this will move a substantial amount of people away from travelling during peak hours, this effectively reduces peak-hour congestion. Sub-centers are now in operation, giving people the ability to live near where they work and work near where they play.…

    • 426 Words
    • 2 Pages
    Good Essays