Preview

Hrm/531 Week 4

Good Essays
Open Document
Open Document
643 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Hrm/531 Week 4
This assignment is based on an Earned Value analysis performed by a cost account manager, who has received a variance report (given below) from a performance measurement system. I have calculated the appropriate variances and included corrective measures for each of them.

REPORT

Variances are calculated as follows:

CV (cost variance) = BCWP – ACWP
SV (schedule variance) = BCWP - BCWS

TASK A B C D E
ACWP $22,550 $32,000 $16,000 $10,000 $23,000
BCWP $25,000 $30,000 $15,000 $17,000 $24,000
Cost Variance $2,450 -$2,000 -$1,000 $7000 $1000
BCWS $30,000 $40,000 $16,000 $15,000 $40,000
BCWP $25,000 $30,000 $15,000 $17,000 $24,000
Schedule Variance -$5,000 -$10,000 -$1,000 $2,000 -$16,000 A positive cost variance indicates that
…show more content…
This means that we are very close to following the budget. One good way of improving costs for would be cutting down the peripheral tools required in the process and sharing them. It does not hit performance very hard.

Schedule Variance of C – This time, we have a small –ve SV of $1000. We can improve this situation by better explanation of the task to the worker so that he/she spends more time doing the work rather than understanding it.

Cost Variance of D - We have a huge +ve CV of $7000. No action plan is necessary.

Schedule Variance of D – We have +ve SV of $2000. Hence we are on schedule and no plan is necessary.

Cost Variance of E - We have a +ve CV of $1000. Hence, once again, we are moving with the budget and no plan is necessary.

Schedule Variance of E – We have a huge –ve SV of $16000 but a +ve CV. Although we are in budget, we are not getting work done well. The best way is to either improve the scheduling because no manager can create a poor schedule or increased motivation for the workers to get more work done. We can also improve the scenario by efficient scheduling of existing tools required to complete the task among the workers so that tools do not remain idle for a long period of

You May Also Find These Documents Helpful

  • Powerful Essays

    Shuzworld Analysis

    • 5851 Words
    • 19 Pages

    A. Workflow: Shuzworld produces Rugged Wear Work Boots at its Shanghai production facility using an 8-step process and an assembly line of 8 workstations. Each workstation performs a single task that can range from 3 minutes to 10 minutes to complete, resulting in a total time of 46 minutes to fully assemble one pair of steel-tipped work boots. The facility has a budget to produce 6 work boots an hour, with a 40-hour work week (48 work boots a day). The following table shows the task schedule, along with the time required for each task and predecessor information to complete the 8-step process. The graph shows the current layout of the 8 workstations in the production line:…

    • 5851 Words
    • 19 Pages
    Powerful Essays
  • Powerful Essays

    Work must be allocated taking into account the availability of resources and the skills of employees.…

    • 3829 Words
    • 13 Pages
    Powerful Essays
  • Satisfactory Essays

    Can Go week 3

    • 321 Words
    • 2 Pages

    VAC: Which would be the Variance at completion/ the difference of the budget and the estimated cost at completion VAC= BAC-EAC $1090.35…

    • 321 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Minnetonka Receiving

    • 687 Words
    • 3 Pages

    A manager of a warehouse in Minnetonka MN is analyzing the number of workers allocated to the receiving dock. The trucks arrive randomly at the average rate of four per hour with a deviation of plus or minus one. Two warehouse workers can unload five trucks per hour or one every twelve minutes. Each warehouse worker receives $14 per hour. The firm put in place a greater amount of associates to the receiving dock in order to deal with the challenging matter on the inbound freight.…

    • 687 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    By discussing the different posts and figures in the investment plans we have formed a report taking in consideration the different aspects of the two projects. A file in Excel was created to be able to change numbers and do new calculations to find out how NPV…

    • 3482 Words
    • 14 Pages
    Powerful Essays
  • Satisfactory Essays

    Woolworths Media Plan

    • 1046 Words
    • 5 Pages

    For $500,000 of actual cost is very high. To achieve this objective should use less budget.…

    • 1046 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    I have run this simulation for several times, each time I have to face some trade-off. If I want to gain full or even extra points from target scope part, which indicates more man-hour to input and heavier workload, I have to assign more upper-level workers to participate into the project, which means, of course, more cost. What’s more, since I do not want to change the target schedule, I have to encourage workers to work overtime and push them hard and these actions will definitely reduce my point in morale part.…

    • 461 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Wescott case study

    • 475 Words
    • 11 Pages

    To solve the problem in Model D & E, the lot size must be minimized to meet the standard working hours or shift them into Model B & C.…

    • 475 Words
    • 11 Pages
    Satisfactory Essays
  • Satisfactory Essays

    mgt 250

    • 550 Words
    • 3 Pages

    Assignments MGT250. Project Management MGT 250. Project Management Course Assignments Assignment 1  Bottom-up cost estimating exercise (Module 3, pp 19-20)  Parametric cost estimate exercise (Module 3, pp. 43-44)…

    • 550 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Cost Variance

    • 660 Words
    • 3 Pages

    Schedule Variance (SV) is a measurement of the schedule performance for a project, and is calculated by subtracting the Planned Value (PV) from Earned Value (EV). EV is the actual value earned in the project, and PV is the value the project schedule tool indicates should have been earned at the measurement point. Subtracting PV from EV provides a measurement to…

    • 660 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Your job is to allocate workers to tasks each week during the project. Planners ‘R Us has agreed to complete the project in 10 weeks (finishing two weeks before the Festival), and wants to minimize the costs associated with the project. All tasks A-K must be completed in 10 weeks. You have four (4) workers, although you do not need to use all of them every week – there are other tasks they can do in your company.…

    • 1009 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    26. A project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?…

    • 371 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Danshui Plant No.2

    • 1991 Words
    • 8 Pages

    The plant has had difficulty hiring enough workers despite raising wages to 35%. In addition, the process of assembling is complex and required almost entirely based on handwork by 325 workers, with 140 steps involving 100 components during 5 days. The DANSHUI controller considers preparing a “flexible budget” whether it is more useful to help them identify the misinterpreting their performance. Li also must analyze the currently static budget have been used and prepare a summary of monthly operations to identify what goes wrong in their operations that contribute to the performance problems.…

    • 1991 Words
    • 8 Pages
    Better Essays
  • Better Essays

    Production departments will be charged for actual labor hours worked at a predetermined standard rate for the type of work required. The parts and supplies used will be charged to the production departments at cost. The assistant controller believes that only two documents will be required in this new system—a Repair/Maintenance Service Request initiated by the production departments and a Repair/Maintenance Work Order initiated by the…

    • 1140 Words
    • 4 Pages
    Better Essays
  • Good Essays

    and thereby establishing BLHPTASK for each task. The Budgeted labor hours could be done based on companies past experience/practice or using an industrial standard.…

    • 745 Words
    • 3 Pages
    Good Essays