hard rock
1. The Critical Path with no slack time is A-B-D-E-F-G-O. The project would take a total of 34 weeks ending at activity O.
2. The Activities with slack time of 8 weeks or more are C, K, L, M, N, Q, R, V, W, Y, and Z.
3. 5 challenges are project manager could potentially face:
1) Being overrun with too many people trying to enter or sneak into the venue.
2) Sudden rise in prices for multiple activities for example sponsors, contracts, etc.
3) Having enough security for crowd control.
4) Late arriving problems such as employee dropouts or cancelled contracts.
5) Having constant communication with all employees in charge of certain sites.
4. A work breakdown structure is useful in organizing and planning event coordination. It allows you to put activities in order of importance and shows what is needed for each task.
(Level 1) Rockfest Concert
1.1.(A) Site finalization and building contract.
(Level 2) (B)Selecting Promoter
B.1.(D) Web design (Level 3)
B.2.(E) T.V. Deal (Level 3)
B.3.(F) Hire director (Level 3) F.1.(G) Plan for TV camera placement
B.4.(H) Headline Entertainers (Level 3) H.1.(I) Target support entertainers I.1.(J) Travel accommodations for talent
B.5.(P) Travel Accommodations for Staff (Level 3)
B.6.(Q) Hire Sponsor coordinator (Level 3) Q.1.(R) Finalize Sponsors R.1.(S) Define/place signage for sponsors
B.7.(Y) Secure Merchandise deals (Level 3) Y.1.(Z) Online merchandise sales
(Level 2) (C) Hiring Production Manager C.1.(K) Set venue capacity (Level 3) K.1.(L) Ticketmaster contract L.1.(M) On-site ticketing C.2.(N) Sound and Staging (Level 3)
(Level 2) (T) Hiring Operations Manager T.1.(U) Develop site plan (Level 3) U.1.(X) Power, plumbing, AC, toilet services T.2(V) Hire Security director (Level 3) V.1.(W) Set policy/fire security plan

You May Also Find These Documents Helpful

  • Satisfactory Essays

    What is the slack time (float) for activity A? (1 points) d) What is the slack time (float) for activity D? (1 points) e) What is the slack time (float) for activity E?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Plant

    • 654 Words
    • 3 Pages

    A Work Breakdown Structure can be the key to assurance that the employees will know what task that they are responsible for completing.…

    • 654 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    Of the five tasks identified, four of these tasks are along our critical path and attribute to 60 weeks or a little more than a year. If we were able to reduce tasks along the critical path by 30% it would provide us an extra 18 weeks or four-and-a-half months to complete the schedule. According to our current schedule we are exceeding our schedule by two-and-a-half months. I am proposing that we reduce all of the aforementioned items by a total of 10% will save us two-and-a-half months on our schedule and should provide adequate time to complete the project in the specified time.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Best Essays

    Project Management Plan

    • 2196 Words
    • 8 Pages

    The work breakdown structure is breakdown of the hardware, services, and data that is required to help produce the finish product or service. It will show how the work will be performed and will reflect in project costs and data will be reported. (Kerzner, 2013) The purpose of the work breakdown structure for this scenario will provide all the executives with internet access smartphones. The company has decided to expand the program to all their employees that have cell phones or laptops in the hope to save them money.…

    • 2196 Words
    • 8 Pages
    Best Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    3. The activity that has the greatest amount of slack is Detailed Marketing Plan, of 179 days.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Work Package

    • 351 Words
    • 2 Pages

    In my opinion, the activities should be divided into different levels. We should try to pick the most important activities and try to avoid the less-important ones. Put the feasible activities on the list and delete the impractical ones.…

    • 351 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    4. The critical path for the project is found by calculating slack as per CPM as shown in the table below. The activities marked in green forms the critical path, I e.,…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    D.U Singer Hospital

    • 5200 Words
    • 21 Pages

    activity begins at its early start, regardless of resource constraints. ..................................... 8 vi. A period labor requirements table for each group and the project as a whole. Include…

    • 5200 Words
    • 21 Pages
    Good Essays
  • Good Essays

    calsberge case study

    • 1110 Words
    • 5 Pages

    B1 is 3 weeks. A2 ( the required time is 5weeks) must be following these…

    • 1110 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    TOPIC: Use the VALUE CHAIN as a framework and the data from the case to analyze the relative strengths and weakness of HSC?…

    • 1438 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    Information regarding the organisation, 4P’s of marketing, and consumer preferences has been obtained through :…

    • 12620 Words
    • 51 Pages
    Powerful Essays
  • Satisfactory Essays

    Final Project

    • 14681 Words
    • 67 Pages

    India is the largest consumer and second largest producer of sugar in the word. The Indian sugar industry is the second largest agro-industry located in the rural India. The Indian sugar industry has a turnover of Rs. 500 billion per annum and it contributes almost Rs. 22.5 billion per annum to the central and state exchequer as taxes and duty every year.…

    • 14681 Words
    • 67 Pages
    Satisfactory Essays
  • Powerful Essays

    Hard Rock

    • 2787 Words
    • 12 Pages

    El presente documento incluye el análisis del caso de la empresa Hard Rock Café Panamá, como parte de las asignaciones del curso Dirección de la Producción. En el mismo se aplicó la metodología de estudio de caso y el uso del esquema racional.…

    • 2787 Words
    • 12 Pages
    Powerful Essays

Related Topics