Preview

Gantt Chart Analysis

Powerful Essays
Open Document
Open Document
1192 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Gantt Chart Analysis
Introduction
I have been assigned the job of creating a project schedule for the construction of a new hotel complex in Preston Town Centre; it is next to a major roundabout in the town centre which is less than half a mile away from the local train station and bus station. As planning permission has been approved, work will begin shortly on constructing the complex.
I have been given a list of all the major tasks that are included in building the complex as well as the duration of each task and an approximate cost of each job, as per standard I will be charging £50 a hour to create the schedule which will include a Gantt Chart, a critical path analysis and a cost analysis for the construction.
Discussion of schedule of projects
The project that I am scheduling will take a lot of time to complete due to the size of the said project, according to the duration of each task that I have been provided with, the project will take at least sixteen months to complete as none of the tasks can be attempted until the tasks previous to it have been completed successfully.
Due to the time that it will take to complete the assignment, I have created a large Gantt chart to compensate the full amount of time it will take to finish construction. I have discovered that all of the tasks rely on the tasks previous to them as it is a building site. For example the construction team cannot pour concrete into the holes for support until the holes have been created or the clearance of the site of all the rubble after the site was cleared.
This have affected my ideas on how the project would be approached, as the site will be busy doing each task as they are rather large to complete, that they cannot be started until the previous tasks have been successfully completed as it would cause too much confusion and workers having to work on multiple tasks simultaneously.

Discussion Of Costing Of Projects
A major part of project management is the cost of completing the project. The

You May Also Find These Documents Helpful

  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Admn232 Assignment 1

    • 993 Words
    • 4 Pages

    Goals in planning involve completing the project on time and under budget, with a high quality of workmanship. Determining and organizing available resources involves preparing contracts for sub-contractors and choosing a site superintendent. Daily correspondence with the site superintendent facilitates the controlling function. Leadership is displayed through clear communication regarding what needs to be done, and encouragement when expectations are exceeded.…

    • 993 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    The project staff analysed with basis in a series of factors like training staff, adequate to legislative requirements, measuring risks, availability of the budget and quality standards to set a timeline. Once every step is scheduled, the whole staff can work with a estimated and real parameter of timeline.…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Satisfactory Essays

    Is305 Project 1

    • 2310 Words
    • 10 Pages

    The project is divided into three major deliverables and four smaller assignments as detailed below:…

    • 2310 Words
    • 10 Pages
    Satisfactory Essays
  • Satisfactory Essays

    gap analysis. You should include tasks, resources, cost estimates, and time estimates in the project plan.…

    • 313 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Gantt Chart

    • 448 Words
    • 2 Pages

    1 |Fabrication |John |2/11/08 |4/11/08 |60 |20% |12 |48 | |1.1 |Spindle shaft | |2/11/08 |2/25/08 |14 |100% |14 |0 | |1.2 |housing | |2/25/08 |3/07/08 |11 |0% |0 |11 | |1.3 |housing end caps | |2/25/08 |3/07/08 |11 |0% |0 |11 | |1.4 |cross-feed flexure | |3/17/08 |4/01/08 |15 |0% |0 |15 | |1.5 |lead screw flexure | |3/17/08 |4/11/08 |25 |0% |0 |25 | |2 |Error model task |Jane |2/11/08 |5/14/08 |93 |0% |0 |93 | |2.1 |list of spindle error sources | |2/11/08 |2/25/08 |14 |0% |0 |14 | |2.2 |model individual spindle errors | |2/11/08 |3/10/08 |28 |0% |0 |28 | |2.3 |finish full spindle error sources | |2/11/08 |5/14/08 |93 |0% |0 |93 | |2.4 |list of flexure error sources | |3/03/08 |3/17/08 |14 |0% |0 |14 | |2.1 |model individual flexure errors | |3/03/08 |3/17/08 |14 |0% |0 |14 | |2.2 |finish full flexure error model | |3/10/08 |4/07/08 |28 |0% |0 |28 | |2.3 |list of drive error sources | |3/31/08 |4/07/08 |7 |0% |0 |7 | |2.4 |model individual drive error | |3/31/08 |4/28/08 |28 |0% |0 |28 | |2.5 |finish full drive error model | |3/31/08 |4/28/08 |28 |0% |0 |28 | |2.6 |HTM-based lathe error model | |2/11/08 |5/14/08 |93 |0% |0 |93 | |3 |Measurement task dates |Bill |3/07/08 |4/28/08 |52 |0% |0 |52 | |3.1 |CMM training | |3/07/08 |3/21/08 |14 |0% |0 |14 | |3.2 |Spindle error motions | |3/07/08 |3/17/08 |10 |0% |0 |10 | |3.3 |Cross Slide error motions | |3/19/08 |4/07/08 |19 |0% |0 |19 | |3.4 |Carriage error motions | |4/07/08 |4/28/08 |21 |0% |0 |21 | |4 |Report results and Conclusions |Bill |2/11/08 |4/28/08 |93 |0% |0 |93 | |4.1 |Outline (text, table & figure placeholders) | |3/31/08 |4/07/08 |7 |0% |0 |7 | |4.2 |images | |2/11/08 |4/30/08 |79 |0% |0 |79 | |4.3 |tables | |3/10/08 |4/30/08 |51 |0% |0 |51 | |4.4 |1st draft in separate modules | |4/07/08 |4/30/08 |23 |0% |0 |23 | |4.5 |integrated, final draft | |2/28/08 |5/14/08 |76 |0% |0 |76 | |4.6 |design notebooks | |2/11/08 |5/14/08 |93 |0% |0 |93 |…

    • 448 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Using the workplace scenario information provided, you will determine the scope of a project and develop a portfolio of draft planning documentation to discuss with your Operations General Manager (the assessor). You will then negotiate aspects of the project with your assigned project team. Finally, you will submit final planning documentation for approval.…

    • 910 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Gantt Chart Ko

    • 459 Words
    • 2 Pages

    Problem: A manufacturer of cable TV systems wanted to provide a system that would allow a utility company to be able to read the power meters and control the power consumption (load control) using their cable plant as the communications medium. The system would communicate to a given house through the CATV system and then be sent to the client devices using the home power lines so that no additional wiring would be required.…

    • 459 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Task estimation is considered as a random variable. Therefore estimating duration of task is an informed or educated guess based on past experience of similar tasks. For complex project, it is very difficult to estimate task duration. Therefore, to make a meaningful task duration estimates, some basic information is essential. This information includes scope document, work breakdown structure (WBS), associated risk, task list, task details, and task dependencies. Schedule risks and the critical path are also essential.…

    • 1407 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    Project Cost Management

    • 1638 Words
    • 7 Pages

    Estimating costs developing an approximation or estimate of the costs of the resources needed to complete a project…

    • 1638 Words
    • 7 Pages
    Good Essays
  • Good Essays

    One of the key successes to most projects is in the planning preparation. It is important to establish the key members of the site team as soon as possible and then establish them on to the site. As much time as possible should be allowed for planning and preparation with the team on site. Planning includes various parts such as the completion of the network diagram, cash flow and labour preparation.…

    • 2711 Words
    • 11 Pages
    Good Essays
  • Better Essays

    Gantt Chart

    • 1650 Words
    • 7 Pages

    A Gantt chart lists tasks or phases of a project from top to bottom and has time running from left to right. Each task has a start date and duration (or end date). Planned tasks are usually drawn as open bars, which are filled in as the work is done. Alternatively separate filled in bars can be drawn below the open bars to more clearly show how the tasks are proceeding in relation to their planned schedule. Additionally, a Gantt chart may show the resources required for a particular task as well as project milestones and/or task interdependencies.…

    • 1650 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    References: * Somers, Toni and Klara, Nelson. 2003. “The impact of strategy and integration mechanisms on enterprise system value: Empirical evidence from manufacturing firms.” European Journal of Operational Research. 146. 315-338.…

    • 12955 Words
    • 52 Pages
    Powerful Essays
  • Good Essays

    Cist Control

    • 773 Words
    • 4 Pages

    This system was developed at Lough borough University in association with a contractor. It aims to merger the planning and supervision and hence to obtain a more or less zero response time.…

    • 773 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Gantt Chart

    • 800 Words
    • 4 Pages

    The Program Evaluation and Run Technique (PERT) chart is a model for project management. It is a tool designed to represent the tasks involved in a project and analyze the time required for completion during the project management life cycle. It also helps to identify the minimum time required to complete the project. It was developed to simplify the planning and scheduling of a project where all the details and durations of the activities are not known at the start itself. It is used especially in project where time scheduling is of more criticality than the budget factor.…

    • 800 Words
    • 4 Pages
    Good Essays