Preview

Extension Of Time Case Study

Good Essays
Open Document
Open Document
777 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Extension Of Time Case Study
According to Cl-25.1(3)(l)&(v), Period of 40 days of delay is encountered due to late issuance of crucial information by the Engineer (STRUCT) should entitle the Contactor (FOUND) to claim EOT (Extension of Time).

According to Cl-27.1(I), Period of 40 days of delay is encountered due to late issuance of crucial information by the Engineer (STRUCT) should entitle the Contactor (FOUND) to claim direct loss & expenses due to fault by the Engineer (STRUCT).

1. The works progress is adversely affected by several typhoons and heavy rainfalls

According to Cl-25.1(3)(b)&(c), the works progress is adversely affected by several typhoons and heavy rainfalls should entitle the Contactor (FOUND) to claim EOT (Extension of Time).

2. What Architect(SMART)
…show more content…
The reasonableness and fairness of the EOT be decided by reference to the actual construction progress. The EOT granted may be less than the EOT claimed. For example, if the Contractor suffer only 30 days actual delay, 30 days of EOT is reasonable and fair.

3. What Contractor (FOUND) has done

The Contractor (FOUND) submits the Direct Loss and/or Expense claims bases on the entitled 90 days of extension. The claims based on 90 days of extension may exceed his direct loss and/or expense. Because under the contract the recoverable costs incurred must be “direct”, FOUND may only be entitled to direct loss and expense due to the period of 40 days of late issuance of crucial information by the Engineer (STRUCT).

4. What can the Contractor (FOUND) do

However, the Contractor (FOUND) may claim the “loss and expense” under common law due to delay caused by the adverse weather if he can prove that the earlier delay due to the fault of the engineer was the reason why in a later stage the progress was affected by adverse weather and so, had there been no earlier delay, the weather will not delay the
…show more content…
6. Case study on Koufos v. Czarnikow (1967)

According to Koufos v. Czarnikow (1967), the Court held that a party who breaches a contract is responsible for the damages that flow from that breach if at the time the contract was formed.

7. Analysis Summary

The Contractors (FOUND) may be entitled to recover the additional costs for the delay caused by adverse weather if they are able to show that had it not been for an earlier delay caused by the Engineer (STRUCT) they would not have been affected by the adverse weather. The premise is that the Contractor (FOUND) must be able to prove the earlier delay caused by the Engineer (STRUCT) with the effect on later delay caused by the adverse weather.
If the Contractor (FOUND) can prove the earlier delay due to late issuance of crucial information with the effect on later delay caused by the adverse weather, he can sue the Client under common law for damages, although he cannot sue the Client under contract law because adverse weather is not entitled to direct loss and/or

You May Also Find These Documents Helpful

  • Powerful Essays

    Goody’s entered into a contract with Banco to purchase wind suits. On or about July 13, 1994, Goody’s agreed to change the delivery date of the first shipment to September 30, 1994 and assured Banco that the “letters of credit” would be amended appropriately. Around August 23, 1994, prior to the contract delivery date, Goody’s informed Banco that they were terminating the contract. Plaintiff comes to the courts for relieve in the matter to a breach of contract.…

    • 1094 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Case Study 2

    • 278 Words
    • 1 Page

    Situation a. In evaluating the internal control over cash payments of Yankee Manufacturing, an auditor learns that the purchasing agent is responsible for purchasing diamonds for use in the company’s manufacturing process, approving the invoices for payment, and signing the checks. No supervisor reviews the purchasing agent’s work.…

    • 278 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    From what we can determine so far the main issues revolving around your construction project are unionized workers starting strikes and weather concerns during December. We are also informed that the company will suffer from a $500 per week penalty fee on overhead expenses if the construction project is not finished on time. It is also stated in the contract that a penalty clause of $15,000 per week of delay beyond February 15 of the following year will be implemented.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Good Essays

    tax research problem

    • 554 Words
    • 3 Pages

    1. Code Section 168(i)(6) provides the treatments of additions or improvements to property. It states that in the case of any addition to (or improvement of) any property, the applicable recovery period for such addition or improvement shall begin on the later of the date on which such addition (or improvement) is placed in service, or the date on which the property with respect to which such addition (or improvement) was made in placed in service.…

    • 554 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Contract Breach

    • 1284 Words
    • 6 Pages

    Situations that involve written and oral contracts between clients and contractors happen every day. Quite often, a price is agreed upon based on a completion date and the performance that happens along the way. One such situation that I have experienced was when my Dad decided to purchase a brand new townhouse in a downtown Cincinnati residential redevelopment project. A private contractor named Drees had won the rights from the city to be the only firm that could be used in the construction project and they are very popular there. A contract was signed between my parents and the developers that a new home would be built to their specifications and delivered within a six month period and upon that date they could move in. The focus of this analysis is to bring the contract under scrutiny that existed between Drees and my parents and how the contractor performed their duties.…

    • 1284 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    Quiz: Backup and Choices

    • 676 Words
    • 3 Pages

    5. Which of the following terms describes the actual time required to successfully recover operations in the event of an incident?…

    • 676 Words
    • 3 Pages
    Powerful Essays
  • Powerful Essays

    Legt1710

    • 2593 Words
    • 11 Pages

    Please note – in this unit we are NOT DEALING with: • Sale of Goods • Product Liability Therefore the following paragraphs in Latimer are NOT RELEVANT: ¶7-011 to ¶7-215…

    • 2593 Words
    • 11 Pages
    Powerful Essays
  • Powerful Essays

    Essay

    • 1594 Words
    • 7 Pages

    The construction must start on January 14, 2004 and must be completed within fifteen months. Liquidated damages (penalty clause) of $250,000 per calendar day of delay beyond March 31, 2005 is written into the contract. On the other hand, Ace will receive an Early Completion Bonus of $100,000 per day for each workday the project is completed before March 31, 2005.…

    • 1594 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Over The Years

    • 307 Words
    • 2 Pages

    A contracting company is involved in a dispute over its bill to a customer. The bill for $500,000 was recently reduced to $400,000 by a decision of the courts. The company is appealing the decision.…

    • 307 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Risk Assessment

    • 768 Words
    • 3 Pages

    The project implementation deadline occurs in 9 months. Each month after the deadline is missed, a penalty of $100,000 is assessed. Three months after the deadline, the contract will be cancelled.…

    • 768 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Tokyo Afm

    • 1244 Words
    • 5 Pages

    * Delivery has occurred or services have been rendered- the life of contract is 5 years, therefore Tokyo AFM is liable for the damages over the life of the policy.…

    • 1244 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Construction of towers were already behind the schedule; HQ reluctant to terminate the contract since the former company did a great deal of work on the construction…

    • 346 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    The contractor, Hill Construction (Bob Hill) was given a 270 days deadline for the project. There will be a contract penalty of $10,000 per day for running late. Hill again reviewed the data and noted that the optimistic time estimates can be used as crash times. He gathered his foremen and told them, “Folks, if we’re not 75% sure we’ll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days— also for 240 days. I want to be early, not just on time!”…

    • 966 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    C. Another problem is the late delivery of insurance policies. They usually complete in 14 days on the average. However, it is only able for small policies and a large policies always take at least 43 days to finish. In details " 26 days for First…

    • 1216 Words
    • 5 Pages
    Powerful Essays
  • Powerful Essays

    weather working day

    • 1224 Words
    • 4 Pages

    Weather working days have been be considered on several occasions: One of them was in London arbitration 10/04 (LMLN 0639) where the vessel was chartered under a C/P on the Gencon form. This particular vessel was loading not one but various and different cargoes (amongst others both timber and steel cargo). Loading was disturbed by the weather including snow and rain.…

    • 1224 Words
    • 4 Pages
    Powerful Essays