Exam: Critical Path Method and Project Management Techniques

Good Essays
Exam b 16 project 1. Which of the following statements regarding project management is false? a. Project organization works well when the work contains simple, independent tasks. b. Gantt charts give a timeline for each of a project 's activities, but do not adequately show the interrelationships of activities. c. Project organization is most suitable for projects that are temporary but critical to the organization. d. All of the above are true. e. None of the above are true. a (Project planning, moderate) 2. Which of the following statements regarding Gantt charts is true? a. Gantt charts are visual devices that show the duration of activities in a project. b. Gantt charts give a timeline and precedence relationships for each activity of a project. c. Gantt charts use the four standard spines of Methods, Materials, Manpower, and Machinery. d. Gantt charts are expensive. e. All of the above are true. a (Project scheduling, moderate) 3. Which of the following statements regarding PERT times is true? a. Optimistic time estimate is an estimate of the minimum time an activity will require. b. Optimistic time estimate is an estimate of the maximum time an activity will require. c. The probable time estimate is calculated as t = (a + 4m + b)/6. d. Pessimistic time estimate is an estimate of the minimum time an activity will require. e. Most likely time estimate is an estimate of the maximum time an activity will require. a (Project management techniques: PERT and CPM, moderate) 4. Which of the following statements regarding critical paths is true? a. The shortest of all paths through the

You May Also Find These Documents Helpful

  • Satisfactory Essays

    QUANTITATIVE TECHNIQUES MIDTERM EXAMINTION SECTION: TE203 Enumeration Questions: 1-7. Methodology of Quantitative Techniques 8-10. Three Types of Decision Making 11-13. Benefits of Quantitative techniques 14-17. Decision tree Diagram parts 18-23. Steps of the CPM of project planning 24-25. Two possible ways of representing activity in Network Planning Techniques 26-30. Parts of project network 31-32. Two project management techniques…

    • 259 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    What is project management, and what are its main objectives? What is the relationship between tasks and events, or milestones? What is a work breakdown structure? How do you create one? What are task patterns, and how can you recognize them? Compare the advantages and disadvantages of Gantt and PERT/CPM charts. Define the following terms: best-case estimate, probable-case estimate, and worst- case estimate, and describe how project managers use these concepts. How does a project manager calculate…

    • 702 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Critical Path Method

    • 894 Words
    • 4 Pages

    CPM - Critical Path Method In 1957, DuPont developed a project management method designed to address the challenge of shutting down chemical plants for maintenance and then restarting the plants once the maintenance had been completed. Given the complexity of the process, they developed the Critical Path Method (CPM) for managing such projects. CPM provides the following benefits: Provides a graphical view of the project. Predicts the time required to complete the project. Shows which…

    • 894 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    in 18 days or shorter. Using PERT or Project Evaluation and Review Technique method, we are required to show the solution regarding this case. Program evaluation and review technique (PERT) is a technique adopted by organizations to analyze and represent the activity in a project, and to illustrate the flow of events in a project. PERT is a method to evaluate and estimate the time required to complete a task within deadlines. PERT serves as an management tool to analyze, define and integrate…

    • 530 Words
    • 6 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Nightingale – A 1. Will the project as planned meet the October 25thdeadline? No, the project as planned actually reach end on 21st December2010. 2.What activities lie on the critical path? There are 15 critical activities in this network as below:-a.Architectural decisionsb.Feature specificationsc.Databased.Review designe.Integrationf.Procure prototype componentsg.Assemble prototypesh.Lab test prototypesi.Field test prototypes j.Adjust designk.Order stock partsl.Assemble first production…

    • 264 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    UNCERTAINTY AND PROJECT MANAGEMENT: BEYOND THE CRITICAL PATH MENTALITY Arnoud De Meyer1), Christoph H. Loch2), Michael T. Pich3) 1) Professor of Technology Management, INSEAD (arnoud.de.meyer@insead.edu.sg) 2) Associate Professor of Technology Management, INSEAD (christoph.loch@insead.fr) 3) Assistant Professor of Technology Management, INSEAD (michael.pich@insead.edu.sg) Keywords: project management, uncertainty, project profiles Abstract Project management is often identified…

    • 10531 Words
    • 43 Pages
    Powerful Essays
  • Powerful Essays

    Critical Path

    • 8065 Words
    • 33 Pages

    Engineering and Management, National Central University, No. 300, Jhongda Rd., Jhongli City, Taoyuan County 32001, Taiwan b R&D Center for Construction Project Management, Chung Hua University, No.707, Sec.2, WuFu Rd., Hsinchu, 300 Taiwan Received 7 February 2010; received in revised form 12 June 2011; accepted 16 June 2011 Abstract Assessing schedule delay 's impact on total project duration to distribute delay liability remains a controversy. None of existing delay analysis methods is perfect because…

    • 8065 Words
    • 33 Pages
    Powerful Essays
  • Good Essays

    critical path

    • 543 Words
    • 3 Pages

    Critical Path Analysis (CPA) Critical Path Analysis: A project-management technique that lays out all the activities needed to complete a task, the time it will take to complete each activity and the relationships between the activities. Sets out all the individual activities that make up a larger project. Shows the order in which activities have to be undertaken. Shows which activities can only take place once other activities have been completed. Shows which activities can be undertaken…

    • 543 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    PM 7010 – Project Management Techniques I Unit # 1 Individual Assignment # 2 Date: 09/11/2012 Number of Words: 299 Question: It has been argued that “the Project Manager is the most important person involved in a project”. I do not agree with the argument that the Project Manager is the most important person involved in a project. The most important person in a project is a stakeholder. A project is undertaken to create something unique with a beginning and an end, it could be a product…

    • 367 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    have decided to use a project management approach to bring the new product on line and have identified eleven activities and their precedence relationship as shown in Table 1. The duration for each activity has been estimated by three times estimates in weeks. They also manage to get information on the normal cost of each activity, their crash time and associated cost, shown in Table 2. You have been appointed by Michael and Elyssa to analyze the data and advise them on the project. You are expected…

    • 3058 Words
    • 13 Pages
    Powerful Essays