Preview

Critical Chain Project Management

Satisfactory Essays
Open Document
Open Document
1051 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Critical Chain Project Management
Criticalchainprojectmanagement — Document Transcript
• 1. Critical Path Method and Critical Chain Project ManagementProject schedule plan is the main plan included in any Project Management Plan. Project schedule isresponsible for bringing project time, cost and quality under control. Project schedule links resources,tasks and time line together. Once a Project Manager has list of resources, work breakdown structure(WBS) and effort estimates, he is good to go for planning project schedule. Schedule networkanalysis helps Project Manager to prevent undesirable risks involved in the project. Critical PathMethod (CPM) and Critical Chain Project Management (CCPM) are key elements of schedule networkanalysis. In the following sections we will explore these elements in details to understand theirimportance in keeping project on schedule to get increase in ROI.Critical Path Method (CPM):The Critical Path Method (CPM) is a schedule network analysis technique. CPM was developed by theDuPont Corporation in 1957.Critical path determines the shortest time to complete the project and itis the longest duration path through a network of tasks. Critical tasks (activities) are tasks (activities)on the critical path.To understand CPM further lets first understand nature of the task. According to PMBOK everyscheduled task can be defined by the following four parameters. • Early Start (ES): Earliest possible point in time on which a task can start. • Early Finish (EF): Earliest possible point in time on which a task can finish. • Late Start (ES): Latest possible point in time on which a task can start. • Late Finish (EF): Latest possible point in time on which a task can finish.Early Start and finish dates are calculated by means of Forward Pass and Late Start and Late Finishdates are calculated by means of Backward Pass.Many Tasks have some amount of buffer added to them referred as Slack Time or Float. Float time isamount of time a task can slip before it delays project schedule.

You May Also Find These Documents Helpful

  • Good Essays

    Critical Path is the path(s) with the longest duration in the network diagram. If any activity in the path is delayed, the whole project will be delayed.…

    • 846 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    4. The critical path for the project is found by calculating slack as per CPM as shown in the table below. The activities marked in green forms the critical path, I e.,…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    First Cars Ltd

    • 1031 Words
    • 5 Pages

    Critical path analysis is a method that is used to plan out the many activities involved in a project to be able to find the most efficient way of complete it and how to complete it on time.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Individual Project 2

    • 251 Words
    • 2 Pages

    Scheduling is essential to a project’s success. Forming a network activity with a visual depiction helps the team understand the relationships of tasks in a project. Two of the most common charts used in project management are the Gantt and PERT charts. The purpose of these charts is to assist with project scheduling and illustrate task dependencies. Another tool that can be used is the critical path method (CPM).…

    • 251 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Management

    • 1126 Words
    • 4 Pages

    Project management is one of the most important and critical tool or technique, which defines the entire course of development of any kind of project.…

    • 1126 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    Pert Mustang

    • 1016 Words
    • 5 Pages

    A table containing the project activities, the time estimates and the precedence relationship will be prepared and a network diagram will be drawn to structure the immediate predecessor activities. The critical activities will be identified to indicate that the project can be completed within 45 working days.…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.…

    • 7028 Words
    • 29 Pages
    Satisfactory Essays
  • Good Essays

    Most likely time estimate is an estimate of the maximum time an activity will require.…

    • 6920 Words
    • 28 Pages
    Good Essays
  • Powerful Essays

    The critical path is then determined by calculating the longest path of planned activities to the end of the project, meaning, the earliest and latest that each activity can start and finish without lengthening the project.…

    • 2429 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Project Management Models

    • 989 Words
    • 4 Pages

    A project defines a combination of interrelated activities that must be executed in a certain order before an entire task can be completed. Project management has evolved as a field of study, with the development of two analytical techniques for planning, scheduling, and controlling projects. These techniques are the project evaluation and review technique (PERT) and the critical path method (CPM). The purpose of this exercise is for the student to appreciate project planning issues and the application of PERT\CPM techniques. Please answer the following questions.…

    • 989 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Book Report

    • 683 Words
    • 3 Pages

    Critical chain is a modified or refined technique about critical path; it involves the deterministic and probabilistic approaches to analyze the project schedule, which is more realistic and practical than critical path.…

    • 683 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Suppose you now wanted to calculate duration estimates for these activities. How would you make use of the following approaches? Are some more useful than others?…

    • 710 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    THE CRITICAL CHAIN SOLUTION TO PROJECT SCHEDULING Developing the Critical Chain Activity Network Critical Chain Solutions versus Critical Path Solutions PROJECT PROFILE – BAE Systems and Critical Chain Project Management 11.5 CRITICAL CHAIN SOLUTIONS TO RESOURCE CONFLICTS 11.6 CRITICAL CHAIN PROJECT PORTFOLIO MANAGEMENT PROJECT MANAGEMENT RESEARCH IN BRIEF – Advantages of Critical Chain Scheduling 11.7 REACTIONS TO CCPM Summary Key Terms Solved Problems Discussion Questions Problems Case Study 11.1: Judy’s Hunt for Authenticity Case Study 11.2: Ramstein Products, Inc. Internet Exercises Bibliography TRANSPARENCIES 11.1 FIVE KEY STEPS IN THEORY OF CONSTRAINTS 11.2 DISTRIBUTION BASED ON COMMON CAUSE VARIATION [pic] 11.3 DISTRIBUTION BASED ON MISINTERPRETATION OF VARIATION [pic] 11.4 GAUSSIAN (LOG NORMAL) DISTRIBUTION [pic] 11.5 STUDENT SYNDROME MODEL [pic] 11.6 EFFECTS OF MULTITASKING ON ACTIVITY DURATIONS [pic] 11.7 THE EFFECT OF MERGING MULTIPLE ACTIVITY PATHS [pic] 11.8 REDUCTION ON PROJECT…

    • 3421 Words
    • 14 Pages
    Powerful Essays
  • Satisfactory Essays

    Aib Problem

    • 409 Words
    • 2 Pages

    A project uses the critical path when you are starting to build the projects network diagram. Critical Path is the path of activities that all have a slack or float of 0. This process is very important because if any of the projects critical path gets completed later than schedule than the project might not be completed on time.…

    • 409 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Critical path analysis identifies the most efficient and cost effective way of completing a complex project. The various activities which together will make up the project are identified, and the order of these activities are identified. Then, the duration of each activity is estimated and these factors are then arranged as a network or graph, showing the whole project from start to finish, and showing which tasks can happen at the same time. The sequence of tasks which have to be done one after another with no gaps in between is called the Critical Path.…

    • 711 Words
    • 3 Pages
    Good Essays