Chap001
Chapter 01
Modern Project Management

Multiple Choice Questions 1. The advent of project management has been most profound in
A. Automobile manufacturing
B. Construction
C. Information technology
D. The U.S. Department of Defense
E. Film making 2. A professional organization for project management specialists is the
A. PMI
B. AMA
C. MIS
D. IPM
E. PMBOK 3. Which of the following is not considered to be a characteristic of a project?
A. An established objective
B. A clear beginning and end
C. Complex tasks
D. Only for internal use
E. Never been done before 4. Which of the following activities is not considered a project?
A. Developing a new software program
B. Designing a space station
C. Preparing the site for the Olympic Games
D. Production of automobile tires
E. Developing a new advertising program 5. From among the following activities, which is the best example of a project?
A. Processing insurance claims
B. Producing automobiles
C. Writing a term paper
D. Completing a college degree
E. All of these are good examples of projects 6. Which of the following constraints is not typically found in managing projects?
A. Time
B. People
C. Cost
D. Performance
E. Both B and D are not typical constraints 7. Which of the following choices is not one of the stages of a project life cycle?
A. Conceptualizing
B. Defining
C. Planning
D. Executing
E. Delivering 8. In which of the following stages are project objectives established, teams formed, and major responsibilities assigned?
A. Conceptualizing
B. Defining
C. Planning
D. Executing
E. Delivering 9. In which of the following stages is a major portion of the physical and mental project work performed?
A. Conceptualizing
B. Defining
C. Planning
D. Executing
E. Delivering 10. In which of the following stages are you more likely to find status reports, many changes, and the creation of forecasts?
A. Conceptualizing
B. Defining
C. Planning
D. Executing
E. Delivering 11. Which of the following

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    (TCO A) Which step of the project life cycle produces all of the project deliverables?…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Chap9WBKEY 1

    • 2845 Words
    • 25 Pages

    2. How is the ionic charge of a Group 1A, 2A, or 3A ion determined?…

    • 2845 Words
    • 25 Pages
    Satisfactory Essays
  • Good Essays

    GB560 Unit 6 PaigeHarward

    • 1135 Words
    • 4 Pages

    The next stage would include project planning. This is the stage in which the team would establish a detailed project plan and would navigate from the existing plan and lead to an end result. This part of the process would include creating a chart indicating what changes are being made and help the team see the flow of the “As-Is” process and the “To-Be” process.…

    • 1135 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Chap009

    • 4787 Words
    • 22 Pages

    2. One cell sends second messengers to another cell through gap junctions. What type of signaling would this be considered?…

    • 4787 Words
    • 22 Pages
    Satisfactory Essays
  • Good Essays

    Pmp 42 Processes

    • 878 Words
    • 4 Pages

    Description The process of developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholder's needs and expectations. The process of documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans. The process of performing the work defined in the project management plan to achieve the project's objectives. The process of tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan. The process of reviewing all change requests, approving changes, and managing changes to the deliverables, organizational process assets, project documents, and the project management plan. The process of finalizing all activities across all of the Project Management Process Groups to formally complete the project or phase. The process of defining and documenting stakeholders' needs…

    • 878 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Unit 3 Quiz

    • 866 Words
    • 4 Pages

    1. Which of the following is NOT one of the four values of the agile approach?…

    • 866 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Project Management Email

    • 473 Words
    • 2 Pages

    3. Launch and Execution – In this phase the tasks are further defined and assigned to specific team members for action.…

    • 473 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    BSOP 588 Final Exam

    • 614 Words
    • 3 Pages

    7. (TCO A) Which of the following is NOT a characteristic of a Six Sigma project?…

    • 614 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    WFV1 Notes

    • 4474 Words
    • 16 Pages

    Statement of work Internet Business Associate v2.0, Lesson 10: IT Project and Program Management, section "Project Management Phases."…

    • 4474 Words
    • 16 Pages
    Good Essays
  • Powerful Essays

    3.What to do project life cycle add to the planning and execution of a project?…

    • 1571 Words
    • 7 Pages
    Powerful Essays
  • Powerful Essays

    Project Management

    • 2565 Words
    • 9 Pages

    - Project stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion. They may also exert influence over the project's objectives and outcomes.…

    • 2565 Words
    • 9 Pages
    Powerful Essays
  • Satisfactory Essays

    B. The phases a business goes through from when it first opens to when it finally closes.…

    • 502 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    PROJ 586 Final Exam

    • 814 Words
    • 4 Pages

    7. (TCO G) Which of the following is not an advantage of using project management software?…

    • 814 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Grt Task 1

    • 19334 Words
    • 78 Pages

    Correct Answer: D QUESTION 5 During which of the following process groups is the availability of required resources for the project determined? A. Executing…

    • 19334 Words
    • 78 Pages
    Powerful Essays

Related Topics