Preview

Xembra case study

Good Essays
Open Document
Open Document
13709 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Xembra case study
Baseline Report
Basic Project Data





Project duration is 123 days.
The work scheduled is 2,693 hours.
The cost for personnel is $173,329.43.
The project contains 55 tasks.

Cash Flow
This cash flow report indicates the baseline plan for spending on labor resources.

Task Usage
This task usage report depicts the number of hours, start times, and finish times for each task
(and for each resource assigned to the task).


Inventory tasks are front-loaded to have the task complete as soon as possible.



Report times are back-loaded to plan the time for the report to be completed and ensure availability of resources.



Due to resource leveling with a resource constraint, some tasks are started, then paused, then finished at a later date to ensure that the project is not delayed by a second task to which the resource is assigned.

Table 1: Resource Usage for Each Work Package and Task
Task
Number
1
2

3
4
5

6

7
8

9

10

11
12

13

Task Name
Computer inventory and requirements
Inventory computers in use by new telecommuters
Elizabeth
Marcel
Determine requirements to use current computers
Marcel
Identify computers for upgrade
Marcel
Determine requirements for technology
Elizabeth
Clemencia
Report outcomes for inventory and requirements
Elizabeth
Marcel
Clemencia
Technical support
Determine technical support needed
Hugh
Jackson
Identify staff requirements
Hugh
Jackson
Report technical support needs and staff requirements
Hugh
Jackson
Computing support
Identify required computer support relative to inventory
Kimberly
Lianne
Identify staff requirements
Hugh
Lianne

Work

Duration

Start

Finish

340 hrs
140 hrs
70 hrs
70 hrs
60 hrs
60 hrs
40 hrs
40 hrs
60 hrs
40 hrs
20 hrs
40 hrs
11.43 hrs
22.85 hrs
5.72 hrs
200 hrs
120 hrs
60 hrs
60 hrs
40 hrs
20 hrs
20 hrs
40 hrs
20 hrs
20 hrs
210 hrs
120 hrs
60 hrs
60 hrs
50 hrs
20 hrs

45.18

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Unit 421 Unit 7

    • 686 Words
    • 3 Pages

    The resource allocation for each activity for each week and the total weekly resource assignments are show…

    • 686 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    6. Double click the time located at the right side of the Taskbar and this dialog box displays.…

    • 1234 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Medical Coding Workflow

    • 282 Words
    • 2 Pages

    Productivity figures will be calculated by dividing the output by the amount of time to complete the task.…

    • 282 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Castle Family Restaurant

    • 1300 Words
    • 6 Pages

    References: AsureForce Software. (n.d.). AsureForce Time & Labor Management. Retrieved September 14, 2012, from AsureForce Software: http://www.asuresoftware.com/products/asureforce…

    • 1300 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    * Working hours/days – This will tell you what hours you will be expected to work in a day, the time you start & finish, how long your breaks will be & how many days a week you will be working…

    • 2197 Words
    • 9 Pages
    Good Essays
  • Better Essays

    Greendale Stadium Case

    • 1281 Words
    • 6 Pages

    1. Will the project be able to be completed by the May 20 deadline? How long will it take?…

    • 1281 Words
    • 6 Pages
    Better Essays
  • Good Essays

    Exercise

    • 562 Words
    • 2 Pages

    1. The report is due on Wednesday, but we’re flying back from Miami that morning. I told the project manager that we would be able to get the report to her later that day, but she instead suggested that we come back a day early to get the report done on time. I informed her that unfortunately we would not be able to arrive a day early, as we have meetings to attend until our flight took off. To solve our dilemma we then emailed our contact, who let us know that he would need to talk to his boss about the matter. His boss said that the project could afford a delay, as long as they wouldn’t have to make and edits or changes to the file. She allowed us some extra time and our new deadline is next Friday.…

    • 562 Words
    • 2 Pages
    Good Essays
  • Good Essays

    * Time spent on project activities is approximately 370 minutes including going over project reports and preparing for weekly status meeting (25m), Progress review meeting (45m), Reviewing project assignment with Victoria (30m), listening to teammates (20m), Discussing problem with John (30m), negotiating with purchasing agent (30m), Conference call (60m), negotiating with Mary (40m), reviewing the impact the client’s requests (30m), Reviewing e-mails and project documents (30m), and Working with “what-if” scenarios (30m).…

    • 861 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Critical Path

    • 1605 Words
    • 7 Pages

    4. Draw a project network with nodes and arcs depicting the activities and immediate predecessors listed in steps 1 and 2. Please see problem 4, 7, and 8 below for an example of a network with arcs.…

    • 1605 Words
    • 7 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The one metric that has been identified to measure the process is time. The flowchart will incorporate the identified metric for every day of the workweek being studied. The following times listed are for the data collected for work week #1:…

    • 493 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Assembly Line Design

    • 525 Words
    • 3 Pages

    The following tables give the tasks, task times, and predecessors that are to be performed on an…

    • 525 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    In Poor Richard’s Almanac, Benjamin Franklin penned the familiar lines: “For the want of a nail the shoe was lost, for the want of a shoe the horse was lost, for the want of a horse the rider was lost, for the want of a rider the battle was lost, for the want of a battle the kingdom was lost — and all for the want of a horseshoe nail.” Looking at the outcome in hindsight, could project management concepts have avoided the loss of the kingdom? Explain your answers.…

    • 702 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    To decide or arrange to delay an event or activity until a later date or time *…

    • 1220 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    and thereby establishing BLHPTASK for each task. The Budgeted labor hours could be done based on companies past experience/practice or using an industrial standard.…

    • 745 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Project Proposal - A project proposal is written, to make an offer and to try to convince a supervisor or a future customer to accept it. In a project proposal you state that, in exchange for time and/or money, you will give them something that they want (an analysis of a procedure, for example), make something they desire (a prototype of a new product), or do something they wish to have done (redesign an existing structure).…

    • 287 Words
    • 2 Pages
    Satisfactory Essays