Method Statement for Construction of Low-rise Building

Table of Contents
1. Introduction
2. Summary of RC structure Dimension
3. Specification for Reinforced Concrete Structures
4. Competent Persons for Constructions of the Low-rise Building (LRB) Structure
5. Plants
6. Labour
7. General Construction Methodology
8. Construction Procedure
9. Site Logistic Plan
10. Environmental Protection Measures
11. Contingency Plan
Appendix A –
Appendix B – Design Calculation for Floor span
Appendix C – Design Calculation for Column
Appendix D – Design Calculation for Beam
Appendix E – Design Calculation for Wall
Appendix F – Design Drawing
Appendix G – Design Calculation for Floor span

1. Introduction This submission presents the method statement and corresponding temporary work design for the construction of low-rise building (LRB). Footing foundation will be chosen for the foundation of structure. Design calculation and drawing for the structure, including beams, columns, foundations, walls, floor slabs will be shown in the following categories. Furthermore, formwork will be adopted for the construction of structure and timber formwork will be the first priority.
2. Summary of RC Structure Dimension
Element
Member Size (mm)
Type of formwork
Foundation

Timber
Slab
250
Timber
Beam
500 x 500 x 5000
Timber
Wall
150
Timber
Column
500 x 500
Timber
3. Specification for Reinforced Concrete Structures
All concrete works shall conform to the General Specification as following:
Elements
Grade
Column
Wall
Beam
Slab
Blinding layer
Reinforcement
35
35
35
35
35
260, 460 MPa

4. Competent Persons for Constructions of the Low-rise Building (LRB) Structure
Construction Manager & Engineer – He shall supervise all technical items of construction works of MPS 2 structure, but not limited to the following items:
1. To handle the difficulties during the construction.
2. All required tests arrangement and Submission to the

You May Also Find These Documents Helpful

  • Satisfactory Essays

    bubbaganoosh

    • 515 Words
    • 3 Pages

    There are specific procedures in place for each part of the construction process, one procedure involves checking all materials when arrive at the site. All materials must be checked against an ordering list to ensure all materials have arrived and are consistent with what was ordered. This procedure is, at times, long and involved, however must be in place to ensure each stage of the project is completed on time and no re-ordering has to occur.…

    • 515 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Role Description: Responsible to the Project Manager for coordination of all activities related to design and…

    • 740 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    responsible for meeting the deadline of the project. The architect or building manager will be responsible for…

    • 315 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Hnc Forms of Construction

    • 3301 Words
    • 14 Pages

    Contents 1.0 Introduction 2.0 Methodology 3.0 Inception 4.0 Feasibility 4.1 Overview of stage 4.2 Assessing the feasibility 4.3 Site investigation 4.4 Effects on design 5.0 Then brief 5.1 Overview of stage 5.2 What the brief should cover 5.3 What the brief should include 5.4 Consultants at this stage 6.0 The concept/outline proposals 6.1 Overview of stage 6.2 Requirements to proceed with concept design 6.3 Developing the brief into concept design 6.4 Planning permission 6.5 Building regulations approval 6.6 Achieved at this point 7.0 The design development 7.1 Overview of stage 7.2 Developing the design 7.3 Finalisation of design 7.4 Planning proposal 7.5 Building regulations 7.6 Sampling and testing 7.7 Health and Safety 7.8 Achieved at this stage 8.0 Technical design 8.1 Overview of stage 8.2 Implications on design 9.0 Production phase 9.1 Overview of stage 9.2 Design implications 10 Other construction projects…

    • 3301 Words
    • 14 Pages
    Powerful Essays
  • Powerful Essays

    Construction Congress, Walsh, K. D., American Society of Civil Engineers., M.E. Rinker, Sr. School of Building Construction., & International Council for Building Research, Studies and Documentation. (2000). Construction Congress VI: Building together for a better tomorrow in an increasingly complex world : proceedings of the congress : February 20-22, 2000, Orlando, Florida. Reston, Va: The Society.…

    • 1188 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    | |contractors/builders carrying out work on the premises. This is the main legislative framework that|…

    • 1335 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Undertake management responsibilities for some or all aspects of the design and construction of new construction or refurbishment projects…

    • 893 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Riba Design

    • 574 Words
    • 3 Pages

    Construction strategy needs to be cinsidered including offsite fabrication and develop health and safety strategy. Sustainability strategy is the strategy for delivering the sustainability aspirations. Maintenance and operational strategy is the strategy for the maintenance and operation of a building, including details of any specific plant required to replace components. Handover strategy and risk assessments have already been defined. Research and development is project-specific research and development responding to the initial project brief or in response to the concept design as it develops. Project execution plan is produced along with the project lead and lead designer. The construction strategy is a strategy which considers certain aspects of a design that may affect the building or logistics of a construction project or possible the health and safety aspects. The health and safety strategy covers all aspects of health and safety on a project. The sustainability checkpoint for this stage is 2 and the information exchanges demand the concept design including defined structural and building services design, related project strategies, preliminary cost information and final project…

    • 574 Words
    • 3 Pages
    Good Essays
  • Good Essays

    We will meet with you and discuss all ideas and preferences you may have for this project. Our experts also will collect all pertinent measurements in order to create a construction plan.…

    • 481 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Rc Description

    • 332 Words
    • 2 Pages

    | As reflection deepens, the focus should move away from concern with the ‘technical’ aspects of the classroom towards wider issues. A good reflective commentary should also contain thoughts about what the process of reflection has taught you about yourself as a learner and as a teacher. Your commentary should include some analysis about how your reflection has led you to consider wider issues (this discussion should be supported by reading) and about how the person you are has had an impact on your developing reflective processes.…

    • 332 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    The Project Manager is authorised by the General Manager to manage and coordinate this important phase of the company’s development. The Project Manager is authorised to issue directives relating to the project.…

    • 794 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Construction Management

    • 1103 Words
    • 5 Pages

    Construction as a service activity having many dimensions. Starting from ideas, thru find funds, investor, design construction, find contractor, phase of construction, meet the requirements which investment needs to be in use and complete facility.…

    • 1103 Words
    • 5 Pages
    Better Essays
  • Better Essays

    Engineering the Impossible

    • 1111 Words
    • 5 Pages

    Construction of the Millennium Tower will include traditional building techniques, that, in this case, will put ironworkers thousands of feet in the air to place 5-ton girders with a minimum of safety gear. But engineers are planning to also use a new technology — building by computer.The Self-Rising Factory is a set of computerized cranes and lifts surrounded by a weatherproof enclosure. According to a precise schedule, the steel beams are essentially handed to the machinery which then places them for workers to bolt together. Once the beams and…

    • 1111 Words
    • 5 Pages
    Better Essays
  • Good Essays

    some directions of how the envelope or the massing of the buildings will be (Master of Architecture).…

    • 587 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Soil Exploration

    • 2527 Words
    • 11 Pages

    Sidney, Levy. Construction Site Work, Site Utilities and Substructures. New York: McGraw Hill Professional, 2001. Print.…

    • 2527 Words
    • 11 Pages
    Powerful Essays

Related Topics