System| Work Packages| Activities| Tasks|
0 Rosie Perry’s Content Management System | 1Project Management| 1.1 Project Launch Meeting| 1.1.1 Choose date to launch meeting.| | | | 1.1.2 Choose venue.|
| | | 1.1.3 Send notification to all Project team.|
| | 1.2 Project Planning| 1.2.1 Establish Scope (Technical and Non Technical)| | | | 1.2.2 Determine Roles and Responsibility for each team member.| | | | 1.2.3 Establish tentative budget and schedule estimation.| | | | 1.2.4 Determine Composite Plan.|

| | | 1.2.5 Composite Project Plan Approval.|
| | | 1.2.6 Obtain Team Signature.|
| | | 1.2.7 Review composite plan (i.e. Master Plan/Baseline Plan)| | 2 Requirements Gathering | 2.1 Brainstorming| 2.1.1 Take meeting| | | | 2.1.2 Generate many possible ideas/requirements as possible.| | | | 2.1.3 Prioritize possibilities.|

| | | 2.1.4 Obtain Team signature.|
| | | 2.1.5 Review/Report|
| | 2.2 Document Sampling| 2.2.1 Review documentation of existing system. | | | | 2.2.2 Collect other related documents|
| | | 2.2.3 Review collected documents.|
| | | 2.2.4 Generate Report.|
| | 2.3 Observation| 2.3.1 Choose date for the observation day. | | | | 2.3.2 Identify process flow, turning and twisting points.| | | | 2.3.3 Understand Business Process. |
| | | 2.3.4 Generate Report.|
| | 2.4 Interview| 2.4.1 Create possible questions.|
| | | 2.4.2 Choose Main/Key questions.|
| | | 2.4.3 Pick a date for an |
| | | 2.4.4 Get appointment|
| | | 2.4.5 Review interviewed results|
| | | 2.4.5 Generate Report|
| 3 Analysis and Design| 3.1 Functional Specification| 3.1.1 Generate User Interface Mock-Up.| | | | 3.1.2 Review Design|
| | | 3.1.3 Deliver final functional specs.|
| | | 3.1.4 Obtain User Signature.|
| | 3.2 Technical Specification| 3.2.1 Develop Technical Specs.| | | | 3.2.2...