1.0 Introduction to the Structure of a WBS

A Work Breakdown Structure or Work Element Pyramid is a results-oriented family tree that captures all the work of a project in an organized way. It is often portrayed graphically as a hierarchical tree, however outlined; it should organize and define the scope of the project. It can also be a tabular list of "elements" categories and tasks or the indented task list that appears in your Gantt chart schedule. Listed below is a very simple illustration of a WBS tree of a sample project.

WBS Tree

1.0 Level 1 (Total Job)

1.1, 1.2, 1.3 Level 2 (Major Subdivision)

1.1.1, 1.1.2, 1.1.3 Level 3 (Minor Subdivisions),, Level 4 (Tasks),, Level 5 (Subtasks)

The WBS chart listed above is an example but not inclusive. Large, complex projects are organized and comprehended by breaking them into progressively smaller pieces until they are a collection of defined "work packages" that may include a number of tasks. A $1,000,000,000 project is simply several $50,000 projects joined together. The Work Breakdown Structure (WBS) is used to provide the framework for organizing and managing the work and most importantly tying resources to jobs and tracking the performance of the efforts. In planning a project, it is normal to become overwhelmed and confused as one begins to grasp the details and scope of even a modest size project. This is a common result when trying to understand the details of work that will be performed by a number of people over a period of time. The best way to break through the confusion is to break the project into smaller pieces (tasks and subtasks), and organize the pieces in a logical way using a WBS. The WBS format enables placement of the tasks in a placeholder category that can be accounted for and have better visibility. The visibility of tasks within a WBS allows us to see if tasks are causing delays on the entire project especially when they are in the critical path. Critical path is any task that must be accomplished along the way that, if not accomplished, brings the project to a screeching halt.

The psychologists say our brains can normally comprehend around 7-9 items simultaneously. A project with thousands or even dozens of tasks goes way over our ability to grasp all at once. The solution is to divide and conquer. The WBS helps break thousands of tasks into chunks that we can understand and assimilate. Preparing and understanding a WBS for your project is a big step towards managing and mastering its inherent complexity. Standard (MIL-STD) 881B (25 Mar 93) as follows: "A work breakdown structure is a product-oriented family tree composed of hardware, software, services, data and facilities .... [It] displays and defines the product(s) to be developed and/or produced and relates the elements of work to be accomplished to each other and to the end product(s)." Mental discipline is required to develop a product-oriented or deliverable-oriented grouping of project elements adding up to comprise the entire project scope. Intuitively, we tend to start out with a task-oriented approach. This is OK for very small projects where extensive project management controls will not be used. The task-oriented approach is easy to understand, because we can easily think of projects as collection of tasks. A task-oriented WBS can be developed by beginning with a simple "to-do" list and then clustering the items in a logical way. The logical theme could be project phases, functional areas, or major end-products.

If your organization will be collecting historical data to form a cost database, you should try to select a standard approach consistent with the organization's long term data collection needs.

A WBS for a large project will most likely have multiple levels of detail, and the lowest WBS element will be linked to functional area cost accounts that are made up of individual work packages. Work packages should add up through each WBS level to form the project total.

1.2 Product or Process Oriented WBS

Should our Project be Product or Process Oriented? That is a good question and the answer is; that depends. The WBS is initially defined as a product oriented family tree, however subsequent definitions have evolved over the years and now introduce more flexibility -- so a WBS can also be a deliverable product or process oriented. Your WBS can be built on nouns or verbs. If the results of your project are primarily verbs, then a verb based or process based WBS may make more sense. If your WBS is to be product or deliverable oriented, then you can start by thinking of the WBS as a parts list for the ultimate end-items of your project. This link will give a simple illustration of a product or process based WBS orientation. These differences are not shown to tell you what the right way for your project are, but just to familiarize you with the ideas and methods to caveat your project to obtain the highest visibility, so you can think about them and choose what's best for your project. WBS Numbering is often a confusing subject because you see different ways. Some are numerical and some are alpha-numeric. In any case, consistency is the key. Once you have established the project WBS, changing it is a no-no. It can be done, but if it is automated, you will have to redo the entire database and load the schedules, resources ...etc. Never, ever change the WBS without customer concurrence. That is not to say that WBS changes can't be done, but rather to say, spend extra time establishing the WBS to reduce pain and confusion later. Let's continue the discussion on how common WBS elements appear. WBS elements are usually numbered, and the numbering system may be arranged any way you choose. The conventional numbering system is shown in the figure. The shaded box shown in the above slide could be numbered, which would tell you it was in the second box in level 2, the second box in level 3, and the third box in level 4.

1.3 WBS Dictionary

If a WBS is extensive and if the category content is not obvious to the project team members, then it is necessary to write a WBS dictionary. In fact, that is a good procedure to make mandatory because when you have people cycling through projects, they need a point of reference. The WBS dictionary describes what is in each WBS element, and it may also say what is not in an element, if that is unclear. Here is a sample of a WBS dictionary description:

WBS Element - Systems Integration Test Equipment Planning - This element includes the effort to identify requirements and specify types and quantities of test equipment needed to support the System Integration and Test process. It does not include the design or procurement of such equipment, which is covered in Element Mapping WBS for Cost Management

In a product-oriented WBS, functional categories of work may form "cost accounts" within a WBS element. Cost account managers are responsible for a functional area's contribution to a WBS element. Cost accounts from several departments or functions may combine into one WBS element. Internal department planning for a cost account will be made up of individual work packages. A work package will typically have its own budget and schedule. Work packages should be small enough to be executed by individuals or small groups in a single department, and they should be of relatively short schedule duration. A small project might define a maximum work package size as two weeks of effort.

Larger projects will assemble larger work packages that can be appropriately managed and controlled. The project manager will have to decide to what degree employment of various details of WBS implementation will benefit the efficient management of the project. On a very small project, a formal WBS may serve no useful purpose, but it can become valuable if project size or complexity start to increase. As an organization's project management environment matures, or as larger size and complexity are encountered, application of the WBS concept can evolve from an ad hoc list of tasks, to time-phased activity lists, task lists clustered by project deliverables and services, or an end-product focused WBS fed by cost accounts and work packages.

If you are using MS-Project or a similar project management software application, you may encounter the WBS as a vertical list with indents to show structure. This will be compatible with the Gantt View data entry screens. While some software packages provide a separate WBS view, you could prepare your WBS in the vertical format using a word processor, and then cut and paste your WBS into your project management software package.

1.4 Program and Contract WBS

A top-level WBS for a large program is sometimes called a Program WBS (PWBS) or Program Summary WBS (PSWBS). If a project involves several organizational participants or contractors, guidance for one contractor can be provided in a Contract WBS (CWBS). The project manager may provide a high-level CWBS for each developer, perhaps to level 2 or level 3. The developer will then fill in the details of lower WBS levels to reflect the work to be accomplished and the data flow in that organization. Your organization may want to decide on a standard WBS format or group of formats, use these across all projects, and communicate definitions widely so everyone will be speaking the same language. This can save re-learning project lessons and can lay the groundwork for successful data gathering to aid future cost estimates.

1.5 WBS Implementation

When you set up a project WBS, always be forward thinking -- think about how you will be using it later in the project. Try to consider how you will organize the WBS, schedule format, manager assignments, and charge numbers, in your early project planning. These days, the WBS in smaller projects ends up automatically being the indent structure in your Gantt schedule, so pay attention to those indents, and make sure that is the WBS you want for rolling up costs in your project, especially if you will be using Earned Value Management (EVM). It will be helpful if you can map the charge numbers, managers, and task groups to each other. This will help you track costs and progress for each manager. If your project schedule will on MS-Project, you may want to insert "text" columns into your schedule (Gantt View) for project charge numbers and manager names. If your project charge numbers cannot be linked to groups of tasks assigned to specific managers, you will have no way to provide performance measurement feedback to managers.

Some project management environments have definite conventions for grouping items in a WBS. The best method is to have a WBS that works for your particular project environment. The WBS should be designed with consideration for its eventual uses. Your WBS design should try to achieve certain goals:

* Be compatible with how the work will be done and how costs and schedules will be managed,

* Give visibility to important or risky work efforts,

* Allow mapping of requirements, plans, testing, and deliverables,

* Foster clear ownership by managers and task leaders,

* Provide data for performance measurement and historical databases, and

* Make sense to the workers and accountants.

1.6 Conclusions

There are usually many ways to design a WBS for a particular project, and there are sometimes as many views as people in the process. The most important thing is to ensure you capture the main efforts and tasks to be accomplished and that you have stakeholder concurrence on the WBS for the project.


Pennypacker & Dye "Managing Multiple Projects; chapter 3" 2002

"Project management production and manufacturing" online:

"US Department of Defense (DoD) Handbook Work Breakdown Structure" online:

Cite This Document

Related Documents

  • What Is a Work Breakdown Structure (Wbs)?

    ...What is a Work Breakdown Structure (WBS)? Once we have identified all of the things that we are supposed to produce in the project, it is necessary to develop the specific items of work that must be done to complete all of the work. The work breakdown structure takes the pr...

    Read More
  • Work Breakdown Structure

    ...Work breakdown structure A Work Breakdown Structure (WBS) in project management and systems engineering, is a tool that defines a project and groups the project’s discrete work elements in a way that helps organize and define the total work scope of the project.[1] [pic] [pic] Example of a work breakdown structure of an aircraft system. ...

    Read More
  • Work Breakdown Structure

    ...Week 3 Assignment Work Breakdown Structure BUS 611 Project Planning and Management August 13, 2012 Week 3 Assignment WBS Level 1 | Level 2 | Level 3 | Responsibility | CPN Electronic Medical Record Work Breakdown Structure | 1.1 Project Conception and Initiation | Task: 1.1.1 Evaluation and recommendations Task: 1.1.2 Review Scope and...

    Read More
  • Work Breakdown Structure

    ...A work breakdown structure is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. Since many projects involve many people and many different deliverables, it is important to organize and divide the work into logical sections based on how the work will be performed. The work breakdown s...

    Read More
  • Work Breakdown Structure

    ...Work Breakdown Structure In project management a hierarchical delivery oriented breakdown of project into individual components is called as work breakdown structure (WBS). WBS decomposes project into individual functions, deliverables and work packages that facilitates resource allocation, assignment of responsibilities, and measurement and...

    Read More

    Read More
  • Project Management and Work Breakdown Structure

    ...Conveyor Belt Project WBS and Network Diagram This document contains Work Breakdown Structure and Network Diagrams for the Conveyor belt project. The document also contains screenshots of MS Project schedule and Gantt chart. Conveyor Belt Project 1. Work Breakdown Structure WBS for Conveyor Belt Project is illustrated below: Does ...

    Read More
  • Work Breakdown Structure

    ...WORK BREAKDOWN STRUCTURE (WBS) The description of the WBS is as follows: 1. SIMS 1.1 Feasibility Study (Phase 1) Activities in this phase are carried out to understand the potential of the project taken. This phase uncovers the strengths and weaknesses of the project. 1.2.1 Monitor Progress (Task A) The information tha...

    Read More

Discover the Best Free Essays on StudyMode

Conquer writer's block once and for all.

High Quality Essays

Our library contains thousands of carefully selected free research papers and essays.

Popular Topics

No matter the topic you're researching, chances are we have it covered.