Preview

Tep Case Study

Good Essays
Open Document
Open Document
540 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Tep Case Study
Case study teaching notes
Trans
-European Plastics
TEP makes a range of more than 500 plastic household items using batch injection moulding.The case highlights increasing problems with inventory shortages and declining service levels,at the same time that total inventory levels were at a high level. The company was evenconsidering investing in a warehouse extension. This case allows students to explore theunderlying reasons for this situation, and there is considerable numerical data that can beanalyzed.This case provides an ideal introduction to the topic of inventory management, and is at a levelto be of use on both undergraduate and Masters/MBA courses. Although describing amanufacturing situation, there are no technical issues to be understood, and the analysis would be little different in a retailing type of service. It provides sufficient information for the studentsto prepare spreadsheets for ABC analysis and categorization. This would be a good case for assessed work, but is too long and complex for a traditional examination.
Some notes on the Trans-European Plastics case
1. Why is TEP unable to deliver all its products reliably within the target of one week,and what effects might that have on the distributors?
There are 24 machines working a standard (non-overtime) week of 105 hours. Thus, there are2520 machine hours available per week. There are 500+ stock keeping units (SKUs), eachtaking 3 hours to set-up, and the minimum run length is 20 hours. Thus, any batch takes at least23 hours of machine time. Theoretically, the maximum number of SKUs per standard(nonovertime)week is thus 2520/23 = 110. Thus, on average
, each SKU could be made only every4.5 weeks (500/110 = 4.54) or even less frequently, because larger batches for popular itemswill occupy more machine time. This illustrates that it would be impossible to make all productswithin the one-week delivery window, and the company must operate a make to stock (MTS)system, with inventory levels

You May Also Find These Documents Helpful

  • Powerful Essays

    Shuzworld Analysis

    • 5851 Words
    • 19 Pages

    A. Workflow: Shuzworld produces Rugged Wear Work Boots at its Shanghai production facility using an 8-step process and an assembly line of 8 workstations. Each workstation performs a single task that can range from 3 minutes to 10 minutes to complete, resulting in a total time of 46 minutes to fully assemble one pair of steel-tipped work boots. The facility has a budget to produce 6 work boots an hour, with a 40-hour work week (48 work boots a day). The following table shows the task schedule, along with the time required for each task and predecessor information to complete the 8-step process. The graph shows the current layout of the 8 workstations in the production line:…

    • 5851 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    3. Following up on Question 2, which do you think is worse, refusing a customer’s order upfront because you don’t have the units available or accepting the order and then failing to deliver? What are the implications for master scheduling?…

    • 666 Words
    • 3 Pages
    Satisfactory Essays
  • Better Essays

    Functional Area

    • 825 Words
    • 4 Pages

    The ultimate goal for the company is to foster growth and expansion by becoming the foremost provider in quality products and customer service. In order to reach this goal and experience 100% growth over the next five years, the Production and Operations department (“Productions”) must streamline its manufacturing and restructure inventory processes. At present, the current facility operates at maximum capacity. Adding second and third shifts will enable the company to meet consumer demand and to provide the right product for the right price.…

    • 825 Words
    • 4 Pages
    Better Essays
  • Good Essays

    Little Field

    • 770 Words
    • 4 Pages

    One of our initial goal for day 52 was to make sure our system was clear of any bottleneck and to have sufficient level of inventory to last us until day 73. This strategy was in part due to the fact that we did not have much time to analyze and properly forecast the future demand (initially meeting took place at midnight due to the long commute), but also to allow us to have more data about the incoming demand. To determine the proper level of order quantity and reorder point, we did a simple forecasting of incoming demand by using a simple linear regression analysis of observed demand for the first 50 days. Using this data we determined that the reorder point must be increased to 45 and the order quantity should be set at 250 kits.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Direct Labour

    • 844 Words
    • 4 Pages

    The company’s plant has a capacity of 130,000 direct labor-hours per year on a single-shift basis. The company’s present employees and equipment can produce all five products.…

    • 844 Words
    • 4 Pages
    Good Essays
  • Better Essays

    The master production schedule (MPS) at Riordan determines what parts will be needed on a weekly basis to meet the quarterly projected needs. Because Riordan uses a make-to-stock system, they are easily able to satisfy customer demand without production delays. A fixed-order quantity inventory method is used with an automated system to order parts when inventory levels drop to a determined level. A flexible time fence is utilized, as capacity remains unremarkable, and the majorities of Riordan’s suppliers are reliable and do not cause significant delivery…

    • 685 Words
    • 3 Pages
    Better Essays
  • Satisfactory Essays

    One of our team members conducted a full operations analysis. Using the analysis, demand for the 268 days of production was forecasted, and our strategy set accordingly.…

    • 655 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Stonehaven Inc

    • 785 Words
    • 7 Pages

    + (4.00 x 4) = 17.6 min/batch Manufacturing Lead Time (MLT) 23 min/batch. Capacity = 480 min/day ÷ 23 min/batch =…

    • 785 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Husky Injection

    • 233 Words
    • 1 Page

    Calculating the amount of days it will take to product the same amount of products with the competitor’s machine:…

    • 233 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Husky project

    • 155 Words
    • 2 Pages

    Calculating the amount of days it will take to product the same amount of products with the Husky’s machine:…

    • 155 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Economics Test Questions

    • 348 Words
    • 2 Pages

    Current operations allow the company to make 500 boxes per day, in two 8-hour shifts (250 boxes per shift). The company has introduced some small changes in equipment, and conducted…

    • 348 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Executive Shirts

    • 1700 Words
    • 7 Pages

    Show details of calculations and answers todescriptive questions on pages 2 to 8 of this handout. Also, please fill in numericalanswers for the questions in the table below.…

    • 1700 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    Toyota Case

    • 3091 Words
    • 13 Pages

    Toyota Motor Manufacturing, Indiana, Inc. (TMMI) manufactures Toyota’s first full-size truck. In order to make TMMI as profitable as possible there are a couple of fundamental logistical processes that had to be defined. An important decision that had to be made was the use of appropriate shipping containers for the delivery of parts and materials from suppliers.…

    • 3091 Words
    • 13 Pages
    Powerful Essays
  • Powerful Essays

    * There are 24 machines which are working on a standard (non-overtime) week of 105 hours. Thus, there are 2520(24 X 105) machine hours available per week.…

    • 3310 Words
    • 14 Pages
    Powerful Essays
  • Satisfactory Essays

    Desired Cycle Time

    • 108 Words
    • 2 Pages

    A company is setting up an assembly line to produce 192 units per eight-hour shift. The following table identifies the work elements, items, and immediate predecessors.…

    • 108 Words
    • 2 Pages
    Satisfactory Essays