Tata Project

Only available on StudyMode
  • Topic: 1943, 1941, 1965
  • Pages : 5 (652 words )
  • Download(s) : 718
  • Published : August 28, 2010
Open Document
Text Preview
ACE PLANT PANTNAGAR
ACE PLANT HEAD (PANTNAGAR)

• Mr. P. K. Chobe. • Mechanical Engineering Graduate from IIT Kanpur. • Joined Tata Motors in July 1978 as GET. • Worked in maintenance, production & as Engine Factory Head. • Fond of swimming. PLANTS OF TATA MOTORS LTD.

MILESTONES
DATA REGARDING THE SITE

[pic]

MASTER PLAN

ORGANIZATION STRUCTURE AND PHILOSOPHY

STRUCTURE FOR SUPPLY CHAIN
STRUCTURE FOR SUPPLY CHAIN

VENDOR PARTNERING

[pic]

PROJECTED STATE EARNINGS FROM TATA MOTORS

[pic]

[pic]
 
OVERALL RAMP-UP PLAN TO PLANNED CAPACITY

Feb 07 Aug 07 Mar 08 Sep 08

Feb 07 Aug 07 Mar 08 Sep 08 MANPOWER STATUS / PROJECTION FOR 750/DAY

NEW IDEAS IMPLEMENTATION FOR LOGISTICS

[pic]
CORPORATE SOCIAL RESPONSIBILITY

[pic]

[pic]

[pic]
LAYOUT OF THE TATA MOTORS PANTNAGAR PLANT

TATA MOTORS LTD. Pantnagar has four shops for manufacturing of vehicles. These Shops are oriented in a shape of alphabet ‘E’.

VARIOUS SHOPS OF TATA MOTORS PANTNAGAR PLANT

TCF 1A TCF SHOP
➢ ASSEMBLY SHOPSTCF 1B i.e.
TCF 1C TRIM CHASSIS FITTING

ENGINE SHOP
➢ ENGINE SHOP
GEAR BOX SHOP

COMPLETE KNOCK DOWN (CKD)
➢ PAINT SHOP
TAIKISHA PAINT SHOP

BIW 1A BIW SHOP
➢ WELDING SHOPBIW 1B i.e.
BIW 1C BODY IN WHITE SHOP -----------------------

Objective

• To ensure that community members benefit from the industrialization boom in Uttarakhand
• To build a private-public partnership to ensure an inclusive growth process

So Far

• Conducted a Participatory Rural Appraisal for Udaynagar to identify the needs of the villagers
• Initiated the process to get a clearance from the government to upgrade ITIs. • Held informal meetings in Udaynagay and Chitranjpur. • Arranging a health camp for Primary School children at Udaynagar.

Tata Motors has contributed 471 lacs to state exchequer upto Nov 07

Proposed Activities

• Upgrade two ITIs.
• Initially, start activities at two villages.
• The thrust areas for TML interventions would be: Heath, Education and Livelihood • Interventions would be designed and implemented on the basis of needs identified and their prioritization

➢ Vendor park leverage into streamlining logistics ➢ Just-in-time deliveries to the plant ➢ Milk Runs for vendor park items
➢ Logistics responsibilities to Service Provider ➢ Vendor and Service Provider to manage inventories ➢ Vehicles usage for both in-bound and out-bound logistics

• Our local procurement from Uttarakhand will be Approx Rs 2250 Cr. at production level of 225,000 ACE vehicles.

• Only raw materials will be procured from outside Uttarakhand, as there are no suppliers exist for these items within the state.

Pune Line Shifting

50/day

Second Lines Operational

300/day

750/day

• State revenue from Tata Motors in 20 years ( 2007-2027) - Rs.3811 Crores • Average revenue per year spread over 20 years - Rs.191 Crores/yr

Paint Shop Operational

250/day

Plant Capacity

• No. of suppliers in Vendor Park: 60
• No. of items to be supplied from vendor...