Preview

Regency Plaza Case Study - Risk Management Process, Review of the Options

Powerful Essays
Open Document
Open Document
1263 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Regency Plaza Case Study - Risk Management Process, Review of the Options
3. Risk Management Process of the Regency Plaza Project

Regency Plaza is a mixed-use multi million US dollar project carrying quite high stakes. So the risks of it should be evaluated beforehand and managed well in order to make sure that the project wouldn’t over run budget or time and end with a successful result. Here we use the “Four Stage Risk Management Process” to evaluate the risk management happened in Regency Plaza project.

3.1 Risk Identification

Evaluation: how well the project was analyzed and source of the risk identified.

In the below table we will take a closer look at how well the risk was identified by Kris Hodgkins.

Description | Identified/Not | Constraints and Remarks | Size the layout of the floor plate | Identified | Complicated due to condominiums lying over the hotel rooms over a parking garage, which resulted in fixed column spacing and elevator core locations. | Number, mix and size of the condominium units | Identified | BRA approved maximum number of units to be built was 96, which Hodgkins chose opposing Farley, the marketing consultant’s idea of building spacious 72 units because of Hodgkins’ expected performance targets of $134.4 million gross sales and $26 million net profit out of the project. | Time Constraints | Not identified | Project was on a tight schedule as Kelly Constructions was convinced to cut off 03 month from the estimated 32 months of the project duration, with a promise of minimal changes to the original design. Eventually with the allowance of individual customization in the units, customers (i.e Millers) required drastic changes. | Manpower deficiency | Not identified | Neither RHG nor Hodgkins expect customers to require big alterations. But customers did, causing constant changes in the project design decreasing manpower and efficiency of the construction. | Extra Costs and Delays | Not identified | RHG allowed customers to modify their units as they please as long as they pay for

You May Also Find These Documents Helpful

  • Satisfactory Essays

    I know that we've previously discussed about the ability to separate the bottom floor into three 1,300 SF units (or some variation of it since the space was originally designed as three 1,300 SF units), if you were to build-out the first two 1,300 SF suites (to the left of the building)…

    • 270 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    opma 317

    • 395 Words
    • 5 Pages

    Since two weeks were added to task #3 - Obtaining Final Drawings and Building Permits, in order to complete the project in the original normal time with minimal costs, he would crash activities #2, and #1 since these activities would reduce the project by two weeks’ time at a minimal cost of $7000 as shown by our project crashing…

    • 395 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Week 2 Assignment

    • 320 Words
    • 2 Pages

    Before agreeing to the contract I would like to outline some risks that goes with this current project. I will address the concerns by showing you the qualitative and the quantitative risks…

    • 320 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Business development brings weights to a framework that might not have had room schedule-wise/experience to get intended up for expanded generation or administrations. New timings of payables/receivables may make monetary strain. Clients may feel underserved. Workers may be uneasy about all the progressions.…

    • 1477 Words
    • 5 Pages
    Powerful Essays
  • Better Essays

    Hillson, D & Simon, P. (2007). _Practical Project Risk Management: The ATOM Methodology_, Vienna, VA: Management Concepts, Inc.…

    • 1150 Words
    • 6 Pages
    Better Essays
  • Good Essays

    The following paper discusses the risk assessment process while explaining the framework, how each phase interrelates, and why the framework is so important in assisting with the risk assessment process. The paper will also discuss some of the innovations that have occurred over the last several years.…

    • 823 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Before developing a risk management plan an analysis of risk needs to be performed. This analysis should include all aspects of the project that may be part of an uncertain event or condition that may have a positive or negative effect on the project objectives and outcome. The overall goal is to work to address any type of risk before they become problematic. Analyzing and relaying the level and probability of the risk to the stakeholders, sponsors and project team can help in reducing mistakes that can be cause for project failures. Some common mistakes that can be overlooked when analyzing risk, is not understanding the benefits of a risk management plan, not allowing time for risk management, not properly identifying and assessing risk.…

    • 1195 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    Risk Management Plan

    • 2116 Words
    • 9 Pages

    The Project Management Team will need a proactive approach in the management of risks and related uncertainty. Management of risks for this project will follow a continuous risk management model, refined as the PLC develops. Involvement of support from the business, technical, executive, and external partners is crucial to having a viable risk management process. Tasks will be evaluated and identified for the mitigation of risks; uncertainty of organizational environmental factors will be included in the evaluation of impact and probability, as appropriate. This will ensure that tracking of progress, or lack thereof, occurs and necessary resources are identified for corrective/mitigating actions planned.…

    • 2116 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    BAE Case Study

    • 908 Words
    • 4 Pages

    Design and build at the same time: after BAE signed the contract in April 1992; the tight lead time only allows this automated baggage system to be designed while building. This practice brought great uncertainty to the project on both budget and process management.…

    • 908 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Investiong in Tufs

    • 524 Words
    • 3 Pages

    Another thing that went wrong in the project is the imbalance between its scope and the scheduling of the project as result of the management pressure to produce fast result regardless of what feasible. This problem would have avoided if the scheduling of the project take into account what was possible more than what was desired given the scheduling of the project.…

    • 524 Words
    • 3 Pages
    Good Essays
  • Best Essays

    Case Study Woody 2000

    • 2614 Words
    • 11 Pages

    In 1989, Due to a mini-boom in commercial construction, Bruce Sharpe, the company’s VP Sales and Estimating persuaded directors to expand their manufacturing business. There were two options for the company to go and there were either stay in the premises and expand or relocate to completely new and more modern facilities. Due to various personal views on this issue and polarization of opinions, Ron Carpenter, also called “Woody”, organized a meeting of directors and key personnel to come to a resolution regarding this matter. Based on the meeting, project concept was settled that the company will remain at the existing property but will expand the current facility by 25%. The premises will be modernized with new equipment, software and hardware and the directors’ premises will be renovated. The budget available for the changes was set at $17 million and a target date of 18 months.…

    • 2614 Words
    • 11 Pages
    Best Essays
  • Good Essays

    Dubai

    • 354 Words
    • 2 Pages

    The plans and design revisions caused many hotels and facilities to be completed behind schedule (almost 2 years)…

    • 354 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Conclusion

    • 694 Words
    • 3 Pages

    As previously discussed throughout our report Red Stone is currently facing many issues within their company, they are unable to deliver their finishing projects on time and remain on budget. A number of gaps have been identified; these gaps have been that cause of all the issues. By determining where the gaps are we are able to act efficiently and effectively to complete all projects successfully and on or before the due date of the project.…

    • 694 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Chapman, R. J. (1999), The Likelihood and Impact of Changes of Key Project Personnel on the Design Process, Construction Management and Economic 17:99-106.…

    • 18329 Words
    • 74 Pages
    Powerful Essays