The Electrohydraulic Turbine Controller
NPC DOC. NO. TAPP-3/64110/5526/DN/R0---------------------------------4 13300 00 486 ---REV. NO. 01

WRITE UP ON ELECTROHYDRAULIC TURBINE CONTROLLER ( EHTC )
Reference Documents: 1.MPL for Steam Turbine Doc. No. :- 41330000488(TAPP3/64110/5516/SCH) 2.Scheme for speed measurement turbine and generator Doc. No. :- 41330098204(TAPP3/64110/5512/DN) 3.Write up on LRR for MSCV and AEOR Doc. No. :- 41330000481(TAPP3/64110/5661/DN) 4.OGA of TG control desk 6610 – PL – 9 Doc. No. :- 06560000403(TAPP3/64100/5724/GA) 5.OGA of TG control desk 6610 – PL – 10 Doc. No. :- 06560000404(TAPP3/64100/5725/GA) 6.Turbine controller – CJJ01 – Cubicle & Rack assembly diagram Doc. No. :- 36560001746(TAPP3/64100/5728/GA) 7.Turbine controller – CJJ01 – Signal Flow Diagram(SFD) Doc. No. :- ED-031027-SF-S105(TAPP3/64100/5729/WD) 8.Turbine controller – CJJ01 – Functional Diagram(FCD) Doc. No. :- ED-031027-FC-S105(TAPP3/64100/5729/WD)
NPC. DOC. NO. TAPP3/64110/5526/DN/R0

01 00 REV

1.10.02 17.11.02 DATE

REVISED AS PER BS RANA NPC COMMENTS FIRST ISSUE REMARKS V. KUMAR WORKED

BS RANA BS RANA CHECKED A. ALI APPROVED

---------------------------------------------------------------------------------------------- Sheet no. 1 of 37 STE, BHEL-HARDWAR

NPC DOC. NO. TAPP-3/64110/5526/DN/R0---------------------------------4 13300 00 486 ---REV. NO. 01

Electro-hydraulic turbine controller INDEX 1 2 3 3.1 3.2 4 4.1 4.2 5 5.1 5.1.1 5.1.2 5.1.3 5.1.4 5.2 5.2.1 5.2.2 5.2.3 5.2.4 5.2.5 5.2.6 5.3 5.4 5.5 5.5.1 5.5.2 5.5.3 6 7 8 8.1 8.2 8.3 8.4 9 Introduction Turbine Control System Hydraulic Controller Hydraulic Amplifier and Electro hydraulic Converter Load Rejection Relay Electro hydraulic Controller Control Requirements for Electro hydraulic Controller Structure of Electro hydraulic Controller Control Loops of Electro hydraulic Controller Speed Control Loop Speed Set point Adjuster Speed Set point Control Actual Speed Derivation Speed Controller Lift Set point control loop Lift Set point

You May Also Find These Documents Helpful

  • Good Essays

    Turbins assginmen

    • 376 Words
    • 2 Pages

    8. Identify the safety features, which may be incorporated into an electro-hydraulic propulsion control system. Describe the function of each.…

    • 376 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Direct to Home

    • 1307 Words
    • 6 Pages

    and accessories. General layout of steam power plant. Different systems such as fuel handling system,…

    • 1307 Words
    • 6 Pages
    Satisfactory Essays
  • Powerful Essays

    Low Speed Wind Turbine

    • 12089 Words
    • 49 Pages

    | Myat Myat Doe, "Design and Manufacturing of Wind Turbine Blade," in Third GMSARN International Conference, Kunming, 2008.…

    • 12089 Words
    • 49 Pages
    Powerful Essays
  • Powerful Essays

    Research

    • 1835 Words
    • 8 Pages

    2. Kothare, Mayuresh, Bernard Mettler, Manfred Morari, P. Bendotti, and C. Falinower. "Level Control in the Steam Generator of a Nuclear Power Plant." IEEE Transactions on Control Systems Technology, 8.1 (2000): 55-69.…

    • 1835 Words
    • 8 Pages
    Powerful Essays
  • Good Essays

    C. Barron, M. Wildeman, B. Horstman, Project Associates Inc. (December 20, 2010), “IPL Petersburg Generating Station- System Description Document- Unit 4 Cooling Tower Control”…

    • 2538 Words
    • 11 Pages
    Good Essays
  • Powerful Essays

    Published by: © Robert Bosch GmbH, 2000 Postfach 30 02 20, D-70442 Stuttgart. Automotive Equipment Business Sector, Department for Automotive Services, Technical Publications (KH/PDI2). Editor-in-Chief: Dipl.-Ing. (FH) Horst Bauer. Editorial staff: Dipl.-Ing. Karl-Heinz Dietsche, Dipl.-Ing. (BA) Jürgen Crepin. Presentation: Dipl.-Ing. (FH) Ulrich Adler, Joachim Kaiser, Berthold Gauder, Leinfelden-Echterdingen. Translation: Peter Girling. Technical graphics: Bauer & Partner, Stuttgart. Unless otherwise stated, the above are all employees of Robert Bosch GmbH, Stuttgart. Reproduction, copying, or translation of this publication, including excerpts therefrom, is only to ensue with our previous written consent and with source credit. Illustrations, descriptions, schematic diagrams, and other data only serve for explanatory purposes and for presentation of the text. They cannot be used as the basis for design, installation, or scope of delivery. We assume no liability for conformity of the contents with national or local legal regulations. We are exempt from liability. We reserve the right to make changes at any time. Printed in Germany. Imprimé en Allemagne. 4th Edition, February 2000. English translation of the German edition dated: September 1998.…

    • 15212 Words
    • 61 Pages
    Powerful Essays
  • Good Essays

    and fire detection systems. The investigation of the turbine engine induction system focuses on the…

    • 902 Words
    • 6 Pages
    Good Essays
  • Powerful Essays

    Hydroelectric dams use water turbines in the same way to generate power. The turbines used in a hydroelectric plant look completely different from a steam turbine because water is so much denser (and slower moving) than steam, but it is the same principle.…

    • 2160 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Apple Plus Case Study

    • 778 Words
    • 4 Pages

    The converged flow sheet is exported to Aspen plus dynamics and the resultant graph are shown for condenser pressure control with corresponding duty, reflux level control to the corresponding reflux rate and composition control of TAEE in retentate for the side stream flow rate from RD to pervoporation unit.…

    • 778 Words
    • 4 Pages
    Good Essays
  • Good Essays

    The compressor main job is to prepare the air for combustion by adding energy in the form of pressure and heat. The compressor has two 2 subdivisions known as the low pressure compressor and the high pressure compressor. The low pressure compressor is connected to the fan and the low pressure turbine. The low pressure compressor pushes the air further back into the engine by the rows of spinning blades. As the air is…

    • 1008 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Thermal power plant

    • 19674 Words
    • 79 Pages

    V SAMMANFATTNING VI ACKNOWLEDGEMENT VII ORGANIZATION OF THE REPORT VIII 1 INTRODUCTION 1 2 BACKGROUND 3 2.1 2.2 Facilities in a Thermal Power Plant 3 Thermal Power Plant Operation 4 2.2.1 Fuel and Combustion 4 2.2.2 Rankine Cycle 4 Thermal Power Plant Control 6 2.3.1 Turbine Governor 7 Amagerværket Block 1 7 Frequency Control 9 2.5.1 Frequency Control in the ENTSO-E RG Continental Europe Power System 9 2.5.2 Frequency Control in the ENTSO-E RG Nordic Power System 10 2.5.3 Decentralized Frequency Control Action 11 2.5.4 Centralized Frequency Control Action 12 2.3 2.4 2.5 3 MODELING 14 3.1 Modeling and Simulation Software 3.1.1 Acausality 3.1.2 Differential-Algebraic Equations 3.1.3 The ObjectStab Library 3.1.4 The ThermoPower Library Connectors Synchronous Generator Steam Turbine Control Valves Boiler, Re-heater and Condenser Overall Steam Cycle Excitation System and Power System Stabilizer Turbine Governor Turbine-Generator Shaft Overall Model Boundary Conditions Simplifications within the Model 3.13.1 Steam Cycle 3.13.2 Governor 3.13.3 Valves and Valve Characteristics 3.13.4 Electric Grid 14 14 15 15 16 16 17 22 23 23 23 24 25 26 26 27 28 28 28 29 30 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12 3.13 ii 3.14 3.13.5 Turbine-Generator Shaft 3.13.6 Fuels Simulation and Visualization 31 31 31 4 SIMULATION AND RESULTS 32 4.1 4.2 4.3 Open-Loop Test 1 Open-Loop Test 2 Frequency Drop in a Real Case…

    • 19674 Words
    • 79 Pages
    Powerful Essays
  • Satisfactory Essays

    2014 Deep Research Report on Global and China Generator Control Unit Industry was professional and depth research report on Global and China Generator Control Unit industry. The report firstly introduced Generator Control Unit basic information included Generator Control Unit definition classification application industry chain structure industry overview; international market analysis, China domestic market analysis, Macroeconomic environment and economic situation analysis and influence, Generator Control Unit industry policy and plan, Generator Control Unit product specification, manufacturing process, product cost structure etc.…

    • 449 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    GTA believes that expanded government-sponsored research on improved gas turbine technology will lead to more American jobs going forward, increased American global competitiveness, and potential greenhouse gas reductions in the power sector.…

    • 13970 Words
    • 56 Pages
    Powerful Essays
  • Good Essays

    Hand lay-up combined with autoclave curing is a composite manufacturing technique which is still widely used in the aerospace industry. The main reasons are the confidence in this well established process and the high fibre volume fractions and low void contents which can be achieved due to the high pressures used in autoclaving. However, autoclaving mainly depends on the manual mould lay-up of prepreg material. Manual lay-up of high-curvature products is complicated and most of all a time consuming process. Consequently, the manufacturing costs are high and the process is unsuitable for large series. Many alternative processes are being developed among which automated tape laying, fibre placement and resin infusion are the most promising techniques.…

    • 598 Words
    • 3 Pages
    Good Essays
  • Better Essays

    PIC Mictrocontroller

    • 1373 Words
    • 6 Pages

    The data are periodically updated to the control center. Depending on the data that has been collected from the monitoring system, manipulations are done and the fault control system makes the decision of location and the type of fault that has occurred in the wind turbine. In case of any abnormal conditions, we can automatically shutdown the turbine for a period of time, till the parameters become normal. We use CAN Network to communicate between the Wind turbine and the control center . PIC Mictrocontroller is used for monitoring and control operations and it uses a master-slave configuration.The GSM Module is used to intimate the owner with an SMS when abnormal conditions occur and indicate the fault type.…

    • 1373 Words
    • 6 Pages
    Better Essays