Preview

Critical Chain Project Management

Satisfactory Essays
Open Document
Open Document
1051 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Critical Chain Project Management
Criticalchainprojectmanagement — Document Transcript
• 1. Critical Path Method and Critical Chain Project ManagementProject schedule plan is the main plan included in any Project Management Plan. Project schedule isresponsible for bringing project time, cost and quality under control. Project schedule links resources,tasks and time line together. Once a Project Manager has list of resources, work breakdown structure(WBS) and effort estimates, he is good to go for planning project schedule. Schedule networkanalysis helps Project Manager to prevent undesirable risks involved in the project. Critical PathMethod (CPM) and Critical Chain Project Management (CCPM) are key elements of schedule networkanalysis. In the following sections we will explore these elements in details to understand theirimportance in keeping project on schedule to get increase in ROI.Critical Path Method (CPM):The Critical Path Method (CPM) is a schedule network analysis technique. CPM was developed by theDuPont Corporation in 1957.Critical path determines the shortest time to complete the project and itis the longest duration path through a network of tasks. Critical tasks (activities) are tasks (activities)on the critical path.To understand CPM further lets first understand nature of the task. According to PMBOK everyscheduled task can be defined by the following four parameters. • Early Start (ES): Earliest possible point in time on which a task can start. • Early Finish (EF): Earliest possible point in time on which a task can finish. • Late Start (ES): Latest possible point in time on which a task can start. • Late Finish (EF): Latest possible point in time on which a task can finish.Early Start and finish dates are calculated by means of Forward Pass and Late Start and Late Finishdates are calculated by means of Backward Pass.Many Tasks have some amount of buffer added to them referred as Slack Time or Float. Float time isamount of time a task can slip before it delays project schedule.

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    First Cars Ltd

    • 1031 Words
    • 5 Pages

    Critical path analysis is a method that is used to plan out the many activities involved in a project to be able to find the most efficient way of complete it and how to complete it on time.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Introduction to Project Scheduling IX. The Critical Path Method (CPM) X. Program Evaluation and Review Technique (PERT) XI. Project “Crashing”…

    • 5350 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) 30 days b) Identify the critical path (6 points) BCDFH = 30 Days c) What is the slack time (float) for activity A? (1 points)…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Aib Problem Solution

    • 608 Words
    • 3 Pages

    Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project? (3 points)…

    • 608 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Pert Mustang

    • 1016 Words
    • 5 Pages

    A table containing the project activities, the time estimates and the precedence relationship will be prepared and a network diagram will be drawn to structure the immediate predecessor activities. The critical activities will be identified to indicate that the project can be completed within 45 working days.…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    4. The critical path for the project is found by calculating slack as per CPM as shown in the table below. The activities marked in green forms the critical path, I e.,…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Individual Project 2

    • 251 Words
    • 2 Pages

    Scheduling is essential to a project’s success. Forming a network activity with a visual depiction helps the team understand the relationships of tasks in a project. Two of the most common charts used in project management are the Gantt and PERT charts. The purpose of these charts is to assist with project scheduling and illustrate task dependencies. Another tool that can be used is the critical path method (CPM).…

    • 251 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Most likely time estimate is an estimate of the maximum time an activity will require.…

    • 6920 Words
    • 28 Pages
    Good Essays
  • Powerful Essays

    Project Management

    • 1126 Words
    • 4 Pages

    Project management is one of the most important and critical tool or technique, which defines the entire course of development of any kind of project.…

    • 1126 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    What is a critical path, and why is it important to project managers? How do you…

    • 702 Words
    • 3 Pages
    Good Essays