Comptia.Visualexams.JK0-017.v2013-12-03.by.Rog.402q
Number: JK0-017
Passing Score: 800
Time Limit: 120 min
File Version: 18.5

Exam Code: JK0-017
Exam Name: CompTIA E2C Project+ Certification Exam

Exam A
QUESTION 1
Which of the following are process groups in the project life cycle? (Select Three). A.
B.
C.
D.
E.
F.

Accepting
Mitigating
Avoiding
Initiating
Closing
Planning

Correct Answer: DEF
Section: (none)
Explanation
Explanation/Reference:
Explanation:
QUESTION 2
A project team is comfortable working as a group and has accepted all the project ground rules. They support each other to reach the project goals. Which of the following stages of team development is the project team demonstrating?

A.
B.
C.
D.

Storming
Performing
Conforming
Forming

Correct Answer: B
Section: (none)
Explanation
Explanation/Reference:
Explanation:
QUESTION 3
A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?
A.
B.
C.
D.

Work Breakdown Structure (WBS)
Cost management plan
Approved project charter
Project scope document

Correct Answer: B
Section: (none)
Explanation
Explanation/Reference:
Explanation:
QUESTION 4
The project charter is an output of which of the following project phases? A.
B.
C.
D.

Initiation
Planning
Execution
Closing

Correct Answer: A
Section: (none)
Explanation
Explanation/Reference:
Explanation:
QUESTION 5
All of the following are considered part of the risk management plan EXCEPT the risk: A.
B.
C.
D.

register.
matrix.
assessment.
baseline.

Correct Answer: D
Section: (none)
Explanation
Explanation/Reference:
Explanation:
QUESTION 6
Which of the following is true of fast tracking a schedule?
A.
B.
C.
D.

Project schedule critical path will change.
Project activities will be performed concurrently.
Project schedule is shortened by decreasing the project...