Preview

Bus Rapid Transport Tanzania (Tanroads)

Powerful Essays
Open Document
Open Document
2799 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Bus Rapid Transport Tanzania (Tanroads)
INTRODUCTION:
1. PROJECT LOCATION
The project is located in the city of Dar es Salaam. The Works for the first phase cover a length of 20.9 km starting at Kivukoni Ferry to Kimara Mwisho including sections of Kawawa Road from Magomeni to Morocco and Msimbazi Road from Fire to the intersection with Nyerere Road.
The Works will also include construction of 29 ordinary bus stations (bus stops) within roadway; 5 bus terminals and 2 bus depots along the project corridor as illustrated in Figure 1 below.

Figure 1: The Project Corridor – Phase 1

2. BACKGROUND
The Government of the United Republic of Tanzania has received credit from the International Development Association (IDA) towards the cost of Second Central Transport Corridor Project (CTCP 2). It is intended that part of the proceeds of this credit will be applied by TANROADS to eligible payments under the contracts for the Construction of Dar es Salaam Bus Rapid Transit (BRT) Infrastructure - Phase 1.

3. PAVEMENT
Roadways - From BRT design concept, cement concrete pavement (reinforced concrete) has been adopted for BRT lanes and flexible pavement (thick hot mixed asphalt) adopted in the mixed traffic lanes and will be laid directly on the existing stabilized base.
Walkways -The walkways will be on concrete (pre-cast), according to the chainage definitions, following a module of 10m. There will be a band of 10 x 25 cm stones.

4. ROAD CROSS-SECTIONS CHARACTERISTICS
The project corridor is divided into different seven stretches, according to road characteristics, and the typologies are defined in relation to this division. Typical Cross Section is as shown in Figure 2 below.

Figure 2: Typical Cross Section

5. CONSTRUCTION CONTRACTS
The construction project entails implementation of seven (7) Works Packages namely;
Package 1: Road Works;
Package 2: Ubungo Depot, Feeder Station and Up-Country Bus Station;
Package 3: Jangwani Depot;
Package 4: Kivukoni



References: www.tanroads.org: TANZANIA NATIONAL ROADS AGENCY/ BRT Ancellmi. A, 1st Ed, 2011, Principle of risk management for Tanzanian market.

You May Also Find These Documents Helpful

  • Good Essays

    The Project area is located approximately 40 km south of Wiluna in a direct line to the closest (eastern most) tenement, and approximately 55km from Wiluna to the western most tenement. Access to the project area via Wiluna appears to be good, serviced by a major (unsealed) public road between Wiluna and Leinster, and then via minor roads/ tracks (Figure 2).…

    • 407 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    of concrete slabs stacked on top of one another, fitted with iron bars big enough for a view of…

    • 550 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    Anzac Bridge

    • 342 Words
    • 2 Pages

    The materials that were used to construct this bridge consisted of prestressed concrete, steel casings, prestressed steel, reinforcing steel wire strands and polyethylene. It was built on each side of the land and was eventually connected together in the middle. It was constructed by using a formtraveller (a travelling formwork) and setting up the formwork before positioning and tensioning the cables. They then proceeded to place the reinforcement cement and pouring on the concrete. This was made in a cycle with each cycle being used to make…

    • 342 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    I-35W Highway Collapse

    • 2826 Words
    • 12 Pages

    construction aggregates (sand and gravel for making concrete) were delivered and positioned in the two…

    • 2826 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    Shoring Violations

    • 1052 Words
    • 5 Pages

    deep, thus according to the table 7.2 for unstable soil, the choice is either 4’ or 2’ for the uprights horizontal spacing (uprights may be a solid “sheeting” or spaced from 2’ to 8’ apart to prevent cave-ins), as well as cross braces is either 4’ or 2’ for screw jacks of 2” STD or timbers of (6” x 6”) to hold either horizontal or vertical shoring members in place. Refer to the side table 7.1 and assume the width between (6”-8”) for house line, since it was not reported in the result investigation. However, the minimum number of the horizontal cross braces, either screw jacks or timbers, required for each pair of uprights shall be determined by the number of 4-foot zones or segment into which the depth of the trench may be divided, yet in no case shall be less than two cross braces or jacks. Further, pre planning will reduce the chance of an accident and protect people nearby work site and maintenance operator from falling into the excavation, and it will protect them from possible exposure of atmospheric hazards in the excavation as well (such as leaking gas lines or storage tanks) and define how maintenance operator will get in and out of the excavation safely. An excavation with a depth of 4 ft. or more must have a means for entering and exiting such as a stairway, ladder, or ramp that has a non-slip surfaces employees’ safety may depend on how…

    • 1052 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Fafafaf

    • 10599 Words
    • 43 Pages

    This Chapter describes the general methods used to conduct a roadway inventory. The road inventory types are summarized graphically and by narrative. Process steps are then provided in detail. A basic data collection process is shown using the Active On the SHS inventory process to explain in detail how inventories are conducted. A Data Collection Matrix is provided in the Appendix to assist in tracking the required Features and Characteristics. It displays the data elements to be collected according to functional classification and road ownership.…

    • 10599 Words
    • 43 Pages
    Good Essays
  • Powerful Essays

    Bridge Design To Eurocode

    • 2056 Words
    • 13 Pages

    The objective of this paper is to compare the reliability level of prestressed concrete bridge girders…

    • 2056 Words
    • 13 Pages
    Powerful Essays
  • Powerful Essays

    Tribasa Toll Road Project

    • 2844 Words
    • 12 Pages

    5. What lessons do you take out of this financing? How could this technique be used to arrange financing for other highway and facility concession projects in the developing world? ………………………………10…

    • 2844 Words
    • 12 Pages
    Powerful Essays
  • Better Essays

    Pavement joints are vital to control pavement cracking and pavement movement. Without joints, most concrete pavements would be riddled with cracks within one or two years after placement. Water, ice, salt and loads would eventually cause differential settlement and premature pavement failures. These same effects may be caused by incorrectly placed or poorly designed pavement joints. The Technician is responsible for inspecting all joints to avoid any of the problems associated with joint failure. Forethought should be given to the design and placement of the pavement joints so that the end result is a properly functioning pavement system. Special care is given at intersecting approaches, turn lanes and crossovers so that the joints required at these locations will complement the joints placed in the mainline pavement. Since the mainline pavement is typically placed prior to any auxiliary pavement, the location of all joints is required to be known in advance of the initial pours. If the initial joint placement is correct, the extension of the same joint lines throughout any adjacent pavements is done. "Dead ending" of joints in the middle of adjacent slabs is avoided whenever possible to prevent the risk of reflective cracking. An example of a well planned joint design is shown in Figure 7-1. The joints in this diagram are continuous from edge of pavement to edge of pavement. Also, the joints in the mainline pavement are aligned to serve the joints in the adjoining pavements. The following pavement joints and related materials are discussed: 1) D-1 contraction joints 2) Longitudinal joints 3) Transverse construction joints 4) Terminal joints 5) Expansion joints 6) Retrofitted tie bars…

    • 2148 Words
    • 9 Pages
    Better Essays
  • Good Essays

    * In case of Stone Crushing Plant operating with CTE /CCA of the Board existing since long, which are located at a distance less then 200 meter from highways, the unit shall provide minimum 6 meter high compound wall or barrier of GI sheets along their plot periphery towards highway/road side. 2)…

    • 797 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Departments of Melaka Government 1. Office of Legal Counsel 2. Melaka State Department of Treasury (JKPNM) 3. Melaka Mufti Office 4. Melaka Islamic Religious Department (JAIM)…

    • 445 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    design management

    • 820 Words
    • 3 Pages

    According to Building (Planning) Regulations chapter 123F, there are two staircases in the new building in our design. The staircases have a clear height of not less than 2 m and width of not less than 900 mm. The staircases would be constructed with treads not less than 225 mm in width and with risers not exceeding 175 mm in height.…

    • 820 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Perpetual Pavement

    • 711 Words
    • 3 Pages

    Perpetual Pavements North Dakota Asphalt Conference Bismarck, ND April 6, 2010 Perpetual Pavement • Not a new concept –Full-Depth –Deep Strength –Mill & Fill MS-1 Perpetual Pavement Principles } 1.5 - 3” SMA, OGFC or Superpave 4” Zone to Of High 6” Compression Max Tensile Strain High Modulus Rut Resistant Material (Varies As Needed) Flexible Fatigue Resistant Material 3 - 4” Pavement Foundation Fatigue and Rutting HMA Repeated Bending Leads to Fatigue Cracking Base Subgrade Repeated Deformation Leads to Rutting Thinner pavements – High Strain » Minimize Tensile Strain with Pavement Thickness » Thin Asphalt Pavement =…

    • 711 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Road Design

    • 2693 Words
    • 11 Pages

    The principle factors that influence the choice of a design standard for a road are as follows:…

    • 2693 Words
    • 11 Pages
    Powerful Essays
  • Powerful Essays

    Surfaces and Guideways

    • 2036 Words
    • 9 Pages

    Surfaces and Guideways Introduction Basic Components Structural Design of Pavements Portland Cement Concrete Design Asphalt Concrete Pavement Design THE END Thank you Surface - the term surface refers to Roadway pavement which includes Portland Cement concrete, treated soil (gravel or other aggregate materials) and Asphalt concrete Guideway - A track along which Automated Transit Vehicles are guided. Guideway include monorails, concrete guideway for rubber tired vehicles and conventional duo-rail steel-on-steel railroad track Surface Course - also known as the pavement. It is the material laid over the Base Course consisting of Asphalt Concrete or Portland Cement Concrete. Base Course - is the material laid on top of the sub grade consisting of crushed stone or gravel.They may be stabilized by means of lime, Portland Cement, or Asphalt Sub-grade or Sub-base - is the earth beneath the road, properly arranged and graded, compacted and stabilized. It is defined as the "supporting structure on which the pavement surface and its special under-courses rest" The design of pavements involves determination of the types and thickness of the various layers of material making up the pavement. The goal is to specify the most economical pavement which will perform satisfactorily over a designed life so that comparisons between the two require Total Life Cycle Cost Analysis The most common design for Portland cement concrete pavement is the AASHTO rigid pavement design method. Like AASHTO flexible pavement procedure, this method relates to soil conditions, traffic characteristics and pavement design characteristics to a performance index value expected at the end of the pavement life. Highway Pavements Components Life Cycle Analysis for Concrete Life Cycle Cost Analysis for Asphalt Result: Total Life Cycle of Concrete pavement VS Asphalt Concrete Design Considerations Portland Cement Vs Asphalt Concrete Portland Cement Concrete Portland Cement concrete pavement are considered to…

    • 2036 Words
    • 9 Pages
    Powerful Essays