Preview

Bae Assignment

Powerful Essays
Open Document
Open Document
4458 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Bae Assignment
BAE Business Case Study

Submitted by:

Susan Pacheco April 17, 2013
Table of Contents

Part 1: Executive Summary 3 Part 2: Main Issue 4 Part 3: Systemic Issues 4 Leadership & Project Management issues 4 Political Pressure to Fast-Track Project 5 Design Issues 5 Communication Breakdowns 6 City Involvement (Delays) 6 BAE Conditions on Contract Signing (April 1992) 6 Part 4: Environmental & Root cause Analysis 7 Qualitative Analysis: 7 Project Management 7 People (Unqualified): 8 Build-Design 8 Economic & Political Considerations 8 Success with United Airlines 9 Part 5: Alternatives and/or Options: 9 Alternative A 9 Alternative B 11 Part 6: Recommendations and Implementation 11 Recommendation: 11 Recommendations Implementation Plan: 12 Part 7: Monitor and Control: 13 Part 8: Conclusion: 13 Part 9: References, Exhibits and Appendixes 13

Part 1: Executive Summary
In order to address the immediate issue of the letter received by the City Mayor holding us responsible for the delay of the new baggage system by charging BAE a penalty of $12k/day backdated to October 29, 1993 and also requesting a charge back for the $50M tug-and-cart baggage backup system, immediate action and priority needs to be given to address this accusation.

A prompt analysis of our project plan and missed milestones with reasons and factual data is critical in defending our position. We need to prove where certain milestones outside our control were missed and the domino effect it created and where dependencies to our commitments were broken and by whom. There were many points at which we voiced our concerns on the project delays and access issues that further hindered our ability to perform but no one took responsibility or acknowledged the delay. In addition, the Build-Design approach has in itself created many hurdles and time delays outside our control as well as created



References: Exhibits and Appendixes Appendix 1 - New Project Management Team Structure Appendix 2 - RACI Matrix example (for initial phase) of new structure

You May Also Find These Documents Helpful

  • Better Essays

    Mgmt404 Project Plan

    • 1494 Words
    • 6 Pages

    I have made a list of all areas that might cause project delays or failure with their respective outcomes (see numerical list below). The five risks I have chosen…

    • 1494 Words
    • 6 Pages
    Better Essays
  • Good Essays

    Appointing people who believe and committed to the project into leadership position to lead the team and make time for communication from team and other leadership (Wager, Glaser, 2009). Another issue that was an indicator of failure to this project was the requirements analysis was rushed several key workflow and system integration issues were missed. To minimize this indicator a thorough requirement analysis is done to ensure that all workflow analysis to support the change in workflow and the system requirements analysis to ensure the requirements needed for the system to work are aligned with the strategic goals of the organization (Wager, Glaser, 2009). Budget cut to the project was a big indicator the would lead to failure of this project because in the status review meeting it was presented that the project was on scope, on schedule, and on budget led to leadership taking resources from the CPOE project. It is important the present a true picture…

    • 762 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    • Key project deliverables • High level milestones • High level cost estimates • Identify stakeholders • General project approach • Problem statement • High level assumptions • High level constraints • High level risks • Project objectives 1.5 Outline the process groups of the project life cycle • Initiating/Pre-Project Setup • Planning •…

    • 124851 Words
    • 663 Pages
    Powerful Essays
  • Satisfactory Essays

    Law 531 Memorandum

    • 981 Words
    • 4 Pages

    This memo is in response to the dispute over the contract between Span Systems and Citizen-Schwarz AG (C-S). Management is taking the necessary steps in resolving the issues C-S is reporting of low quality deliverables and schedule delays. C-S is threatening rescission of their contract and demand immediate transfer of all unfinished codes (University of Phoenix, 2002, Legal Environment of Business: Contract Creation and Management, Law 531). C-S must prove a material breach is occurring and give adequate notice to Span Systems to issue a rescission (Cheeseman, 2010). Span Systems and C-S signed a one-year contract worth $6 million dollars that has five clauses for breach of contract and a project structure clause. This memo will identify what management is doing to avoid legal risks, minimize liabilities, and benefit from opportunities presented to make this contract successful.…

    • 981 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    There are many reasons why plans fail to succeed. In discussing our answers to this question, Team C felt that in the list of reasons on why plans fail, poor planning would be on top of the list. When there are no attempts in pushing forward with already made plans, the project is bound to fail. Another reason why project plans fail is because the data in which plans are based are insufficient making it difficult for project managers to take control and give out orders. With insufficient data, the project’s scope would seize to exist. Along with not have an identified scope, the team would not know the ultimate objective of the project, and because of this, people will work towards different directions rather than one common goal. It is important that the reasons on the list are taken care of or prevented. This can be done during the defining and sequencing process.…

    • 335 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Six Sigma Tollgate Review

    • 1472 Words
    • 6 Pages

    2. What is the business reason(s) for completing this project? How are they compelling for the improvement team and the management team? How are they tied to strategy?…

    • 1472 Words
    • 6 Pages
    Satisfactory Essays
  • Satisfactory Essays

    “Very few projects are ever completed according to the original plan. The changes to the plan result from either increased knowledge, a need for competitiveness, or changing customer/consumer tastes. Once the changes are made, there is almost always an accompanying increase in the budget and/or elongation of the schedule.”(Kerzner, p.949, 2009).…

    • 317 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Tacoma Narrows Bridge

    • 316 Words
    • 2 Pages

    In the Tacoma narrows bridge project the project planning was fairly planned, developers and Engineers did not coordinate proper strategies and a scope management for this project, even before its inauguration and opening, the bridge exhibited strange characteristics that were noticeable right away. I think the only appropriate project planning was the budget that was obtains by the federal government’s public Administration. The conceptual development was a disaster because they did not ask the necessary question and research what or when something would happen before and after the construction of this project. In the management process when even before the bridge was open they did not took the time to investigate the strange characteristic that the bridge was developing, they did not respond properly and come up with a plan to investigate and find out why the bridge was developing this strange symptoms.…

    • 316 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Matrix Template

    • 756 Words
    • 4 Pages

    GenRays Matrix Template Project Management Knowledge Areas|Recommended Tool(s)|Justification for Tool| Project Integration Management | Expert Judgment|-PM Plan is Formal, single document, approved (becomes officially the project plan. It defines how project is executed and controlled. Scope, schedule, and Cost, Change, and Configuration Management plans are created in this process and are part of the PM plan- Scope Management plan is developed here as well.| Project Scope Management | -Interviews -Focus Groups -Facilitated Workshops -Group Creativity Technique -Group decision making techniques -Questionnaires and Surveys -Observation(Job Shadowing) -Prototypes| Facilitated Workshops examples: JAD and Quality Function Deployment Group Creativity Technique examples: -Brainstorming -Nominal Group Technique: enhances brainstorming with voting process -Delphi Technique-Idea and Mind Mapping -Affinity Diagram: large numbers of ideas to be sorted into groups Group Decision making technique -Unanimity: everyone agrees on single course of action -Majority: support from more than 50% of the members of the group -Plurality: the largest block in a group decides even if a majority is not achieved Dictatorship: one individual makes the decision for the group| Project Time Management| -Bottom- up Estimating -Expert Judgment -Alternative Analysis -Published Est. Data -PM Software| Bottom-up estimating: Breaking down complex activities into pieces. -Published Est. Data: Published data as books and journals -Alte. Analysis: means considering several different options for how to assign resources| Project Cost Management | -Analogous Estimating -Bottom-up Estimating -Parametric Estimating -Cost of Quality -Vendor Bid Analysis -Reserve Analysis -Expert Judgment -Three-point estimates -PM estimating software| -Cost of quality: Cost that is incurred to achieve required quality -Rough order of magnitude: As the project moves, estimates should become more accurate -Direct Costs: Costs…

    • 756 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Why are we doing this project? Describe the framework of the project and the justification for doing it. Are there any tactical, outfitted improvement or dogmatic reasons why this project must be done? This is the kind of information that tells stakeholders the why of the project and engages people to step up and deliver.…

    • 539 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    This paper will examine Ericksen’s project strategy, which initially start off with two parallel paths: one for the boat design and the other for crew training. As the project is laid out and the cost accounted, Bjorn and his team analyze the critical path of the project and determine ways to meet the time constraint on the project. Taking advantage of crash time, Ericksen’s team develops resources to get the project complete, maintain performance, at the cost of budget overruns. However, the overruns are tolerable based on the priority matrix chosen by this team. Lastly, implementation of project closure is discussed as the program makes a normal transition from a full fledge project to completion upon delivery.…

    • 3031 Words
    • 13 Pages
    Powerful Essays
  • Satisfactory Essays

    Annotated Bibliography

    • 680 Words
    • 3 Pages

    Assaf, S.A. and Al-Hejji, S. (2006) Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-57.…

    • 680 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    The information that provided in part 1 alone is not enough to allow the project team in defining any milestones of the project. Actually the hierarchical breakdown of the activity can be designed out of this information but for defining milestones; the project team may well require the following:…

    • 576 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Needless to say that did not happen and the project becomes plagued by internal rivalry, poor leadership, poor coordination among other things that ultimately leads to a failure. Our mission is in short to explain in relevant terms why we think this happened and finally describe how it could be prevented to happen again.…

    • 5421 Words
    • 22 Pages
    Powerful Essays
  • Good Essays

    Overall decision making and schedule completion were the successes of this project. Decision making based on project management development, resource allocation, communication styles and team dynamics were highlights of the ultimate scores. The project was completed after the optimum deadline, although not totally out of the window of opportunity.…

    • 1509 Words
    • 7 Pages
    Good Essays

Related Topics