Assignment #5: Scheduling at Red, White and Blue Fireworks Company

Only available on StudyMode
  • Download(s) : 317
  • Published : April 8, 2012
Open Document
Text Preview
Develop a Staffing plan for RWBFC in Accordance with the Constraints Stated in the Case
According to Reid and Sanders (2010), in the case Scheduling at Red, White, and Blue Fireworks Company, the production manager Joan Bennett decided to change the work schedule for manufacturer employees. She wanted to develop a schedule to operate ten hour each day, seven days each week. The schedule is developed in this assignment based on information given in the case. The results are shown in Table 1 and Table 2 Table 1

Minimum Number of Employees Needed and Consecutive Days
Days of the Week Three Consecutive Days M T WThFSaSu MTW TWTh WThF ThFSa FSaSu 202020202020206060606060

191919192020205757585960
191919181919195756565657
181819181918185555565555
171718171918185252545455
171718161817175251525152
161618161816165050525050
151517151816164747504950
151517141715154746484647
141517141614144646474444
131416131614144343454344
131416121513134342434041
121315121513124040424040
111214111513123737403940
111214101412113736383637
101113101412103434373636
1011139131193433353333
910128131193130333233
810128121083030323030
79117121082727302930
7911611972726282627
6911610862626272424
5810510862323252324
581049752322232021
47949742020222020
36839741717201920
36828631716181617
25728621414171616
25717511413151313
14607511110131213
04606401010121010
046053010101188
0350530881088
035042088966
024042066866
013042044766
013031044644
013020044522
002020022422
002010022311
001010011211
001000011100
000000000000

Table 2
Schedule for Employees
Employee M T W Th F Sa Su 11111000
20001111
31100011
41111000
50001111
61100011
71111000
80001111
91000111
101111000
110001111
121110001
131111000
140001111
151110001
160001111
171111000
181000111
191111000
200001111
211111000
221111000
230001111
241110001
251111000
260001111
271110001
280001111
291111000
301000111
310001111
321111000
330001111
341111000
351111001
360001111
370001111
381111000
390001111
401111000
410001111
421111000
431110001

Discuss the Method Used in Developing the Staffing Plan
The schedule is developed using Tibrewala, Phillippe, and Brown technique. The schedule enables RWBFC to operate seven days a week and give each employee three consecutive days off. Tibrewala, Phillippe, and Brown technique is developed in the following steps.

The first step is to identify the number of employees needed for each day for the week. According to the case study the manufacturing process requires a minimum of 20 employees (Reid & Sanders, 2010, p.587). Therefore, the number of employees needed for each day is 20. This number for each day is shown in the first row of Table 1 on the left side.

The second step is to calculate the number of employees needed for each three consecutive days during the week based on minimum number of employees needed each day. This is calculated as follows. The consecutive days are: Monday, Tuesday, Wednesday (MTW), and...