Aib Problem Solution

Topics: Critical path method, Network diagram, Project management Pages: 3 (608 words) Published: January 24, 2012
Aib Homework Wk3
Problem 1
The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors
A 5 Days ---
B 6 Days ---
C 8 Days ---
D 4 Days A, B
E 3 Days C
F 5 Days D
G 5 Days E, F
H 9 Days D
I 12 Days G
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions: (15 points total)
a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT
b) What is the Critical Path of the Project? (3 points)
B,D,F,G,I -> CORRECT
2,4,6,7,9
c) What is the ES for Activity D? (2 points)
6 -> Correct
d) What is the LS for Activity G? (2 points)
15
e) What is the EF for Activity B? (2 points)
6 -> Correct
f) What is the LF for Activity H? (2 points)
32 -> Correct
g) What is the float for Activity I? (2 points)
0
Problem 2
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors
A 6 weeks ---
B 6 weeks ---
C 5 weeks B
D 4 weeks A, C
E 5 weeks B
F 7 weeks D, E, G
G 4 weeks B
H 8 weeks F
I 5 weeks G
J 3 week I
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions: (15 points total)
a) Calculate the scheduled completion time. (3 points)
30
b) Identify the critical path (4 points)
B,C,D,F,H
c) What is the slack time (float) for activity A? (2 points) 5
d) What is the slack time (float) for activity D? (2 points) 0
e) What is the slack time (float) for activity E? (2 points)4 f) What is the slack time (float) for activity G? (2 points) 5
Problem 3
The following data were obtained from a project to design a new software package: Activity Duration Predecessors
A 5 Days ---
B 8 Days ---
C 6 Days A
D 4 Days C, B
E 5 Days A
F 4 Days D, E, G
G 4 Days B, C
H 3 Day G
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions: (15 points total)
e) Calculate the scheduled completion time. (3 points) 19...
Continue Reading

Please join StudyMode to read the full document

You May Also Find These Documents Helpful

  • AIB Problem Essay
  • Aib Problem Essay
  • Aib Problems
  • Week 3 Aib Problems Essay
  • Essay on Week 3 Homework Aib Problems
  • problem solution Essay
  • Problem solution Essay
  • Problem Solution Essay

Become a StudyMode Member

Sign Up - It's Free