Solutions to Week 4 Homework (Crashing and Ev)
PROBLEM 1
Use the network diagram below and the additional information provided to answer the corresponding questions. [15 points]

a) The crash cost per day per activity [10 points]

Activity A: Crash Cost = ($800 - $300) / (7-3) = $500 / 4 = $125 per day

Activity B: Crash Cost = ($350 - $250) / (3-1) = $100 / 2 = $50 per day

Activity C: Crash Cost = ($900 - $400) / (6-4) = $500 / 2 = $250 per day

Activity D: Crash Cost = ($500 - $200) / (3-2) = $300 / 1 = $300 per day

Activity E: Crash Cost = ($550 - $300) / (2-1) = $250 / 1 = $250 per day

b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? [3 points]

The diagram shows two paths: ABE and CDE. Based on normal duration estimates, ABE will take 12 days to complete and CDE will take 11 days. Therefore the earliest the project can be completed (on critical path ABE) is 12 days.

The total project cost based on normal time is: $300 + $250 + $400 + $200 + $300 = $1450

Activity on the critical path that can be accelerated at the lowest cost per day is Activity B @ $50.

If Activity B is crashed 1 day (from 3 days to 2 days), the total project duration = 11 days and project cost = $1500 (i.e. $1450 + $50)

There are now two critical paths ABE and CDE; both with 11 days. The activity with lowest cost per day on the CDE path is Activity C or E; both $250. Since Activity E is however on both paths, we should crash it by the one day available bringing the project completion to 10 days. This increases the total project cost to:

$1500 + $250 = $1750

This beats the alternative of crashing Activity C on the CDE path and Activity B on the ABE path. By crashing Activity B for 1 day

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Week 3 Aib Problems

    • 895 Words
    • 4 Pages

    The most critical path is B – D – F – G – I: 32 Days…

    • 895 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    PROJ 586 W4 Homework

    • 588 Words
    • 3 Pages

    b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities? [3 points]…

    • 588 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Pm 586 Week 4

    • 686 Words
    • 3 Pages

    b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities? [3 points]…

    • 686 Words
    • 3 Pages
    Good Essays
  • Good Essays

    The activity-based costing cost per unit of Product A is closest to: (Points : 4)…

    • 831 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    chap 3 quiz 2

    • 511 Words
    • 5 Pages

    Activity rate = Estimated overhead cost ÷ Expected activity = $234,900 ÷ 9,000 setups = $26.10 per setup…

    • 511 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    In this part of the exercise the activity-based overhead is configured for every activity cost item. There are four activities which are mentioned in the exercise; market analysis, product design, product development, and prototype testing. Each have an annual cost; market analysis-annual cost is $1,050,000, product design annual cost is-$2,350,000, product development annual cost is $3,600,000, and prototype testing annual cost is $1,400,000 (John Wiley & Sons, Inc. 2011) . Each have estimated drivers; Market analysis estimated drivers is 15,000 hours, product design estimated drivers is 2,500 designs, product development estimated drivers is 90…

    • 668 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Greendale Stadium Case

    • 1281 Words
    • 6 Pages

    There are two critical paths that share the same beginning and end. They differ from only two separate activities:…

    • 1281 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    Educare Ltd Project Report

    • 3316 Words
    • 14 Pages

    Next is Critical Path (CP). It identifies the activities which has no room for error, or zero Slack. It is identified by linking all the activities with zero TF. For this project, it is as follows:…

    • 3316 Words
    • 14 Pages
    Powerful Essays
  • Satisfactory Essays

    Space Constructors

    • 570 Words
    • 3 Pages

    From the excel above, we can find that Path AF and BG is ten weeks. And the path CEG is 8 weeks. So just need to control the path ADG within 10 weeks. So activity A and D are to use original time, and D use additional cost time. SO…

    • 570 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Cost Questions

    • 377 Words
    • 2 Pages

    2) Workers paid $15.00 per hour with an overhead charge of 1.45 and a personal time allowance of 1.15, have what total direct labor cost for an 8-hour work day?…

    • 377 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    a) What is the probability that the project will be completed between 35 and 45 days?…

    • 5665 Words
    • 87 Pages
    Satisfactory Essays
  • Good Essays

    minimize total costs and activity days. The model was implemented successfully with savings over $100 million…

    • 312 Words
    • 1 Page
    Good Essays
  • Good Essays

    Project Mangement

    • 2339 Words
    • 10 Pages

    Given above assumption, CPM analysis seeks to examine the consequences of crashing on total cost. Since the behavior of indirect project cost is well defined, the bulk of CPM analysis is concerned with the relationship between total direct cost and project duration. The procedure used in this is: 1. Obtain the critical path in normal network. Determine the project duration and direct cost.2. Examine the cost time slop of activities on the critical path obtained and crash the activity which has the least slope.3.Constrct the new critical path crashing as per step 3. Determine the project duration and cost.4.Repeat steps 2 and 3 till activities on the critical path are crashed.…

    • 2339 Words
    • 10 Pages
    Good Essays
  • Powerful Essays

    Student

    • 1558 Words
    • 7 Pages

    The Assignment Problem and the Hungarian Method 1 Example 1: You work as a sales manager for a toy manufacturer, and you currently have three salespeople on the road meeting buyers. Your salespeople are in Austin, TX; Boston, MA; and Chicago, IL. You want them to fly to three other cities: Denver, CO; Edmonton, Alberta; and Fargo, ND. The table below shows the cost of airplane tickets in dollars between these cities. From \ To Denver…

    • 1558 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Pert

    • 292 Words
    • 2 Pages

    Task 1,2,4,5,6 are critical path. Task 3 is not in critical path , If task 3 delayed for 2 days will be no effect in the critical path.…

    • 292 Words
    • 2 Pages
    Satisfactory Essays