Preview

Project management

Good Essays
Open Document
Open Document
298 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project management
2.2) Determination of Timing of Activities and Total Float

A network diagram is the display of the activities and the relationships among those activities that are logically arranged. To determine the timing of activities, we need to use the activity-on-node (AON) method, also known as the Precedence Diagram Method (PDM). To understand this better, we first need to define the following:
(EST) Early start Time is the earliest time the activity can begin.
(LST) Late start Time is the latest time the activity can begin and still allow the project to be completed on time.
(EFT) Early finish Time is the earliest time the activity can end.
(LFT) Late finish Time is the latest time the activity can end and still allow the project to be completed on time

Diagram A: Activity-on-the-node diagram

Timing of activities in the network diagram is determined by the following calculations for each node as shown in diagram A. Using the forward pass method, the EST + Duration = EFT. Similarly, using the backward pass method, the LFT- Duration = LST. To determine if an activity is critical or not, the EST and LST or the EFT and LFT has to be equal.

The difference between LST and EST or LFT and EFT is called Float or Slack. In conclusion, Total Float, TF = LST-EST = LFT-EFT As defined by Burke (2003) “Float is the measure of an activity’s flexibility, quantifying how many working days the activity can be delayed before it will extend the completion date of the project, or any target finish dates.”
Another words, float is the amount of time an activity can slip without any delay in the project finish date. Free float is the amount of time an activity can slip without any delay in the early start of any activity that immediately follows.

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19)…

    • 552 Words
    • 5 Pages
    Satisfactory Essays
  • Powerful Essays

    • The project schedule is liberal in respect to time for completion of each phase, because not keeping up with the…

    • 1244 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project.…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints?…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    Pt2520 Sow

    • 79 Words
    • 1 Page

    Time allotted: Deliverable: Total time between beginning and end of project:…

    • 79 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Use the network diagram below and the additional information provided to answer the corresponding questions. [13 points]…

    • 668 Words
    • 20 Pages
    Satisfactory Essays
  • Satisfactory Essays

    PROJ 586 W4 Homework

    • 588 Words
    • 3 Pages

    Use the network diagram below and the additional information provided to answer the corresponding questions. [13 points]…

    • 588 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project?…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Aib Problem Solution

    • 608 Words
    • 3 Pages

    Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project? (3 points)…

    • 608 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    TPV1 Sample Questions

    • 453 Words
    • 3 Pages

    Which of the following network diagram methods uses arrows to represent activities, but is limited because it can only represent Finish-to-Start dependencies?…

    • 453 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Supporting Activity

    • 653 Words
    • 3 Pages

    Start-to-Finish: Rarely used but is useful when developing a schedule backwards from a fixed end date.…

    • 653 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Individual Project 2

    • 251 Words
    • 2 Pages

    Scheduling is essential to a project’s success. Forming a network activity with a visual depiction helps the team understand the relationships of tasks in a project. Two of the most common charts used in project management are the Gantt and PERT charts. The purpose of these charts is to assist with project scheduling and illustrate task dependencies. Another tool that can be used is the critical path method (CPM).…

    • 251 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    D.U Singer Hospital

    • 5200 Words
    • 21 Pages

    activity begins at its early start, regardless of resource constraints. ..................................... 8 vi. A period labor requirements table for each group and the project as a whole. Include…

    • 5200 Words
    • 21 Pages
    Good Essays