Business Decision Models Adm2303 Assignment 6

Only available on StudyMode
  • Download(s) : 57
  • Published : January 24, 2013
Open Document
Text Preview
Assignment 6

Business Decision Models

ADM 2302, Section D
Professor Daniel E. Lane

Wednesday, December 5, 2012

Prepared by:

Personal Ethics Agreement Concerning University Assignments
Individual Assignment
By signing this Statement, I am attesting to the fact that I have reviewed the entirety of my attached work and that I have applied all the appropriate rules of quotation and referencing in use at the Telfer School of Management at the University of Ottawa, as well as adhered to the fraud policies outlined in the Academic Regulations in the University’s Undergraduate Studies Calendar. I further attest that I have knowledge of and have respected the “Beware of Plagiarism” brochure found on the Telfer School of Management’s doc-depot site

______________________________
SignatureDate

________________________________ ______________ Last Name (print), First Name (print) Student Number

Question 7:

H
D
C
A
B

START
E
F
G

END

K
L
M
I
J

EST: Earliest Starting Time
LST: Latest Starting Time
LFT: Earliest Finishing Time
LFT: Latest Finishing Time

Activity| EST| EFT| LST| LFT| Slack| Critical Activity| Start| 0| 0| 0| 0| 0| |
A| 0| 4| 7| 11| 7| No|
B| 4| 13| 12| 21| 8| No|
C| 13| 18| 21| 26| 8| No|
D| 18| 20| 26| 28| 8| No|
E| 4| 12| 11| 19| 7| No|
F| 12| 19| 19| 26| 7| No|
G| 19| 21| 26| 28| 7| No|
H| 21| 24| 28| 31| 7| No|
I| 0| 10| 0| 10| 0| Yes|
J| 10| 16| 10| 16| 0| Yes|
K| 16| 20| 16| 20| 0| Yes|
L| 20| 25| 20| 25| 0| Yes|
M| 25| 31| 25| 31| 0| Yes|
Finish| 31| 31| 31| 31| 0| |

Critical Points: I, J, K, L, M
Expected Duration is 31 days
Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.

Question 10:
a) Sequence 1: Choose topic,...